| 1 | Taking down cement plasteron brick or stone walls or ceiling surfaces etc including raking out joints hacking for key scrubbing down with water and include for all necessary lowering, etc., removal of rubbish off the premises,removal and depositing serviceable materials where directed and leaving the work clear of any plastering complete all as specified and directed. |
| 2 | M&L for 10mmthick plastering in CM 1:6on fair faces of bricks or concrete surfaces (internal surfaces) finished even and smooth w/o using extra cement complete all as specified and directed. |
| 3 | M&L for Preparation of new surface of wall and applying two coat of oil emulsion distemper over a coat of primer over 3mm thick wall care putty on internal walls surfaces complete all as specified and directed. |
| 4 | M&L for 15mm thick external plastering in CM (1:4) with water proofing compound on fair faces of bricks or concrete surfaces finished even and smooth w/o using extra cement complete all as specified and directed. (Water proofing compound will measured and paid separately) |
| 5 | Supply only integral water proofing compound complete all as specified and directed. |
| 6 | M&L for preparation of new plastered surfaces of walls andapplying two or more coats with 100% premium acrylic emulsion paint having VOC content less than 50 gms/litre and UV resistance as per IS 15489:2004, alkalie and fungal resistance, dirt resistance, exterior paint of required shade with silicon additives @ 1.43L/10sqm over and including priming coat of exterior primer applied at 0.9L/10sqm complete all as specified and directed by Engr-in-Charge |
| 7 | M&L for preparation of new plastered surfaces of walls andapplying two coats of cement base paint over a coat of primer ,as per manufacturer\"s specification complete all as specified and directed. |
| 8 | M&L for 5mm thick plastering in CM 1:3on fair faces of concrete surfaces (ceiling surfaces) finished even and smooth w/o using extra cement complete all as specified and directed. |
| 9 | M&L for Preparing of new plastered surface of ceiling surfacesand applying three coats of white wash complete all as specified and directed. |
| 10 | M&L for Preparing of new plastered surface of ceiling surfacesand applying two coats of distemper oil emulsion over a coat of primer complete all as specified and directed. |
| 11 | M&L for 50 mm thick guniting in patches on to the required area on RCC slabs, sunshades, roofing slab etc. of all sizes and shapes at all heights from existing ground floor and all locations with cement mortar 1:3 (1 cement : 3 sand) under 2 to 2.8 Kg/Cm2 pressure after removing the damaged loose spalt concrete portions by chipping, removal of dust and applying one coat of rust converter/kp- 100 equivalent grade over reinforcement wherever necessary providing and tying in position 75x75x10 g MS welded mesh or smaller size over treated surface ready to receive grouts, curing for 10 days etc, complete operation all as directed including labour charges hire for all tools and plant machineries cost of consumables, scaffolding all types of protective equipments, plant floors, pipelines, vessels, materials etc. so as to do guniting in plant, removing the debris etc. rebound materials etc. to low lying areas in the factory compound and leveling as directed, complete all as directed by GE.Note: (i) After placing the additional reinforcement all concrete surfaces shall be thoroughly scrubbed with brushes, washed with water and alloy to dry. To this surface apply chemistic polycrete admixture at the rate not less than 2% by weight of cement or as per manufacturer\"s insturctions.(ii) When polymix coating is in tackey condition guniting is done with polycrete admixture at the rate not less than 2% by weight of cement or as per manufacturer\"s instruction. Polycrete admixture shall be procured form Chemical Adhesive Pvt Ltd Co or their authorized dealer. (iii) Cost of the above aspects shall be deemed to be included in the quoted rate of the respective item and nothing extra shall be paid on any account. |
| 12 | M & L for 10mm dia and over TMT steel cut to length, bend to shape and binding with ms wire (annealed)of dia not less than 0.9 mm complete all as specified and directed. |
| 13 | All as peritem No 12 above but 6mm to 8mm dia |
| 14 | Demolition of reinforced cement concrete as in Roofs, floors (other than groundfloors), beams, staircases, landing, chajjas and similar suspended work reinforcement cut as required to facilitate demolition)complete all as specified and directd by Engineer in charge |
| 15 | M&L of RCC nominal mix 1:1.5:3 type A1 using 20mm stone aggregate as in Chajjas, lintel/landigns, staircse, parapet walls etc all as specified and directed by Engineer in Charge |
| 16 | Formwork to chajjas, intel etc rough finished surfaces complete all as specifed and directed by Engineer in Charge |