| 1 | 125 mm, thick brick work with 1st class bricks in cement mortar (1:4) in ground floor |
| 2 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes |
| 3 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)a) 25 mm to 30 mm thick wooden shuttering as per decision & direction of(f) 25 mm to 30 mm shultering without staging in foundation Engineer-In-Charge |
| 4 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etcinitial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and directiono 4 m (i) Tor steel/Mild Steel (ii) Tor steel/Mild Steel (JSW/Shyam/SRMB/Electrosteel etc) |
| 5 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering comers as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor). [Excluding cost of With 1:6 cement mortar, (b) 20 mm thick (ii) With 1:4 cement mortar (b) 15 mm thick plasterplasterover chipping over (ii) With 1:4 cement mortar (b) 15 mm thick plaster |
| 6 | (i) With 1:6 cement mortar (b) 20 mm thick plasterconcrete surface) |
| 7 | Supplying and laying true to line and level vitrified tiles of approved brand (size not less than 600 mm X 600 mm X 10 mm thick) in floor, skirting etc. set in 20 mm sand cernent mortar (1:4) and 2 mm thick cement slurry back side of tiles using cement @ 2.91Kg./sqM or using polymerised adhesive (6 mm thick layer applied directly over finished artificial stone floor/Mosaic etc without any backing course) laid after application slurry using 1.75 Kg of cement per sqM below mortar only, joints grouted with admixture of white cement and colouring pigment to match with colour of tiles/epoxy grout materials of approved make as directed and removal of wax coating of top surface of tiles with warm water and polishing the tiles using soft and dry cloth upto mirror finish complete including the cost of materials, labour and all other incidental charges complete true to the manufacturer\"s specification and direction of Engineer-in-Charge. (White cement, synthetic adhesive and grout material to be supplied |
| 8 | Artificial stone in floor, dada, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement (as necessary) and marble dust in proportion (1:2) including smooth finishing and rounding off corners including raking out joints or roughening of concrete surface and application of cement slurry before flooring works using cement @1.75 kg/sq.m all complete including all materials and labour.in ground floor.3 mm. thick topping (High polishing grinding on this item is not permitted with ordinary cement).(iii) 35 mm. thick |
| 9 | M.S. works in brackets made from flats, angles, tees etc. to sizes specialy bent, twisted, forged; making holes drilled and fitted to rafter of trusses with necessary bolts, nuts, washer or screws etc. (length of straight not less than 230 mm)Window Frame |
| 10 | Door Panel |
| 11 | Rendering the Surface of walls and ceiling with White Cement base WATER PROOF wall putty of approved make & brand. (1.5 mm thick). |
| 12 | Acrylic Distemper to interior wall, ceiling with a coat of solvent based interior grade acrylic primer (as per manufacturer\"s specification)including cleaning and smoothning of surface. Two Coats |
| 13 | Cement washing including cleaning and smoothening surface thoroughly (cement to be used @15 kg./100 sq.m. of surface for one coot and @25 kg./100 sq.m of surface for two coots): External surface (Ground floor) (a) One coat |
| 14 | Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old ar new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer\"s specification and as per direction of the FIC.In Ground Floor:(a) One Coat |
| 15 | Protective and Decorative Textured exterior high class matt finish paint of approved quality, composed of special Tharmoplastic Resin containing fine crystalline additives derive from Granite as per manufacturer\"s specification and as per direction of EIC to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer.In Ground floor Two Coat |
| 16 | (b) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc |
| 17 | (A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc.including using of approved putty etc. on the surface, if neces(b) On steel or other metal surface With super gloss (hi-gloss) -:(iv) Two coats (with any shade except white) |
| 18 | Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS: 13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete. A) UPVC Pipes: (i) 75 mm. Dia. |
| 19 | Supplying, fitting and fixing Stainless Steel railing consist of 38mm dia and 900mm height vertical balustrade at every Iwo alternative steps, 50mm dia top rail, 3 (three) nos 19mm dia horizontal Strainless steel pipe and base/cover plate with Strainless Steel GRADE 304 containing 7.5% nickle (Interior Grade) Brushed/Mat finish, complete as per direction of the Engineer-in-charge. Weight of Strainless Steel railing per metre 6.5 Kg (approx) |
| 20 | Collapsible gate with 40mm x 40mm x 6mm Tee as top and bottom guide rail, 20mm x 10mm x 2mm vertical channels 100mm apart in fully stretched position 20mm x 5mm M.S. flats as collapsible bracings properly rivetted and washered including 38mm steel rollers including locking arrangements, fitted and fixed in position with lugs set in cement concrete and including cutting necessary holes, chasing etc. in walls, floors etc. and making good damages complete |
| 21 | Supplying, fitting and fixing clear visioned, Insulated Double Glazed two track sliding Aluminium window (U-value <3.2W/m 2 K) made up with 6 mm thick toughened glass (wt > 15kg/m2) with 12 mm air gap in between, consaining perforated Al/structural foam spacer filled with moisture absorbant dessicant at all sides duly sealed with primary sealant (polyisobutylene) and affixed inside multi cellular/multi chember profiles of required section made of Alluminium alloy extrusions conforming to 15:733-1983 and 15:1285-2002 annodised/powder coated with (required film thickness and specified colour/natural) matt finished conforming to IS: 1868-2006/15: 13871-2002 measured as per IS:6012-1992, and sealed appropriately with secondary (polysulphide/silicon) sealant all junctions complete in all respect as per direction and satisfaction of Engineer-in-Charge including all incidental charges. (Payment shall be made on finished size of Aluminium window including frame.) |
| 22 | (a) M.S.or W.I. Ornamental grill of approved design joints continuously welded with M.S. W.I. Flats and bars of windows, railing etc. fitted and fixed with necessary screws and lugs in ground floor. (i) Grill weighing above 10 Kg./sq.mtr and up to 16 Kg./sq. mtr. |
| 23 | Sub Total |
| 24 | Add G.S.T 18% |
| 25 | Sub Total |
| 26 | Add Labour Welfare Cess 1% Please Enable Macros to View BoQ information |