| 1 | Earth work in excavation of foundation in hard soil including dressing and leveling the bed and depositing the soil within 50 m initial lead and 1.5 m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3 m in depth and as per direction of the Engineer-in-charge. |
| 2 | Supplying and filling in foundation trenches and plinth, ditches with sand well watered and rammed in layers not exceeding 23 cm. in depth with all lead and lift including cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labour,labour cess, sundries, T&P required for the work etc. complete in all respect as per direction by the Engineer in charge. |
| 3 | Cement concrete of prop.(1:3:6) in foundation up to lowest bed level using crusher broken hard black granite metal of size 4cm down graded of approved quality from approved quarry as per approved design including hoisting,lowering,laying compacting concrete in layers not exceeding 6” thick, watering, curing for three weeks shuttering the exposed surfaces, finished smooth, providing grooves of beads where necessary including cost, conveyance, royalty, & taxes of all materials, with labour, T&P required for the work etc., complete in all respects including dewatering if required as per direction of Engineer-in-Charge. |
| 4 | RCC work in cc (1:1.5:3) using 20mm & down graded CBBHG chips including all cost, conveyance, taxes, royalties, watering & curing and labour with T&P as required for the work etc complete.(A) Column Base footings |
| 5 | (B)Columns |
| 6 | (C) Plinth Beam |
| 7 | (D) Lintel |
| 8 | (E) Wall Beam |
| 9 | (F)Roof Slab |
| 10 | (G) Chajja |
| 11 | Supplying, fitting and placing uncoated HYSD bar Reinforment including cutting, bending, binding and tying the grills and placing in position including cost,conveyance and royalties of all materials and labour etc.complete. |
| 12 | Fly Ash brick masonary in F&P and Superstructure in cement mortar (1:6) in using Fly Ash Bricks of 25cm x 12cm x 8 cm having crushing strength not less than 75 Kg/Cm2 with dimentional tolerance +/- 8% including watering, curing and cost, conveyance, royality of all materials & cost of labour charges etc complete.(A) Foundation |
| 13 | (B) Super Structure |
| 14 | 12mm thick cement plastering with cm (1:6) over brick work finished smooth after racking out joints deep including watering, curing. |
| 15 | Providing 16 mm thick cement plaster with cement mortar of mix (1:6) with screened and washed sharp sand for mortar and finished smooth to the rough surface of walls in all heights after racking out joints including watering and curing, rounding of corners, providing grooves where ever necessary with cost, conveyance, royalties and taxes of all materials with cost of all labour,labour cess, T&P, and scaffolding required for the work etc. complete in all respect as directed by the Engineer in charge. |
| 16 | 6mm thcik CP(1:4) over RCC work for ceiling plaster including cost,carriage of all materials and labour etc.complete. |
| 17 | 25mm thick Grading Concrete (1:2:2) over roof slab using 6mm thick cbhg chips including cost,conveyance, royalties and taxes of all materials etc.complete. |
| 18 | Supplying, fitting & fixing of 30cm x 20cm/20cm x 20cm special plain/printed series Ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753 in dadoes, skirting and risers of steps laid on 12 mm thick cement mortar (1:3) (1 cement : 3 course sand) jointed with slurry mixed with pigment to match the shades of the tiles etc. complete including cost of all materials, labour T&P etc. required for the work all complete as per direction of the Engineer-in-charge |
| 19 | Providing, fitting and fixing Vitrified tile in floor of size 600x600 mm of approved make conforming to IS: 13755 laid on 20 mm thick cement mortar 1:4 (1 cement: 4 course sand) and filling joints with white cement of approved quality including cost of all materials, labour T&P etc required for the work all complete as per direction of Engineer-In-Charge (for New work only) |
| 20 | Supplying M.S. Grill, Gate made out of angle,flat and square bar including cost of transportation, taxes, painting Two coats enamel paint, one coat of priming etc.all complete. As per approved design and Direction of Engineer - In- Charge. (per Kg.) |
| 21 | Finishing wall surface of walls with Acrylic wall putty (Water based ) of approved make and finished smooth and even receive painting including cost of scaffolding surface to staging charges with cost of all materials taxes, labour T&P etc complete. |
| 22 | Wall painting two coats with weather coat paint of approved shade on new work to give an even shade including cost of paint and all materials etc.complete. |
| 23 | Distempering two coats with good shade including cost,conveyance, taxes and labour with T&P etc. complete. |
| 24 | Painting two coats with Synthetic Enamel paint to new MS work including cost of paint and all labour etc.complete. |
| 25 | Add for Internal PH Works @ 7.5% |
| 26 | Add for Internal E.I Works @ 7.5% |
| 27 | Compound wallEarth work in excavation of foundation in hard soil including dressing and leveling the bed and depositing the soil within 50 m initial lead and 1.5 m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3 m in depth and as per direction of the Engineer-in-charge. |
| 28 | Supplying and filling in foundation trenches and plinth, ditches with sand well watered and rammed in layers not exceeding 23 cm. in depth with all lead and lift including cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labour,labour cess, sundries, T&P required for the work etc. complete in all respect as per direction by the Engineer in charge. |
| 29 | Cement concrete of prop.(1:3:6) in foundation up to lowest bed level using crusher broken hard black granite metal of size 4cm down graded of approved quality from approved quarry as per approved design including hoisting,lowering,laying compacting concrete in layers not exceeding 6” thick, watering, curing for three weeks shuttering the exposed surfaces, finished smooth, providing grooves of beads where necessary including cost, conveyance, royalty, & taxes of all materials, with labour, T&P required for the work etc., complete in all respects including dewatering if required as per direction of Engineer-in-Charge. |
| 30 | Brick masonary using Fly ash bricks in CM(1:6) in foundation and plinth with cost of all labour and materials, etc complete.(25X12X8) |
| 31 | Brick work in super structure with flyash bricks of size 25cmx12cm 8cm (1:6) having crushing strength not less than to 75kg/cm2 including cost,conveyance of all materials and labour charges etc.complete. |
| 32 | RCC work in cc (1:1.5:3) using 20mm & down graded CBBHG chips including all cost, conveyance, taxes, royalties, watering & curing and labour with T&P as required for the work etc complete.(A) Column Base footings |
| 33 | (B)Columns |
| 34 | (C)Column above plinth |
| 35 | Supplying, fitting and placing uncoated HYSD bar Reinforment including cutting, bending, binding and tying the grills and placing in position including cost,conveyance and royalties of all materials and labour etc.complete. |
| 36 | 12mm thick cement plastering with cm (1:6) over brick work finished smooth after racking out joints deep including watering, curing. |
| 37 | 16mm thick CP (1:6) over inside rough surface of brick work including cost, conveyance of all materials and labour etc.complete. |
| 38 | Supplying M.S. Grill, Gate made out of angle,flat and square bar including cost of transportation, taxes, painting Two coats enamel paint, one coat of priming etc.all complete. As per approved design and Direction of Engineer - In- Charge. (per Kg.) |
| 39 | Wall painting two coats with weather coat paint of approved shade on new work to give an even shade including cost of paint and all materials etc.complete. |
| 40 | Painting two coats with Synthetic Enamel paint to new MS work including cost of paint and all labour etc.complete. |
| 41 | Contingency work Please Enable Macros to View BoQ information |