| 1 | Supplying all labour, T&P for earth work in excavation in all kind of soil ( for pipe line trench ) with in 50 mtr initial lead and 1.50 mtr initial lift including rough dressing and leveling etc.all complete |
| 2 | Supplying all labour, T&P for filling foundation trenches with sand watering and ramming etc. all complete as per the direction of Engineer–in–charge |
| 3 | Supplying all materials, labours and T&P for providing C.C (1:4:8) in foundation and plinth with 40mm size HG metal with cost, conveyance, royalty of materials including watering, curing etc. all complete. |
| 4 | Fly ash Brick masonary in CM (1:6) in F&P using H.G stone etc. including all cost |
| 5 | Supplying all materials, labours and T&P for providing rigid and smooth centering and shuttering for RCC work and dismantling them after casting including cost of materials T&P etc all complete Column base |
| 6 | Grade Beam |
| 7 | Coloumn Superstructure |
| 8 | Lintal |
| 9 | Wall Beam |
| 10 | Roof Slab |
| 11 | Chajja |
| 12 | Stair Case |
| 13 | 2.5mm thick grading concrete in CC (1:2:2) using 6mm size CB chips etc. |
| 14 | Supplying all materials, labours, and T&P for cutting, bending, binding the reinforcement and tying the grills and placing in proper position including cost of binding wire of 18 to 20 gauge and cost and conveyance of HYSD rod having IS |
| 15 | Fly Ash brick masonary in Superstructure in cement mortar (1:6) in using Fly Ash Bricks of 12cm x 11cm x 8 cm having crushing strength not less than 75 Kg/Cm2 with dimentional tolerance +/- 8% including watering, curing and cost, conveyance, royality of all materials & cost of labour charges etc complete. |
| 16 | Supplying all materials, labours and T&P for providing 12mm thick cement plaster in cement mortar (1:6) over brick work including watering and curing etc all complete |
| 17 | Supplying all materials, labours and T&P for providing 16 mm thick cement plaster in cement mortar (1:6) over brick work including watering and curing etc all complete |
| 18 | Supplying all materials, labours and T&P for providing 6 mm thick cement plaster in cement mortar (1:4) over brick work including watering and curing etc all complete |
| 19 | Supplying all materials, labours and T&P for providing 20 mm thick cement plaster in cement mortar (1:6) over brick work including watering and curing etc all complete |
| 20 | Supplying, fitting, fixing of industrial tile in floors marbonite or equivalent make in all floors using vertified tile over ground floor |
| 21 | Providing, fitting, fixing of M.S Iron grill gate etc including all cost |
| 22 | Providing fitting & fixing of vertified tiles in floor pf premium grade having thickness 8mm to 10 mm confirming to I.S 13756 of size (600mm x 600mm) coloured/ printed series ( Homogeneous) including cost, conveyance etc complete. (Ground floor) |
| 23 | Providing fitting & fixing of vertified tiles in dado including cost, conveyance etc complete ( Homogeneous) |
| 24 | Providing and applying wall putty (water based) over interior wall surface etc. complete |
| 25 | Painting two coats with approved enamel paint over a coat of redoxide primer etc. complete. |
| 26 | Paiting two coats with weather sealed paint over a coat of primer and putty (water based) including all cost,conveyance of all materials, labour and T&P etc complete |
| 27 | Painting two coats with plastic emulsion over a coat of wall primer of approved shade on new work to give an even shade complete. |
| 28 | Septic Tank |
| 29 | Soak Pit |
| 30 | ELECTRICAL INSTALLATIONSupplying, fitting, fixing of installation of electrification completely on L.S |
| 31 | PH & SANITARYSupplying, fitting, fixing of water connection & PH Works completely on L.S Please Enable Macros to View BoQ information |