| 1 | Dismantling exiting plaster including disposal of refuse as directed by the engineer in charge with in a distance of 60 metre (SINo.706) |
| 2 | R.C.C. work with Cement, approved coarse sand and 2cm gauge approved stone grit in proportion of 1:2:4 in Sunshed, door and window level lintel and plinth bend all cost of complete. S.I.No.283 |
| 3 | Providing an laying \"brick coba\" 12mm thick laid with M-150 class brick bat coba 7.50 cm thick with gap of 15mm to each other, over 20mm thick base of cement mortar 1:4 cement and coarse sand mixed with water proofing compound spreading cement slurry mixed with aerelic cement concrete water proofing compound filled gaps of coba & top of coba mortar mixed with water proofing compound in 1:4 cement and coarse sand mortar finished smooth & top mashed false square 30cm x cm and side wall parapet shall be mono tythic plaster wall upto 30 cm higher and junction and corner shall be rounded by brick ballast cement and coarse sand masonary Coba with top finished plaster mixed with acetic water proofing compound @2% by weight & including S/o all material, labour, T&P etc complete for proper comletion of work. SINo.Ch-11 NI-2 |
| 4 | Mild steel or iron work in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of all steel and wastage and over lapping & hooks. S.I.No. 504 |
| 5 | 12 m.m. thick Plaster with Cement mortar consisting of one part of cement and 3 part of c/sand of 2.25 FM on brick work including supply of all material, labour, T&P etcAdd For Extra Labour to all item of plaster if done in ceiling.S.I No 583+587 |
| 6 | 12 m.m. thick Plaster with Cement mortar consisting of one part of cement and 4 part of f/sand of 2.25 FM on brick work including supply of all material, labour, T&P etc.S.I No 584 |
| 7 | Finishing walls with tow coats of water proof cement paint / weather coat of approved quality on previously old treated surface with this paint to give an even shade including supply of all material labour T&P etc. required for prepation of the work, CH.No.15 New Item 8+9+10 |
| 8 | Distemperiing oil bound 2 coat of approv. brand & required shade on undecorated wall surface to with an even shade over and including a primer coat with cement primer of approved brand after throughly brushing the surface free from mortar droppings and other foreign matter and also including preparing the surface even and smooth all cost of complete. S.I. 649 & 650 |
| 9 | Providing wall putty on new surface with approvel quality material of Berger/J.K./Birla or similar make 2 coats. As per SI No-Ch-15, NI- 11 |
| 10 | Supply and fixing 6 to 8 mm thick ivory or light shades vitrefied tiles 600x600 mm size in flooring and skirting with 1:3 approved cement and coarse sand mortar finished within its cement colour slurry,jointing and poliahed of approvedquality complete including supply of all materials labour, tool s and plants atc required for proper completion of work. as per direction of Engineer-in-charge. as per SI NO -CH-14,N.I.-5 |
| 11 | Painting two coats over priming coat on wood or steel with superior synthetic enamel paint to give an even shade and finished and including cleaning the surface all dust and other foreign matter including cost matter and scoured with wire brushes all cost of complete. Chap. 15 1(a),2 & 4 (c) |
| 12 | Dismantling sundried brick work including staking of dismantied materials with in 60 m distance as directed by the Engineer-in- Charge.As per SI- 691 |
| 13 | Excavation in foundation in ordinary soil including lift upto 1.5 mts and lead upto 30 mts &including filling ,watering and ramming of excavated earth in to the trenches or into the space between the sides of foundations. S.I.-251 |
| 14 | Concrete with 4 cm. gauge brick ballast, fine sand of 1.25 F.M. and cement in proportion of 8:4:1 in foundations including supply of all materials, labour and T & P etc. required for proper completion of work. S.I.-275 |
| 15 | M 150 brick work in 1 :4 cement and C. sand of 2.25 F.M. mortar in foundation and plinth including supply of all materials, labour and T & P etc. required for proper completion of work.S.I. No-305 |
| 16 | M 150 brick work in 1 :4 cement and C. sand of 2.25 F.M. mortar in super structure and plinth including supply of all materials, labour and T & P etc. required for proper completion of work.S.I. No-305+309+310 |
| 17 | R.C.C Work with cement approved coarse sand and 2 cm gauge approved stone grit in proportion of 1:1.5:3 in foundation and footing excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.GI Binding wire and including necessary centering and shuttering etc. and supply of all materials, labour and T&P etc. required for proper completion of work. Binding wire of supplied by the contractor free of cost. As per S.I. No-283(a) |
| 18 | R.C.C Work with cement approved coarse sand and 2 cm gauge approved stone grit in proportion of 1:1.5:3 in column excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.GI Binding wire and including necessary centering and shuttering etc. and supply of all materials, labour and T&P etc. required for proper completion of work. Binding wire of supplied by the contractor free of cost. As per S.I. No-289 |
| 19 | R.C.C Work with cement approved coarse sand and 2 cm gauge approved stone grit in proportion of 1:2:4 in lintels of Doors, windows and sunshades excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.GI Binding wire and including necessary centering and shuttering etc. and supply of all materials, labour and T&P etc. required for proper completion of work. Binding wire of supplied by the contractor free of cost. As per S.I. No-283 |
| 20 | Mild steel (Tor steel) in plain work such as reinforced concrete or reinforced brick work including bending for proper shape and supply of all steel and wastage & all cost of Complete.SE PWD MBD |
| 21 | 12 m.m. thick Plaster with Cement mortar consisting of one part of cement and 4 part of coarse sand of 2.25 FM on brick work including supply of all material, labour, T&P etc.S.I No 584 |
| 22 | Earth Work in cutting or in embankment in ordinary soil, excavation to be in the regulour pits not exceeding 1/2 meter(20\") depth and earth work in embankment to be in 20 cm.(8\") layers including ramming and dressing the surface to required levels and slops and also in inculding 1.5 M(5ft.) lift & 30M(100ft.) lead.The earth from cutting to be used in making embankment or to be deposited as spoil banks with in 30 M (100ft.) distance as directed by Engineer-in-charge with extra cartage of 3 km. distance ..SI.No-253(b)+231(a) |
| 23 | Deduction cost of bricks M-150 at site As per S.I No.CH-01 SI No-01(a) (Dismantal Brick of 57.45%) Please Enable Macros to View BoQ information |