| 1 | Surfacing dressing of the ground including removing vegetation and inequalities not exceeding 15 cm deep disposal of rubbish, lead up to 50m and lift up to 1.5m in all kinds of soilincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 2 | Cleaning jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30cm measured at a height of 1m above ground level and removal of rubbish up to a distance of 50m outside the periphery of the area cleared including all tools and plants, labour etc. complete as per direction of engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 3 | Earth work in excavation in trenches for foundations and for pipes, drains & cables etc. (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5m including getting out and stacking the excavated soil and disposal of surplus excavated soil as directed within a lead of 50m in loose or soft soilincluding all tools & plants, labour etc. complete as per direction of Engineer-in-Chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 4 | Providing and laying in position cement concrete of 1:4:8 (1 Cement : 2 Coarse River Sand : 4 Graded Stone aggregate 20mm nominal size) with mechanical mixing up to plinth level including laying, compacting, curing and centering & shuttering , form Works complete with all materials, tools & plants, labours and all other chargesetc. complete as directed by the engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 5 | Providing and laying in position cement concrete of 1:2:4 (1 Cement : 2 Coarse River Sand : 4 Graded Stone aggregate 20mm nominal size) with mechanical mixing up to plinth level including laying, compacting, curing and centering & shuttering , form Works complete with all materials, tools & plants, labours and all other chargesetc. complete as directed by the engineer in charge including cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 6 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. including the cost ofall materials, tools & plants, labours and all other chargesetc. complete as directed by the engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 7 | Supplying and filling in trenches, plinth, sides, of foundation, floors etc. with morroum/river sand in layers not exceeding 20 cm in depth including watering, ramming, consolidated and drressing etc. complete with supply of all labours, tools, etc. complete as directed by engineer-in-chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 8 | Hard stone sloing/ pitching laid in course and required profile with hammer dressed stones having no sides less than 20cm, with minimum depth of 20cm including preparing the bedding surface, supply of all materials, labours, tools and plants etc. completed as directed by the engineer-in-chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 9 | Providing and laying cement concrete 1 : 3 : 6 (1 Cement, 3 Coarse river Sand: 6 graded stone aggregate20 mm normal size) in Foundation and plinth including laying, compacting, curing with materials, tools, labours etc. complete as directed by the engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 10 | Providing and laying in position reinforced cement concrete of grade 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) including the cost of centering, shuttering but excluding the cost of reinforcementincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 11 | Foundation, Footing, Bases of Column etc. Mass Concrete. |
| 12 | Columns, Pillars, Piers, Abutments, Posts and Struts |
| 13 | Suspended floors, roofs, landings, balconies and access platform |
| 14 | Lintel, Beams, Plinth Beams, Girders, Bressumers and Cantilevers |
| 15 | Supply, fabrication, hoisting and placing in position HYSD reinforcement bars (SAIL/ TATA/IISCO / RINL/ JINDAL etc.) conforming to IS 1786 - latest edition Grade FE 415 / 500 as per detailed drawing and specifications including cutting, bending and tying with 18 SWG binding wire complete for all heights and depths as directed etc. complete including supply of all labours, tools, materials etc. complete as directed by the engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 16 | Providing and Fixing upto floor five level precast cement concrete Solid block of 1:1.5:3 ( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size), including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 Coarse sand), cost of required centering, shuttering complete with all materials, tools, labours etc. as directed by the engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 17 | 15mm thick cement plaster in single coat on rough side of single or half brick wall for interior plasteringincluding arises, internal rounded angles chamfers and/ or rounded angles nor exceeding 80mm in girth and finished even and smooth in CM 1:4 ( 1 cement :4 coarse sand) including supply of all labours, tools, materials, etc. complete as directed by the engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 18 | Providing and applying white cement based putty of average thickness 1mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth etc. including supply all materials, tools, labours etc. completed as directed by engineer-in-chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 19 | Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound) content less than 50 grams/ litre of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour ( Two Coats)including cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 20 | Painting two coats with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture to the outside surface of the Lighthouse tower with approved quality Sy. Enamel paint in white colour after cleaning and preparing the surface properly including the cost of materials, labour, tools etc. complete as directedincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 21 | Providing Wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia & length ( Second class teak wood / Padaukwood) including cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 22 | Providing and fixing First class teak / Paudak wood panelled 35mm thick shutters for doors, windows and clerestory windows finished with melamine polish over a coat of wooden primer , including supplying and fixing of ISI marked Brass butt hinges (heavy type) : 100x85x5.5 mm bright finished with necessery brass screws, Brass tower bolt (barrel type) 250x10 mm, Brass handles 125 mm with plate 175x32 mm and Brass mortice latch and lock 100x65 mm with 6 levers and a pair of anodised aluminium lever handles including supply of all labours, tools & plants, materials and all other charges etc. complete as directed by the engineer in chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 23 | Supplying and fixing in trap door (GI framewith cover 90x65cm) in lighthouse tower at all heights made up aluminium chequerred plate with frame of aluminium L angle, providing outer frame G.I angle to be fitted to the concrete slab with necessary hinges for easy opening and closing providing locking arrangements, handles as per drawing and fixing in top slab including supply of all materials, labours, tools and plants and all other charges etc. completed as directed by the engineer-in-charge including cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 24 | Providing and fixing aluminium ladder 4.20m long made out of anodized aluminium sections, fixing the ladder to the slab etc as per drawing including supply of all materials, labours, tools and plants etc. completeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 25 | Providiong and fixing MS grill door to the main door of lighthouse tower/ walls fabricated with MS angle outer frame and MS flats necessary and required hinges & screws, lsocking arrangements, welding, grinding etc and painting with a coat of zinc chromate metal primer. Fixing the door to the wall of the LH tower using suitable hinges and brackets, providing locking arrangement etc. complete as directed. |
| 26 | Providing temporary tents/shed of good quality with raised base for platform for supervisory staff, with tarpaulines, jungles ballies, plants, nylone ropes GI/ Aluminium sheets including supply of all materials cleaning & levelling of ground, necessary earth work all labours, tools plants etc. complete |
| 27 | Providing and laying Ceramic glazed Anti Skid floor tiles of approved size (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse river sand), including pointing the joints with white cement and matching pigments etc., completeincluding supply of all labours, tools and plants, materials and finishing and all other charges etc. complete as directed by the engineer incharge |
| 28 | Providing and fixing M.S Tube for hand raill of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer, painting etc.including supply of materials , labours, tools etc. complete as directed. |
| 29 | Providing and Square Section fixing hand raill of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer,including supply of materials , labours, tools etc. complete as directedincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 30 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 31 | Demolishing brick /CC block work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-chargeincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 32 | Disposal of building rubbish/ malba/ similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by engineer in charge, beyond 50m initial lead, for all leads including all lifts involvedincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |
| 33 | Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead of area 3 sq. metres and belowincluding cost of all materials supply of skilled labours, transportation charges of all men & materials upto worksite, head loads, overheads, cost of minor tools & Plants, safety arrangements, insurance of workmenand all other charges etc complete. |