| 1 | Construction of brick masonry platform using country bricks (19x9x9) in lime mortar 1:2 and filling the core with sand including conveyance of all materials, labour charges, uploading and unloading charges, mixing , watering, curing and the charges also including all applicable taxes etc. complete all as per the directions of the department official. |
| 2 | Careful plastering the base platform neatly with lime mortar 1:2 to an average of 12mm thickness including cost and conveyance of all materials, labour charges, loading and unloading charges, mixing, placing and spreading, watering and proper curing etc., and the charges also including all applicable taxes etc. complete all as per the direction of the department officials. |
| 3 | Filling of sand for providing cushioning including cost and conveyance of all materials, labour charges, loading and unloading charges, placing and spreading etc., and the charges also including all applicable taxes etc. complete all as per the direction of the department officials. |
| 4 | Carefully shifting and relocating loose architectural sculptures from the Main Mandapa to the Cloister Mandapa, including positioning and securing them in place, with sculpture sizes ranging from 37 cm × 35 cm (H) to 76 cm × 127 cm (H). The work includes safe handling by skilled labour for lifting, shifting, loading, unloading, transporting, and installing the sculptures, using all necessary tools, equipment, fittings, and insulation materials to ensure proper fixing and stability as directed by departmental officials. The rate shall include the cost and conveyance of all materials; labour charges for installation, loading and unloading, and transportation; and all applicable taxes and statutory contributions such as GST, EPF, and ESI, completing the work in all respects to the satisfaction of the department. |
| 5 | Making Supplying and fixing of Galvanised steel Grill with 50x50x6 mm Galvanised steel \"L \"angle in frame and 50x6 mm Galvanised steel flat in cross section and with 12mm MS round bars 10cm c/cin vertical section also painting with two coats of Anti corrosive paint over a primer and fixing the fence in position with clamps including cost and conveyance of all materials , labour charges, loading and unloading charges also including all applicable taxes etc. complete all as per the direction of the department officials ( Drawing enclosed) |
| 6 | Cleaning and removing the lime deposits inside the cloister mandapa (South- East Corner) of the Apathsahyeswara temple at Sendamangalam by providing scaffolding supports (Scaffolding pipe available at site) including labour charges and the charges also including all applicable taxes etc. complete all as per the direction of the department officials |
| 7 | Providing drainage cover for the open drainage masonryby using available granite stone slabs from the inner prakara wall to the outer prakara wall in the east side entrance of the Apathsahayeswara temple at Sendamangalam including labour charges, loading and unloading charges, transportation charges, mixing of mortar,placingetc complete and as directed by the department officials also includes GST, EPF, ESI and other applicable taxes if any etc. complete. |