| 1 | Group A- INSTALLATION / LABOUR CHARGES [FIBER OPTIC CABLE LAYING] |
| 2 | Digging of Hard Soil by manual labour (Spec: 3 feet Depth and 1 feet width) and refilling of trenches |
| 3 | Digging of Soft soil by manual labour (Spec: 3 feet Depth and 1 foot width) and refilling of trenches. |
| 4 | HDPE Pipe Laying and Laying of fiber cable through HDPE pipe, welding, cutting, drilling and finishing. |
| 5 | Termination / Splicing of Fibers (per fiber) |
| 6 | Fixing and Installation of LIUs |
| 7 | Splicing of pigtail |
| 8 | OTDR (Optical Time Domain Reflectometer) Testing, Report & Documentation, Labelling in LIU / Fiber Enclosure (per link) |
| 9 | Laying of optical fiber through PVC pipe, welding, wall cutting finishing by wall plaster |
| 10 | Road punching |
| 11 | Excavation and back filling with protection of bricks and sand in three side of HDPE pipe |
| 12 | OFC laying on surface / overhead |
| 13 | Supply and Fixing of RCC (Reinforced Cement Concrete) route marker after OFC cable and warning tape laying.RCC Dimension: 900x200x100mm |
| 14 | Supply and Fixing of Iron route marker after OFC cable and warning tape laying.Route marker dimension: [ Disc size - 200mm diameter; Stand size - Iron angle of 25mm x 25mm x 3mm, length 3 feet.] |
| 15 | OFC Route marking paint on wall (wherever it is required) |
| 16 | Group B - INSTALLATION / LABOUR CHARGES [UTP CABLE LAYING] |
| 17 | Laying and labeling of UTP cable through existing concealed pipe, welding, wall cutting, drilling and finishing wall by plastering. |
| 18 | Fixing of PVC Pipe |
| 19 | Fixing of PVC Casing and Capping |
| 20 | Supply and Fixing of PVC Pipe (Materials to be supplied by the vendor) |
| 21 | Supply and Fixing of PVC Casing and Capping (Materials to be supplied by the vendor) |
| 22 | Installation of wall mount rack. |
| 23 | Supply and fixing of a switch board with 5/15 amp socket and switch beside network rack. |
| 24 | Supply and fixing of a switch board with two 5/15 amp socket and two switchs beside network rack. |
| 25 | Fixing, labeling and termination of Back box, Face plate and I/O. |
| 26 | Fixing, labeling and termination of Face plate and I/O (Without Back box). |
| 27 | Outdoor UTP Cable Laying. |
| 28 | UTP Cable Laying through surface mounted PVC pipe, casing capping and overhead |
| 29 | Fixing of Patch / Jack Panel |
| 30 | Termination and labeling of UTP cable on Patch / Jack Panel (per port) |
| 31 | UTP Testing and documentation at both Patch / Jack Panel side andI/O side using DTX Analyser(per connection) |
| 32 | Termination/Crimping of RJ-45 Connector |
| 33 | Fixing of Wireless Access Point with proper mounting kit on Wall/Ceiling. |
| 34 | Group C - INSTALLATION / LABOUR CHARGES [CCTV SURVEILLANCE] |
| 35 | CCTV Surveillance Camera installation(Indoor Dome/Bullet/PTZ) in the wall/ceiling |
| 36 | CCTV Surveillance Camera installation (Outdoor Dome/Bullet/PTZ) onthe Pole |
| 37 | Installation of pole for CCTV camera which has to be laid at a depth of 2 feet and filled with concrete for 1’ x 1’ x 1’ (“Only pole will be supplied by NIT Rourkela”) |
| 38 | CAT6 Cable Laying in open (ariel) with Stay Wires for Outdoor Surveillance Camera. (Stay wires have to be provided by the contractor ) |