| 1 | GROUND FLOOR |
| 2 | Earthwork in hard soil with initial lead and lift including rough dressing and breaking clods upto 5cm to 7cm size and laying in layers each layer not exceeding 0.3m in depth etc. complete. |
| 3 | Filling foundation and plinth with well watered and rammed to recevied maetal concrete. Including cost ,carriage,roaylty taxes of materials etc.complete. |
| 4 | Cement Concrete (1:4:8) with 4cm size Including cost ,carriage,roaylty taxes of materials etc.complete. |
| 5 | RCC wok of M-20 grade with 20mm downgraded size hard granite chips including hoisting and laying complete in layers watering, curing, centering, shuttering with all cost labour T & P etc. complete. A. RCC Plinth Beam |
| 6 | B. RCC Column |
| 7 | C. RCC Lintel |
| 8 | D. RCC Wall Beam |
| 9 | E. RCC Chajja |
| 10 | F. Stair case |
| 11 | G. RCC Column footing |
| 12 | H. RCC Roof(Slab) |
| 13 | Brickwork with Fly Ash bricks in cement mortar (1:6) in Foundation and Plinth including watering curing etc. |
| 14 | Fly asg brick work(1:6) for superstructure with cost carriage etc complete |
| 15 | Straightening cutting M.S. rod or steel to required size and out of either stright or coil rod bending , binding taying the grills for R.C.C work and hosting and placeing in postion including cost and conveyance of M.S. rod cost and conveyance and of binding wire 18 to 20 gauge required for binding and tying the grills and including all labour charges complete.(No separate payment will made towards weight or binding wire payments will be made on weight of M.S.Rod only) |
| 16 | 12mm thick CP (1:6) cm for 10\" wall outside wall |
| 17 | 16mm thick C.P(1:6) cm below plinth and (above ground level) |
| 18 | 16mm thick CP (1:6) cm for 10\" wall |
| 19 | 12mm thick C.P (1:4) C.M for 5\" wall |
| 20 | 6mm thick C.P (1:4)cm will all cost, carriage etc. complete |
| 21 | 12mm thick (1:4) cm with cement punning over wall to receive roof slab |
| 22 | Fixing vertified tiles in floors,treads (600mm x 600mm) and landings on 25mm thick bed of cement mortar (1:1) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 23 | Fixing vertified tiles in floors,treads (600mm x 600mm) and landings on 25mm thick bed of cement mortar (1:1) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 24 | Fixing glazzed tiles in dados,skirting and in rises of steps on 12mm thick bed of cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 25 | Fixing glazzed tiles in dados,skirting and in rises of steps on 12mm thick bed of cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 26 | Fixing PVC door to the toilet |
| 27 | Supplying M.S Door & Window with cost, carriage etc. complete |
| 28 | Painting two coats enamel paint over one coat primer on M.S door and window |
| 29 | Cement washing one coat including cost of all labour and materials etc. complete |
| 30 | Wall painting two coats with weataher coat paint over a coat of primer of approved shade including cost of paint. |
| 31 | Wall painting two coats with plastic emulsion paint over a coat of primer of approved shade including costof paint. |
| 32 | Supplying ,fitting, stainless steel 304 grade hand railing using 50mm dia of 2mm thick circular pipe of size 32mm x 2mm three rows |
| 33 | Site Development, Light Board etc. |
| 34 | FIRST FLOOR |
| 35 | Fly ash bricks works (1:6) for superstructure with all cost, carriage etc. complete |
| 36 | RCC wok of M-20 grade with 20mm downgraded size hard granite chips including hoisting and laying A.RCC column and beam |
| 37 | B. RCC Lintel |
| 38 | C. RCC Chajja |
| 39 | D. Stair case |
| 40 | E. RCC Roof slab |
| 41 | Cutting,bending & binding of MS Rod with all cost, carriage etc. complete |
| 42 | 12mm thick C.P (1:6)CM complete outside wall |
| 43 | 16mm thick CP (1:6) CM Complete inside for 10\" wall |
| 44 | 12mm thick C.P (1:4) cm compleye (inside wall) for 5\" wall |
| 45 | 6mm thick C.P (1:4) cm complete (celing) |
| 46 | Fixing vertified tiles in floors,treads (600mm x 600mm) and landings on 25mm thick bed of cement mortar (1:1) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 47 | 12mm thick C.P in cm(1:4) with cement punning over wall top to receive roof slab |
| 48 | Fixing glazzed tiles in dados,skirting and in rises of steps on 12mm thick bed of cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 49 | Fixing vertified tiles in floors,treads (600mm x 600mm) and landings on 25mm thick bed of cement mortar (1:1) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 50 | Fixing glazzed tiles in dados,skirting and in rises of steps on 12mm thick bed of cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 51 | Supplying MS Door & Window with cost carriage etc. |
| 52 | Fixing PVC door to the toilet complete |
| 53 | Painting two coats enamnel paint over one coat primer on MS Door & Window |
| 54 | Cement washing one coat including cost of all labour and materials etc. complete |
| 55 | Wall painting two coats with weataher coat paint over a coat of primer of approved shade including cost of paint. |
| 56 | Wall painting two coats with plastic emulsion paint over a coat of primer of approved shade including costof paint. |
| 57 | 25mm grading (1:2:2) to the roof on the 1st floor, portico & open terrace |
| 58 | Fitting, fixing stainless steel 304 grade hand rilling using 50mm dia of 2mm circular pipe of size 32mm x 32mm x 2mm three rows |
| 59 | STORE ROOM |
| 60 | Fly ash bricks works (1:6) for superstructure with all cost, carriage etc. complete |
| 61 | RCC wok of M-20 grade with 20mm downgraded size hard granite chips including hoisting and laying complete in layers watering, curing, centering, shuttering with all cost labour T & P etc. complete. A. RCC Column |
| 62 | B. RCC Lintel |
| 63 | C. RCC Chajja |
| 64 | D. RCC Roof Slab |
| 65 | Straightening cutting M.S. rod or steel to required size and out of either stright or coil rod bending , binding taying the grills for R.C.C work and hosting and placeing in postion including cost and conveyance of M.S. rod cost and conveyance and of binding wire 18 to 20 gauge required for binding and tying the grills and including all labour charges complete.(No separate payment will made towards weight or binding wire payments will be made on weight of M.S.Rod only) |
| 66 | 12mm thick cement plaster in cement mortor (1:6) over brick work including all cost conveyance etc.complete |
| 67 | 16mm thick cement plaster in cement mortor (1:6) over brick work including all cost conveyance etc.complete |
| 68 | 12mm thick C.P (1:4) C.M for including all cost conveyance etc.complete |
| 69 | Fixing vertified tiles in floors,treads (600mm x 600mm) and landings on 25mm thick bed of cement mortar (1:1) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 70 | Providing and fixing Glazed Ceramic tiles in dados,skirting and in rises of steps on 12mm thick bed of cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile. |
| 71 | Wall painting two coats with weataher coat paint over a coat of primer of approved shade including cost of paint. |
| 72 | Wall painting two coats with plastic emulsion paint over a coat of primer of approved shade including costof paint. |
| 73 | Supplying M.S Door & Window with cost, carriage etc. complete |
| 74 | SEPTIC TANK |
| 75 | Earthwork in hard soil with initial lead and lift including rough dressing and breaking clods upto 5cm to 7cm size and laying in layers each layer not exceeding 0.3m in depth etc. complete. |
| 76 | Filling foundation and plinth with well watered and rammed to recevied maetal concrete. Including cost ,carriage,roaylty taxes of materials etc.complete. |
| 77 | Providing C.C(1:4:8) using 4cm metal with cost carriage etc |
| 78 | Brickwork with Fly Ash bricks in cement mortar (1:6) in superstructure including watering curing etc. |
| 79 | RCC wok of M-20 grade with 20mm downgraded size hard granite chips including hoisting and laying complete in layers watering, curing, centering, shuttering with all cost labour T & P etc. complete. |
| 80 | PCC (1:2:4) including hoisting and laying complete in layers watering, curing, centering, shuttering with all cost labour T & P etc. complete. |
| 81 | Straightening cutting M.S. rod or steel to required size and out of either stright or coil rod bending , binding taying the grills for R.C.C work and hosting and placeing in postion including cost and conveyance of M.S. rod cost and conveyance and of bind |
| 82 | 12mm thick (1:4) CM with cement punning over wall to receive roof slab. |
| 83 | Site Development, Light Board etc. |
| 84 | Electrical Work (10%) |
| 85 | PH Work (10%) Ground Floor |
| 86 | PH Work (15%) First Floor Please Enable Macros to View BoQ information |