| 1 | Carefully demolishing the existing damaged CC flooring for providing new stone flooring to the mandapa areas and disposal the same to a far off place etc., including cost of all materials, labours, conveyance and other charges etc., |
| 2 | Retoning the gopuras, vimanas, prakara walls with water based finishing coats for restoring the existing color substances including cost of all labours, scaffolding, neat finishing and material charges etc. |
| 3 | Providing MS Iron steps for easy approach to the Dhandayadapani shrine both sides after provided the stone flooring with MS L angle, MS Flat and sheet as per drawings and specification including cost of all labours, materials, all conveyance and other charges etc.(As per drawing) |
| 4 | Earthwork excavation in hard gravel soil of depth less than 50cm with initial lead and lift including cost of all materials, labours and other charges etc complete. |
| 5 | Sand filling the below foundation concrete and compacting, ramming including cost of all labours, materials and other charges etc complete. |
| 6 | Laying a bed of lime concrete in pure Lime 1:2 using 20mm size brick aggregate of 100 mm thick (1 Part of Lime: 2 Part of Brick Aggregate) for stone flooring in and around the temple area including compacting, ramming, cost of all materials, labours and conveyance charges etc complete |
| 7 | Construction of Coursed rubble masonry revetment wall using with lime mortar 1:2 (1 Part of Lime: 2 Part of Dry River Sand) including cost of all labours, materials and other charges etc complete. |
| 8 | Pointing to the revetment wall stone joints in lime mortar 1:1.5 (1 Part of Lime: 1.5 Part of Dry River Sand) for the strengthening the wall including cost of all labour, material and other charges ete complete. |
| 9 | Filling the earth by proper levelling, compacting for increase the height as per the existing level for providing stone flooring including cost of all materials, labour and other charges etc., complete. |
| 10 | Supply and installation of RCC Precast readymade toilet (6X4) including Earthwork, laying PCC, construction of RR masonry, providing concrete and cost of material labour charges, installation charges at site etc., complete. (As per attached drawing) |
| 11 | Providing the stone flooring in and around the temple area with neatly dressed stone of sizes varying from 90 to120 cm of length, 45 to 60 cm of width with a thickness not less than 10 cm in over a bed of lime concrete in pure Lime 1:2 using 20mm size brick aggregate of 100 mm thick (1 Part of Lime: 2 Part of Brick Aggregate) and set in Lime Mortar 1:2 (1 Part of Lime: 2 Part of Dry River Sand) and Pointing the joints with the Lime mortar 1:1.5 (1 Part of Lime: 1.5 Part of Dry River Sand) with suitable colour oxides including curing, as per the standard specifications and as directed etc., complete for inclduing cost of all materials, labours and conveyance charges etc complete |
| 12 | Carefully deplastering the damaged inner and outer wall surface by sorting useful materials for reuse and throwing away debris etc; complete. |
| 13 | Resetting the undulated flooring stones including removing, earthwork excavation and resetting the same as per the existing style over a bed of lime concrete in pure Lime 1:2 using 20mm size brick aggregate of 100 mm thick (1 Part of Lime: 2 Part of Brick Aggregate) and set in Lime Mortar 1:2 (1 Part of Lime: 2 Part of Dry River Sand) and Pointing the joints with the Lime mortar 1:1.5 (1 Part of Lime: 1.5 Part of Dry River Sand) with suitable colour oxides including curing. as per the standard specifications and as directed etc |
| 14 | Removing the existing undulated stone flooring for construction of drainage for easy flow out the abishega water, rain water etc and pathway approach including cost of all labour, material and other charges |
| 15 | Construction of brick masonry in Lime Mortar 1:2 (1 Part of Lime: 2 Part of Dry River Sand) using country bricks of Size 230mm x 110mm x 70mm in drainage for easy flow out the abhisega water, rain water and drain water including cost of all materials, labour and other charges etc |
| 16 | Plastering with lime mortar 1:2 (1 Part of Lime: 2 Part of Dry River Sand) including cost of all mateials, labour and other charges etc complete. |
| 17 | Providing 10 cm thick new stone slabs over the drainage flow out area for avoiding fallen debris and garbages and poitning the stone joint in LM 1:1.5 (1 Part Lime: 1.5 Dry River Sand) including cost of all materials, labours and conveyance charges etc., |
| 18 | Providing new stone steps using 30% stone available, data for 70% new stone for easy approach to the temple shrines for the purpose of public/tourist/visitors using lime mortar 1:2 necessary brick jelly concrete and pointing the stone joints with lime mortar 1:1.5 (1 Part of Lime: 1.5 Part of Dry River Sand) including cost of all labour, material and other charges etc complete. |
| 19 | Providing MS grills in the monument with necessary 50x50x6mm L angle, MS flat 50x50mm and 16mm dia round rods with necessary openings including cost of all materials, welding charges and other labour charges etc complete.(As per drawing) |
| 20 | Painting to the MS grills and MS grill door with synthetic enamel paint of approved colour including scrapping the old surface with all cost of labours, materials and other charges etc complete. |
| 21 | Painting to the wooden door with syntheticenamel wooden paint of approved colour including scrapping the old surface with all cost of labours, materials and other charges etc complete. |
| 22 | Dismantling safely the existing accretion wall for clear view of mandapa structure including disposal of debris to a far off place etc, including cost of all materials, labours and other charges |
| 23 | Making Supplying and fixing of Direction Notice Board and etching with detailed information size of 4mm thick, 304 grade stainless steel sheet of required dimensions of 450mmx 250mm with given information etched on it and fixing with SS dia pipe 50x6mm thicknes size of 2500mm height with necessary cost of welding, earthwork, laying concrete for fixing the board for base area including cost of all materials, labour charges and conveyance charges etc., complete (As per the attached drawing) |
| 24 | Providing and fixing in position of dust bin 600x600x 1375mm outer dimensions of hallow square by making with 100mm thick granite slabs and jointed with bottom granite slab of 600mm x 600mm x 50mm with necessary groves and fixed with foundation concrete 1:2:4 including cost of earthwork excavation curing etc complete (As per the attached drawing) |
| 25 | Providing MS iron Protection notice board sticking with detailed information (Tamil, Hindi and English) size of 1000x600mm of flat iron and cover the outer frame with mesh, fixing with iron L angle size of 2500mm height with necessary cost of welding, earthwork, laying concrete for fixing the board and brick masonry work for base area including cost of all materials, labour charges and conveyance charges etc., complete.(As per the attached drawing) |
| 26 | Making, supplying and fixing the SS 304grade 4mm thickness for Cultural information signage board size of 900mm x 600mm fixing on the Granite stone slab size of 1200x 800mm with base stone pillar size of 1200x300mm for fixing the stone slab including necessary earthwork, laying PCC Concrete and etched with detailed cultural information (Tamil, English and Hindi) on the SS board including necessary transportation, labour and other cost of materials etc., complete.(As per the attached drawing) |