| 1 | Routine maintenance and repairs of steam boiler (oil-fired, fully automatic) of capacity 600 Kg/hr, Make: Thermax, Model RXA-6, complete with 0.5 HP, 3-phase, 415 V fuel motor and 3 HP, 3-phase, 415 V water pump motor, including:(a) Cleaning and descaling of steel drum using descaling compound(b) Removal of scale from perforated body(c) Replacement of minor parts such as:• Photocell Cat No. THX/06/011• Ignition transformer 14.5 kV• Burner nozzle• Sequence control relay• Water pump oil seal (HCA-7)• Water pump ball bearing (HCA-5)(d) Tuning and overhauling of pumps(e) Repairs required for proper functioning(f)Checking/adjustment of safety devices and control panel(g) Lubrication as required(h) Routine maintenance of water softening plant associated with boiler plant roomBoilers covered:(a) Boiler No. 1 – Sl No. RXA-064907(b) Boiler No. 2 – Sl No. RXA-064906(c) Boiler No. 3 – Sl No. RXA-064905Note: Replacement of spares shall be measured and paid separately. |
| 2 | Repair and maintenance of air compressor of capacity 7.5 HP, Make KG Khosla, including:Complete cleaning(a) Replacement of minor parts.(b)Periodic topping-up of Mobil oil.(c)Maintenance of compressor and electric motor.Machines covered (running two at a time):(i) Sl No. 29004(ii) Sl No. 29923Note: Replacement of spares shall be measured and paid separately. |
| 3 | Repair and maintenance of electrically operated hydro-extractor machine, capacity 50 kg, Make Super Shine, motor 10 HP, 3-phase, 415 V, including:(a) Cleaning.(b) Minor repairs.(c) Adjustments and lubrication.(d) Replacement of minor parts such as:• V-belt No. 6-71• V-belt A-56• Ball bearingsMachines covered (running four at a time):(a) SH-50 – Sl No. 1(b) SH-50 – Sl No. 2(c) SH-50 – Sl No. 3(d) SH-50 – Sl No. 4Note: Replacement of spares shall be measured and paid separately. |
| 4 | Repair and maintenance of calendaring machine, Make : Super Shine, roller size 600 × 3300 mm, Model SFW-224S, including:(a) Repair of steam valve(b) Lubrication of gear system(c) Adjustment of chains and pneumatic valves(d) Repair/replacement of minor parts(e) Replacement of cloth paddingNote: Replacement of spares shall be measured and paid separately. |
| 5 | Repair and maintenance of pneumatically operated, steam-heated, auto temperature-controlled flat bed press, size 1500 × 750 mm, Make Super Shine, including cleaning, minor repairs, adjustment, and lubrication.Machines covered (running two at a time):(a) SFB-30S – Sl No. 1(b) SFB-30S – Sl No. 2Note: Replacement of spares shall be measured and paid separately. |
| 6 | Repair and maintenance of electrical operated side loaded sluice machine 25 Kgs capacity, auto controlled having electric motor of 3HP capacity, 3 phase, 415 Volts for washing machine & extraction (Make-Super Shine) including cleaning, rewinding of motor if required, repairs/replacement of motor parts adjustment, lubricating etc complete for followingMachines Covered (Running two machines at a time):- (a) Model No SSL 255 Sl No 1 (b)Model No SSL 255 Sl No 2Note :- Replacement of spares shall be measured & paid separately herein after. |
| 7 | Repair and maintenance of drying tumbler, capacity 50 kg, Make Super Shine, size 1150 × 950 mm, including:(a) Alignment of line chain(b) Repair/replacement of minor parts(c) Adjustment(d) Cleaning of steam heat exchanger and steam pipeline(e)Maintenance of electrical parts(f)Lubrication and cleaning of gear mountingMachines covered (running three at a time):(a) SDT-50S – Sl No. 1(b) SDT-50S – Sl No. 2(c) SDT-50S – Sl No. 3Note: Replacement of spares shall be measured and paid separately. |
| 8 | epair and maintenance of electrically operated washing machine, capacity 50 kg, front-loading, Make Super Shine, Model SFXL-50S, steam-heating type, automatic control panel with 5 HP, 3-phase, 415 V motor, including:(a) Rewinding of motor (if required)(b)Repair/replacement of major and minor parts including:• Ball bearings (SKF/Tata/ZKL)• Oil seal• V-belt• Pin-type coupling bush• ‘O’ ring• Overload relay• Electronic timer• Micro switch• Drain coils• Rubber door gasket (Neoprene, heat-proof)• Digital temperature gauges• Leg shaft(c) Adjustment and lubricationMachines covered (running two at a time):(a) SFXL-50S – Sl No. 1(b) SFXL-50S – Sl No. 5Note: Replacement of spares shall be measured and paid separately. |
| 9 | Repair and maintenance of washing machine of 100 kg capacity, front-loading, steam heating, automatic control panel with 10 HP, 3-phase, 415 V motor, Make Super Shine, Model SFXL-100S, including repair/replacement of all major/minor parts, lubrication, adjustments etc.Machines covered (running three at a time):(a) SFXL-100S – Sl No. 2(b) SFXL-100S – Sl No. 3(c) SFXL-100S – Sl No. 4Note: Replacement of spares shall be measured and paid separately. |
| 10 | Repair and maintenance of electrically operated mushroom press, size 500 × 250 mm, steam connection 15 mm, with suction blower 1 HP, 3-phase, 415 V, Make Super Shine, including:(a) Repair/replacement of minor parts(b) Adjustment(c) LubricationMachines covered (running two at a time):(a) SMP-19S – Sl No. 1(b) SMP-19S – Sl No. 2Note: Replacement of spares shall be measured and paid separately. |
| 11 | Repair and maintenance of electrically operated steam lagger press, tapered size 1200 mm, equipped with 1 HP, 3-phase, 415 V electric motor, including:(a) Repair/replacement of minor parts(b) Adjustment and lubrication of all moving components(c) Complete functional servicingMachines covered (running two at a time):(a) SWL-475 – Sl No. 1(b) SWL-475 – Sl No. 2Note: Replacement of spares shall be measured and paid separately. |
| 12 | Repair and routine maintenance of steam-operated mattress sterilizer machine, heavy-duty, capacity 150 kg, swing-door type, stainless-steel chamber, equipped with 5 HP vacuum pump, stainless-steel loading carriage and transfer trolley, Make Mediquip, including:(a) Replacement of minor parts such as:• Nuts, bolts• Fan belts• Timers• Hose pipe• All types of filters• Pressure gauges• Relays, contactors, switches(b) Complete cleaning of machine and chamber(c) Checking, adjustment and lubrication of all mechanical/electrical assembliesNote: Replacement of spares shall be measured and paid separately. |
| 13 | Repair and routine maintenance of dry-cleaning machine, capacity 25–35 kg, front-loading open-pocket type, with built-in low-spin extraction system and connected 15 kg hydro extractor (base-tank integrated), Make Super Shine Laundry System, including:(a) Replacement of minor parts such as:• Nuts, bolts• Fan belts• Timers• Hose pipe• All types of filters• Pressure gauges• Relays, contactors, switches(b) Complete cleaning of machine and hydro-extractor(c)Adjustment and lubrication of moving assembliesNote: Replacement of spares shall be measured and paid separately. |
| 14 | Taking down old unserviceable and supply & fixfuel pump for RXA 06 steam boiler |
| 15 | Taking down old unserviceable and supply & fixsteam valve1\" GMfor RXA 06 steam boiler |
| 16 | Taking down old unserviceable and supply & fixelectrodefor RXA 06 steam boiler |
| 17 | Taking down old unserviceable and supply & fixblower fan for RXA 06 steam boiler |
| 18 | Taking down old unserviceable and supply & fix reflector sheet for RXA 06 steam boiler. |
| 19 | Taking down old unserviceable and supply & fix Economiser (Part No PRXEL 10013)for RXA 06 steam boiler. |
| 20 | Taking down old unserviceable and supply & fix packing materialfor RXA 06 steam boiler. |
| 21 | Taking down old unserviceable and supply & fix Bottom duct for RXA 06 steam boiler. |
| 22 | Taking down old unserviceable and supply & fix steam pressure switch for RXA 06 steam boiler. |
| 23 | Taking down old unserviceable and supply & fix Triplex pump overhauling kit for RXA 06 steam boiler. |
| 24 | Taking down old unserviceable and supply & fix Flame sensor for RXA 06 steam boiler. |
| 25 | Taking down old unserviceable and supply & fix Wegman Cone for RXA 06 steam boiler. |
| 26 | Taking down old unserviceable and supply & fix Optimiser for RXA 06 steam boiler. |
| 27 | Supply, install and testing of steam tubes of MS and aluminium fins, the gap between two coils not less than 30mm including inlet, outlet pipes and suitable guage as per existing at site includig outer frame and connecting pipes complete all as directed by Engineer-in-Charge. |
| 28 | Material and labour for rewinding of electric motor, capacity 10 HP, 3-phase, 415 V, including removal of motor from Hydro Extractor and complete workshop rewinding, as under:(a) Disconnecting electrical and earth connections; decoupling motor from Hydro Extractor; removal of foundation bolts and shifting motor to workshop.(b) Opening split case/body cover; separating stator and rotor; cutting and removing burnt/defective winding.(c) Cleaning stator body thoroughly using sandpaper and removing carbon deposits.(d) Inserting new insulation materials such as insulating paper sleeves.(e) Rewinding stator with same size super-enameled copper wire, varnishing, heating to required temperature to achieve specified ohmic resistance.(f) Cleaning rotor; reassembly of motor.(g) Refitting motor to Hydro Extractor; reconnecting electrical and earth connections; tightening foundation bolts; load testing after installation.Complete all as specified and directed. |
| 29 | Ditto as per Item No. 28 above, but for electric motor of capacity 5 HP, 3-phase, 415 V.Note for Item 28 & 29:A 1-year guarantee for rewinding work from certified completion date shall be submitted by the contractor. |
| 30 | Supply and fixing of castor wheel, 6-inch diameter, with ball bearing and hard rubber outer surface, suitable for washroom trolley / self-trolley / mobile trolley, complete as directed by the Engineer-in-Charge. |
| 31 | Supply and fixing of timer, time range 0–60 minutes, suitable for single-phase 230 V AC supply, complete as specified and directed. |
| 32 | Taking out burnt electric motor from foundation, dismantling, rewinding and refixing of 7.5 HP, 3-phase, 415 V induction motor, including:(a) Disconnecting electrical and earth connections(b) Removal of motor from foundation(c) Dismantling of motor(d) Rewinding with approved quality super-enameled copper wire, same gauge and size as original(e) Providing insulating materials, varnishing, heating, and curing(f) Checking insulation resistance (IR value)(g)Reassembly of motorRefitting motor at original position and reconnecting all connectionsComplete all as specified and directed. |
| 33 | Ditto as per Item No. 32, but for induction motor of capacity 0.5 HP, 3-phase, 415 V.Note for Items 33 & 34:A 1-year guarantee for rewinding work from certified completion date shall be submitted by the contractor. |
| 34 | Supply and fixing of bearing, of existing make and type, complete as specified and directed. |
| 35 | Supply and fixing of suspension spring, suitable for hydro extractor machines, matching existing size, complete as specified and directed. |