| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 18-11-2025 | Extension of Date | Date | 26-11-2025 |
| Sl. No. | Item Description |
| 1 | S/E of Terminal Gantry of R.S. Joist-175x85 mm 19.5 Kg/Mtr. 6.1 Mtr. above the ground and1:3:6cementconcretefoundationmountedonastonepadof300x300x75mm complete in all respect as per direction of E/I |
| 2 | S/E of erection of 33 KV line Isolator suitable 1250 Amp. with structure complete in all respect as per direction of E/I |
| 3 | Supply, Errection, testing & Commissioning of 33 KV VCB 750 MVA/1250 Amp., 1500 MVA 25 KA Motorized complete with CT, PT with structure complete in all respect as per approvalofUPPCLandenlistedlatestvendorlist (1 Incoming and 2 Outgoing) |
| 4 | S/E of Bus Bar gantry structure of 105 Lbs/Rail Pole 6.5 Meter long 5.2 Meter above in ground level with 33 KV section Isolator complete in all respect as per direction of E/I |
| 5 | S/E of 33 KV lighting arrestors with structure made of MS channel 125x65 mm 3.1 Kg./M topofMSangle50x50x6mm, 4.5Kg/MLightingArrestor(onesetoflightingarrestor shall be installed on gantry)complete inall respect as per direction ofE/I |
| 6 | Supply, Erection, testing & Commissioning of outdoor type with copper wound 5 MVApower transformerwith on loadtap changerasperUPPCL with followingprovisions.(a)Cable termination box with disconnecting facility for 33 KV XLPE cable outdoor arrangement with 33 KVbushings at 33KV side.(b) Cable termination boxwith disconnecting facility with11KV bushingsfor11KVXLPEcableat11KVside.(c)Onloadtapchanger+5%to -15%(d) Bi directional roller (e) Conservator with drain valve & sump value. (f) Earthing terminals (Two) (g) Double diaphragm explosion vent (h) Radiator with top & bottom shut of valve (i) First filling of oil including makeup fill (j) Silica gel breather with oil seal (k) Rating and Diagram plate (l) Air releaseplug(m)Buchholzrelaywithshutoffvalvesonbothsides.(n)Windingtemperature Indicator(WTI)(o)OilTemperatureindicator(OTI)(p)Magneticoillevelgauge(q)Pressure reliefdevice(r)MarshallingBox(s)Tappositionindicator(t)MarkingplateforOLTC(u) Terminal marking plate (v) Drain valve with plug & locking arrangement (w) Filter valve (x) Oil sampling Valves (03 Each.) (first quality material as per latest amendment in indian standard and approved by UPPCL and enlisted latest vendor list.) |
| 7 | Construction of 33 KV transformer plinth suitable for 33/11KV transformer (1x10 MVA) asper drawingwith all material, labour and T&P etc.requiredfor proper completion of the work as per specifications of UPPCL |
| 8 | S/FofFencingof2.7Mheightofchain link2\"x2\"wirewithIntermediateofTiron complete in all respect as per direction of E/I |
| 9 | Construction of Boundary Wall for the fencing complete in all respect as per direction of E/I |
| 10 | S/B of 40 mm dia x 4.5 meter long GI Pipe earthing as per PWD Sch. No. 701. |
| 11 | S/Fof50x6mmGIstripfromearthelectrodedirectlycompleteinallrespectasper direction of E/I |
| 12 | S/F of 33 KV Post insulator 2x22 KV of approved quality complete in all respect as per direction of E/I |
| 13 | Supply, Fixing, installation, testing & Commissioningof 11 KV VCB Panel as per latest specification outgoing 11 KV completewith1250 Amp., 350 MVA, 600/300/5 Amp. CT ratio with PT 2 Each. incoming panel and 800 AMP., 350 MVA, 400/200/5 Amp. 6 Nos. Outgoing and 1 Nos. Bus coupler panels as per approval of UPPCL and enlisted latest vendor list |
| 14 | S/L of 300 sq. mm, 3 core 11 KV XLPE cable complete in all respect as per direction of E/I (Gloster /KEI / Havells/ Grandlay/Polycab make) |
| 15 | S/L of 300 sq. mm, 3 core 33 KV XLPE cable complete in all respect as per direction of E/I(Gloster / Havells/ Grandlay/Polycab/ KEI make) |
| 16 | S/L of 70 sq. mm, 3 core 11 KV XLPE cable complete in all respect as per direction of E/I as per PWD Sch. No. 506(d) (Gloster /KEI / Havells/ Grandlay/Polycab make) |
| 17 | S/F ofJointingkit 300sq. mm indoor type33 KV heat shrinkabletypecompletein all respect as per direction of E/I (Raychem/Denson/Birla make) |
| 18 | S/F of Jointing kit 300 sq. mm outdoor type 33 KV heat shrinkable type complete in all respect as per direction of E/I (Raychem/Denson/Birla make) |
| 19 | S/F ofJointingkit 300sq. mm indoor type11 KV heat shrinkabletypecompletein all respect as per direction of E/I (Raychem/Denson/Birla make) |
| 20 | S/F of Jointing kit 300 sq. mm outdoor type 11 KV heat shrinkable type complete in allrespect as per direction of E/I (Raychem/Denson/Birla make) |
| 21 | S/FofJointingkit70sq.mmindoortype11KVheatshrinkabletypecompleteinallrespect as per direction of E/I (Raychem/Denson/Birla make) |
| 22 | S/F ofJointingkit 70sq. mm outdoor type11 KV heat shrinkable type completein allrespect as per direction of E/I (Raychem/Denson/Birla make) |
| 23 | Supply & fixing of lugs for Cable (10 sq. mm) as per PWD Sch. No. 504 I |
| 24 | S/laying of 70 sq. mm, 3.5 core Aluminium conductor PVC Insulated, armoured, served, sheathed cable1100V gradeasper PWDSch. No.501(m). (Gloster /KEI / Havells/Grandlay/Polycab make) |
| 25 | S/laying of 10 sq. mm, 2 core Aluminium conductor PVC Insulated, armoured, served, sheathedcable1100VgradeasperPWDSch.No.501(b)(Gloster/KEI/Havells/Grandlay/Polycab make) |
| 26 | S/f of fire extinguisher, dry chemical type 6.00 Kg. capacity as per PWD Sch. No.1131(A). |
| 27 | ConstructionofControlcabletrenchofrequiredsize0.30x0.45Mtr.completeinall respect as per direction of E/I |
| 28 | S/B of 600x600x6mm G.I. Plate earthing with GI Strip as per PWD Sch. No. 702 |
| 29 | S/fillingof20mmstonegritinyardofsize26x36Mtr.75mmthickcompleteinall respects as per direction of E/I |
| 30 | S/Fof100mmdiaGIPipe\"B\"classforprotectionofcableonpolecompleteinall\respect as per direction of E/I |
| 31 | S/F of earth mat in the switch yard of the sub-station for all Electrical Equipments and structure by laying of M.S. rod of 32 mm in 750 mm deep trenches and earth electrode 3 Mtr. long MS round bar 32 mm dia 0.5 Mtr. belowground level as per detail specification of UPPCL complete in all respect as per direction of E/I |
| 32 | Painting of terminal gentry, lightingarrestor, Busbar gentry, lineisolator & Bus isolator structures, post insulator, fencing, Poles and other structure complete in all respects asper direction of E/I. |
| 33 | Supply,installation, testing & Commissioningof battery charger 24V/40 Amp. float cum boost battery charger with dropping diodes suitable for I/P 230V+-10% 1 phase 50 Hz type FCBC as perUPPCL specification |
| 34 | S/Etesting&Commissioningof63KVA11/0.4KVAluminiumwoundoutdoortype Transformer, latest Level as per conforming IS,as per BIS as per direction of E/I (first quality material as per latest amendment inindian standard and approvedby UPPCL) |
| 35 | S/F of fire bucket, round bottom made of GI sheet 9-11 Liters capacity as per PWD Sch.No. 1133 |
| 36 | S/F of shock treatment chart as per PWD Sch. No. 1134. |
| 37 | S/L of 1800x900x12 mm thick chequered rubber matting as per PWD Sch. No. 1136. |
| 38 | S/F of 11 KV TPMO with insulator complete in all respect as per direction of E/I.(Jaishree, azad, Rama make) |
| 39 | S/F of outdoor type 11 KV fuse setwith insulator complete in all respect as per direction of E/I (Jaishree, azad, Rama make) |
| 40 | S/L of Control Cable for metering complete as per direction of E/I (2.5 sq. mm, 2 core copper) (Gloster/KEI/Havells/ Grandlay/Polycab make) |
| 41 | S/L of Control Cable for metering complete as per direction of E/I (2.5 sq. mm, 4 core copper) (Gloster /KEI/Havells/ Grandlay/ Polycab make) |
| 42 | S/L of Control Cable for metering complete as per direction of E/I (2.5 sq. mm, 10 core copper) (Gloster/KEI/Havells/Grandlay/Polycab make) |
| 43 | S/F of brass nickel plated compression gland 10mm x 2 core as per PWD Sch. No. 503 (b) |
| 44 | S/F ofbrass nickel plated compressiongland 70mm x 3.5core asper PWD Sch. No.503 (m) |
| 45 | Providing steel furniture with 1 No. table & four No. chairs completein all respect etc. |
| 46 | S/Providingof1.98MVAr. Capacitor Bankcompleteinall respect asperUPPCLand latest vendor list |
| 47 | Supply & Erection of410-SP-29, 9 Mtr. 129 Kg Long Steel Tubular Pole complete including Exavation, backfilling with 1/6th of overall length of pole in cement concrete with 30 cm dia cement plinth around the pole and30cmabovethegroundlevel.TheFoundationofundergroundwillbeofcement conrete in the ratio of 1:3:6 alround the pole.Thecostincludesallmaterials including MS Pole Cap complete in all respect As Per SIDC No. 2(a) II Bottem section G.I S.NO. 6/110 UPPWD-2018 |
| 48 | Supply & Fixing of MS Box for controling of LED street lights and with arrangement to aviod entry of moisture as well as rain water etc. with 4 way cadmium connector & 20 A SPMCB (Legrand) including making connector complete. |
| 49 | Supply & Fixing of 415 V metal clad TPN rewireable type switch fuse unit an angle ironbracket complete in all respect as per UPPWD Sch. No. 315 |
| 50 | Supply & Wiring of sub-main with 2 Each. of 2.5 sq.mm FRLSH PVC insulated 1100 V grade single core multistarnd copper condcutor cable in existing conduit complete with supplyofallmateriallabourandT&PrequiredforpropercompletionofworkasperPWD Sch. No. 289. |
| 51 | S/EofDoublePolestructureon410-SP-55, 11Mtr. LongSTPole CompleteWithAll Respects as per SIDC Sch. No. ER 04.2 |
| 52 | Supply and fixing of LED Street light Fitting having die cast aluminium body and diffuser with driver set suitable for 110 to 130 Watt. Confirming to IP 66 Protection complete in allrespect.asperPWDSch.No.1424Cat-AA(firstqualitymaterialasperlatest amendment in indian standard ) |
| 53 | Painting of ST pole and all mountings on it with two coats of aluminium paints with an under coat of red oxide paint on length of above 10 M. support above the ground level asperdirectionofEngineerin-chargeofwork/siteincludingT&P,men&material required for proper completion of work as per SIDC Sch. No. 20.2 |
| 54 | Supply & fixinganticlimbing devicefabricated from G.I. flat of 25mm x 6 mm sizein a shape of ring of the pole size, having G.I.flat pointed fins of length 225 mm in 8 Each. andalsobarbedwirein200mm lengthabovethesaidringincludingmaterialasper SIDC Sch. No.26.1 |
| 55 | Supply & fixing of danger board fabricated from 10 guage M.S. sheet as per I.E. Rules as per SIDC Sch. No. 27.1 |
| 56 | (Internal Wiring)Supply and fixing of approved quality celling fan including all cost all materials labor, T&P etc. from proper completion of the work. (NSI) |
| 57 | Wiring point for light with 1.5 sq. mm. far. P.V.C. insulated multistrand and single core copper conductor cable in P.V.C. conduit pipe concealed in the wall, complete with 14 SWG copper earth continually wire, Piano type switch & celling rose/angle/button holder on3mmthickphenoliclaminatedbackelitesheetetc.completeinallrespectsas directed including matching colour wash. (PWD Sch.No. 131(B) |
| 58 | Wiring point for fan fresh air fan (light duty exhaust fan) in PVC conduit with 1.5 sq. mmFRPVCinsulatedmultistrandcopperconductorcableasearthwiredrawninsidethe conduit.(PWD Sch.No. 133(B) |
| 59 | Wiring point for plug with 1.5 sq.mm FR. PVC insulated multistrand single core copper conductor cable in P.V.C. conduit concealed in the wall, complete with 14 SWG copper earth continuity wire piano type switch and socket etc. complete in all respects including matching colour wash. (PWD Sch.No. 134(B) |
| 60 | Wiringpoint for exhaust fan/power plugin PVC conduit with1.5sq. mm FRinsulated multistrandcopperconductorcableasearthwiredrawninsidetheconduit.(PWDSch.No. 137(B) |
| 61 | S/F of 63 amp DP MCB (10 KA) CAT ‘A’ complete in all respect PWD Sch.No. 1011 Catt- A Type |
| 62 | Supply and fixing of 10 to 15 watt led light fittings required for proper completion of the work. |
| 63 | Supply and burying of 600 mm *600 mm*6mm Gi plate vertically for earthling with its top at least 3 meters below ground level completewith 20mm dia G.I. pipe andfunnel for watering and one earthling lead of one no 8 to 10 SWG copper wire in 15mm dia G.I. piper and copper wire will be extra 30 mm square C.I. frame with hinged cover misery housingalternatelayersofcharcoalcokeandsaltatleast150mmthickalluringetc. complete in all respect PWD Sch.No. 704 |
| 64 | Supply & wiring of submains with 2 Each. 4 sq mm & with 1 Each. earth wire of 2.5 sq mm for FRLSH PVC insulated copper conductor cube in existing PVC conduit complete including supply of all material labor and T&P etc required for proper completion of the work as directed by Engineer in charge as per UPPWD sch. No. 291 (A). |
| 65 | Supply and fixing of 6 amp. to 32 amp DP MCB (10 KA) as per UPPWD sch. No. 1009Catt. B Type |
| 66 | Supply and fixing of 63 Amp T.P. isolator as per UPPWD sch. No. 1006(B) Catt. B Type |
| 67 | Supply and fixing of 63 Amp S.P. isolator as per UPPWD sch. No. 1004(B)Catt. B Type |
| 68 | (CivilBuildingandBoundryItem) Excavationinfoundationinordinarysoil (Loam clay or sand) including lift up to 1.5 mtr. And lead up to 30m and including filling watering and ramming of exacavated earth into the Grenaches or into the space between the building and sides of foundation vetches’ or in to the all nuts and removed and disposal of surplus earth as directed by the Engineer. Charge up to a distance of 30 mm from the foundation Grenaches.(sl no 251) |
| 69 | Localfillinginplinthincludingsupplyofnecessaryqualityoflocalsandoutsidethe UPPCLpremisesincludingwateringdressingetc.Ratetoundercostofallmaterials laborandT&Petc. required fbrproper completionof work(local from approvedlocalquarry) .(Sl no 255(a) |
| 70 | Concrete with 4 cm gauge 1st class brick ballast (class 150) fine sand (F.M. 1.8 to 2.5) and. cement in proportion of 10:05:1 in foundations and under floors including supply of all materials labor and T & P etc. required for proper completion of work .(sl no 274) |
| 71 | 1st class brick (class 150) work in 1.6 cement & fine sand (F.M. 1.8 To 2.5) mortar infoundation&plinthincludingsupplyofallmaterials,LaborandT&Petc.requiredfor proper completion of work.(sl no 303) |
| 72 | 1st class brick (class 150) work in 1.6 cement & fine sand F.M. (1.8 to 2.50) mortar but in supper structure but for wall of one brick thick including supply of all materials, labor T&P required for proper completion of work. (sl no 303) |
| 73 | 1st class brick (class 150) work in 1.6 cement & fine sand F.M. (1.8 to 2.50) mortar but in supper structure but for wall of 1.5 brick thick including supply of all materials, labor T&P required for proper completion of work. (sl no 310(a)) |
| 74 | Hall brick thick (115 mm) wall with 1 class brick (class150) in cement mortar 1:4 cement & coarse sand in super structure 1/c supply of all materials labor and T&P etc. required for proper completion ofwork.(sl no6.03+6.07+6.09) (5050+240+210+105) |
| 75 | Cement concrete with 2cm gauge approved hard stone ballast coarse sand (F.M 1.8. to 2.5) & cement in propertied 1:2:1 including supply of all materials, labour, side shuttering if required and T&P etc. required for proper completion of work..(sl no 279(a)) |
| 76 | Mild’s steel 01ironinplainworksuchasreinforcedconcreteor reinforcedbrickwork (when not includedin over all rate) wrought torequiredshapeas necessary including bending for proper completion of the work & including supply of steel its wastage, bend, books and authorized over lapping shall be measured, steel shall not be supplied by the department. (sl no 504 a&b) |
| 77 | Mildsteelorironworkinheavysizessuchastrussesbuiltupgates,doorframes, record, racks roof work gates etc, wrought to required form including bolts nuts wastage etc. and their fixing required for proper completion of the work steel is not supplies bythe Department.(sl no 9.03) |
| 78 | ProvidingM.S.framesworkforB.C.C.TrenchcoversandedgingwithM.S.Angles includingcuttingbendingandvendingofM.S.angleandcuttingandweldingofM.S. barsfor reinforcement andliftingbooks asper approveddesign. Therateis including cost of all labour, materials etc proper completion of the work. (sl no 502) |
| 79 | Concreting of 40 mm thick RCC trench covers in mild steel frame work with c.c. 1:1:5:3 incement.Coarsesandand2cmgaugegradedhardstoneballastwith3mmthick loathing coat of near cement finish on top of cover complete with all labor, materials T&P etc. required for proper completion of thework but excluding gust of frames.(sl no 5.19) |
| 80 | Supply and fixing water proof craft paper in double layer with grease in between over 4 mm thick c.c. 1:1.5:3 in cement coarse sand & 12 mm gauge stone grit (c.c. 1:1.5:3 shallbe paid separately .(sl no 10.13) |
| 81 | S/F hexagonal fan box with hexagonal side of approx 800 mm in length fabricated from 16 SWG MS sheet incorporating 10mm dia. M.S. round bar duly bent for supporting fan hanger duty pained with red oxide and screwing arrangement with wiring conduit mid in theRCCroof beforeconcertingalongwithsupplyofallmateriallabour,T&P.etc required to proper completion of the work.(sl no 11.49) |
| 82 | R.C.C.workwithcementapprovedcoursesand(F.M.1.8to2.5) and2cmgauge gradedapprovedhardstoneballastinproportion1:2:4inlintersofdoors&windows excludingsupplyofreinforcementanditsbendingbutincludingitsfixing&windows excluding supply of reinforcement and its bending but including its fixing & binding the same with 24 BWG G.I. binding wire and including necessary centering & shuttering etc. and also including cost of all materials labor and T&Petc required for proper completion of the work.(sl no 283) |
| 83 | R.C.C.workwithcementapprovedcoarsesand(F.M.1.8to2.50)and2cmgauge gradedapprovedhardstoneballastinproportion1:1:5:3forlighterleamexcluding supply of reinforcement and its bending but including its fixing & binding the same with 24BWGG.I.bindingwireandI/Cnecessary centering&shutteringetc. andalsoI/C costofallmaterialslaborandT&Petc.requiredforpropercompletionofwork.(slno 285) |
| 84 | R.C.C.workwithcementapprovedcoarsesand(F.M.1.8to2.50)and2cmgauge gradedapprovedhardstoneballastinproportion1:1:5:3forlighterleadexcluding supply of reinforcement and its bending but including its fixing & binding the same with 24BWGG.I.bindingwireandI/Cnecessary centering&shutteringetc. andalsoI/C costofallmaterialslaborandT&Petc.requiredforpropercompletionofwork.(slno 284) |
| 85 | R.C.C.columnsin1:1:5:3proportionsofcementfinesandand20mmgradedhard approvedstoneballastR.C.C.columnsexcluding.Supplyofreinforcementandits bending but including its fixing & binding the same with 24 BWG G.I. binding wire and including necessary centering & shutteringetc. andalso includingcost ofall materials laborandT&Petc. requiredforpropercompletionofwork.(slno289). |
| 86 | 12 mm thick plaster with cement in proportion 1:2 cement and fine sand of 1.8 TO 2.5 Linenessmodulusoverbrickworkminimumthicknessnottobelessthan10mm including supply of all materials labor and T&P etc required for propercompletion of thework.(sl no 583) |
| 87 | 12 mm thick plaster with cement in proportion 1:6 cement and fine sandof 1.8 To 2.5 Linelessmodulusoverbrickworkminimumthicknessnottobelessthan10mm including supply of all materials labor and T&P etc required for propercompletion of the work. Add for extra labor and materials for plaster over though over though face of one brick thick wall. .(sl no 11.10+11.15) |
| 88 | 12 mm thick plaster with cement in proportion 1:2 cement and fine sandof 1.8 To 2.5 Linelessmodulusoverbrickworkminimumthicknessnottobelessthan10mm including supply of all materials labor and T&P etc required for proper completion of the work.(sl no 11.10) |
| 89 | 12mmthickplasterwithcementmortarconsistingof 1:4ofapprovedcementand coarsesandmortalincludingsupplyofallmaterialslaborandT&Petcrequiredforpropercompletion of the work same as above in item no. 24.(sl no 584(a)) |
| 90 | Providing(12x15)mmsectiongrooveinplasteratthejunctionofselling&walls, including all material labor and T&P etc required for proper completion of the work .(sl no11.19) |
| 91 | Makingdripcourse(25*12)mm in1:2cementandcoursesandincludingsupply ofall materials labor and T&P etc required for proper completion of work.(sl no 11.22) |
| 92 | R/F glass strip of 3.15mm thickness in points of floor and skirting at the time of laying, floors flush with floor level including labor, Tools and plants etc. complete (a) of 25 mmdepth.(sl no 631(a)) |
| 93 | R/F glass strip of 3.15mm thickness in points of floor and skirting at the time of laying,floors flush with floor level including labor, Tools and plants etc. complete (a) of 40 mm depth (sl no 631(b)) |
| 94 | 2.5 cm thick 1:2:4 plain cement concrete floor with cement approved coarse sand & 2 cm graded approved stone ballast (single for Bareilly lad in panels finished with 3 mm floating coat of neat cement of cement and marble dust in ratio of 5:1 as specified and giving them a uniform finish including supply of all labor and T&P etc required for Proper completion of work.(sl no 631(a)) |
| 95 | 40mm thick 1:2:4 floor without base concrete floor with cement approved coarse sand & 2cm graded approved stone ballast (shingle for barely lard in panels finished with 3 mm floating coat of near cement of cement and marble dust in ratio of 5:1 as specified and giving them a uniform finish including supply of all labor and T&P etc. required for proper completion of work.(sl no 605) |
| 96 | 2cmthickplasterordadoorskirtingconsisting1partofcementand2partsof approved coarse sand laid in panel finished with 3 mm floating coat of neat cement or cement and marble dust in ration 5:1 including supply of all materials, labor and T&P etc. required for proper completion of work.(sl no 597) |
| 97 | Supplyandfixingofsingleleaf flushdoorshutter(boiledwaterresistance,phenol maldehlje resin boded, not pressed factory made commercial quality to ISI 2202 part-a (1983)ISImarkedincludingfixingofwoodencleatsandstoppersandincludingfixing and adjustment of hings including their supply ofapproved anodizedaluminum fittings (a) 32 mm thick (sl no 8.80(a)+8.59)/(470(a)) |
| 98 | Supplyandfixingofsingleleaf flushdoorshutter(boiledwaterresistance,phenol maldehlje resin boded, not pressed factory made commercial quality to ISI 2202 part-a (1983)ISImarkedincludingfixingofwoodencleatsandstoppersandincludingfixing and adjustment of hings including their supply ofapproved anodizedaluminum fittings (b) 35mm thick double leave door shutter.(sl no 8.80 (b)+8.80 (d)+8.59)/(470(b)) |
| 99 | Supply and fixing galvanized mosquito proof zall 14*24 gauge with M.S. flat of 20*3mm size on both sides screwed or welded to window or door frame.(sl no 455) |
| 100 | p/fsteelglazedwindow&ventilatorsofstandardrolledmanormohairsteelsections conforming to is 7452-1974 as per drawing joints metered and welded with 100*14*3.15mm hold fast embedded in cement concrete lock 15*10*10 cm size of 1:3:6 proportioni.e.1partcement 3partsasapprovedcoarsesandand6 partsofgraded stoma(aggregated20mmnominalsizeincludings/fofglasspanesplainpinheaded 4mm thick nuts glazing clips and special putty of approved make complete & including a cost of red oxide paint the fabrications should confirming to 1.5. 1038 to 1975 (aluminum beading with rubber packing included 20 Kg/Sq.mtr.(sl no 9.24) |
| 101 | Painting or varnishing on new iron work in small areas or new wood work with one coat of ready mixed priming paint and three coats of approved superior quality ready mixed paint (Luxor) or equivalent brand or varnish I/C supply of all materials babour T&P etc. requiredforpropercompletionofwork.PainttobeusedshouldconformI.S. 103-1950.(sl no 642+643) |
| 102 | ApplyingBirlaorequivalentputty onnewinteriororexteriorsurfaceoveronecoat of water based cement prime of ICL or equivalent brand for smothering and leveling of the surface as per requirement and direction of engineer including cost of all material laborT & P etc required for proper completion of work.(sl no 13.21) |
| 103 | 3mmthickfloatingcoatofNeatcementfinishoverroof&walls includingsupplyof materials labor and T&P etc. required for proper completion of work (cement consumption 0.444 tag/sq.m.(sl no 20.23) |
| 104 | Supply and fixing of 110mm dia PVC pipe 6 kg./sq, cm for water supply making &rain water pipeof Tirpatior equi.makewithspecial suchastee, bend, socket,elbow, etc including cutting of pipe where necessary and including excavation of trenches for laying the pipe line of approved sixe (600*900mm)and including its back filling after testing the pipeline,wateringrammingetc.completeincludingdisposalofsuiplusmethfromthe sides 100 mtr as per defection of engineer uncharged as required for proper completionof work.(sl no 26.64a) |
| 105 | Supply andfixingof75mm diaPVCpipe6kg./sq, cm for water supply making&rain water pipeof Tirpatior equi.makewithspecial suchastee, bend, socket,elbow, etc including cutting of pipe where necessary and including excavation of trenches for laying the pipe line of approved sixe (600*900mm)and including its back filling after testing the pipeline,wateringrammingetc.completeincludingdisposalofsuiplusmethfromthe sides 100 mtr as per defection of engineer uncharged as required for proper completionof work.(sl no 26.64c) |
| 106 | Supply andfixingof50mm diaPVCpipe6kg./sq, cm for water supply making&rain water pipeof Tirpatior equi.makewithspecial suchastee, bend, socket,elbow, etc including cutting of pipe where necessary and including excavation of trenches for laying the pipe line of approved sixe (600*900mm)and including its back filling after testing the pipeline,wateringrammingetc.completeincludingdisposalofsuiplusmethfromthe sides 100 mtr as per defection of engineer uncharged as required for proper completionof work..(sl no 26.64e) |
| 107 | Providing and fluxing firstqualitywhite glazed “Orissa”patternW.C.pan 80mm Hindustan Cera make with 10 cm. H.C.I. ‘P” Trap approved make with 10 liters high level C.I. lusting cistern (Hindustan sunifa. Ashok make) I.S.I. marked with siphon brass lifting and G.I. chain pull R.s. or ci. Bracket 32 mm dia. G.I. flush pipe “b” class 2mwith brass unionsetc.32mmdieG.I.bend32mmdiaG.I.Secker15mmdiaoverflowpipewith specialsandmosquitoproofcouplingsofapprovedmunicipallasing15mmdiabrass stopcock(400gmsplasticconnect1.5”*a*1”withbrassunionsincludingsupplyofall materials labor and T&P etc required for proper completion of the work and painting of cistern and fittings with apricot paint cutting and making good the walls and floors where requiredwithcementsandandgrit.Theseatandtripshallhavetobefixedover minimum 3” thick c.c. in proportion of 12:6:1 including supply of all materials labor and T&P etc. complete. .(sl no 27.02a) |
| 108 | Providing and fixing 550 mm*400 mm wash hand basin of white glazed Carton ware first qualityI.S.I.marked(HindustanNeycer/ceramake)withR.S.orC.I.bracketpainted white15mmdiaC.P.brasspillarcockwithC.P.metalhandle(weightnotlessthan 400gms)I.S.I.markedand32diaC.P.brasswastestandardpatternwithchecknut 32mmdiaC.P.brassor“s”trapandunionscompletewithP.V.C.connection5”size includingsupply ofall materials labor andT&P etc. Requiredfor propercompletionof the work and including cutting and making good the walls and floor with cement coarse and githi fittings uses should of superior quality. .(sl no 27.07) |
| 109 | Providing and fixing 600mm*450mm beveled edge mirror of Atul,Kiran make glass with Indianpolish6.50mmthickcompletewithbackof600mm*450mm*6mmhardboard sheet fixed to wooden cleats with C.P. brass screws and washers including supply of all materials labor and T&P etc. required of proper completion of the work .(sl no 27.23a) |
| 110 | Providing and fixing 750mm*20mm size C.P. brass towel rill of approve quality (weight 275 gms. Including brackets with pair of C.P. brass brackets to fit the size of towel rail fixedonthewallonwoodencleatswithC.P.brassscrewincludingsupplyofall materialslaborandT&Petc.requiredforpropercompletionofworkandcuttingand making good the wall plaster etc. required to work. .(sl no 27.25) |
| 111 | Providingandlayingandjoining100mmdiastonewarepipelinefirstquality perfect make with special where necessary in proper slope with still mixture of cement (1.30 bag/30m andlinesan(0.45cum/ 30m inproportionof1:1includingtestingof jointsetc completely spun yarn 4.50kg / 30 mtr and including supply of all materials labor T&P etc.required for proper compilation of work. .(sl no 27.71) |
| 112 | SupplyandfixingNahaniTrapIndiamakeofheavyapprovedqualitycompletewith brassgratingNahaniTraplaidoverbasecementconcrete1:6:12includingcostof cement supply of all materials labor and T&P etc. required for proper completion of work..(sl no 27.70) |
| 113 | Provingand fixing100 mm dia C.P. grating over Nahani Trapof drainholes including cost of all materials labor and T&P etc. required for proper completion of the work. .(slno 27.87) |
| 114 | Supply and fixing of brick bllast in soak pit including supply of all labor material T&P etc. required of proper completion of work.(sl no 6.23) |
| 115 | Earthfillingunderfloorsand/orsubstationareawhenearthisobtainedfromoutside UPPCL premises including cutting and cartage upto 3 km. cost of earth royalty and lilting ate site including watering ramming in 20 cm layers & dressing of earth etc complete.(sl no 4.11) |
| 116 | Providing and injecting chemical emulsion for pre construction anti-terminate treatment andcreatingachemicalbarrierunderandaroundthecolumnpits,walltranches basementexcavationtopsurfaceofplinthfillingjunctionofwallandflooralongthe externalpermeterofbindingexpansionjointsshroudingofpipersandconduitetc. complete (plinth area of the building at ground floor only shall be measured as per I.S. 6313(part II 1981) Airlineemulsifialbeconcentrateor another approvedmaterial such as Heptachlor or chlordance will be used. The rate of application of chemical shall be as follows1 Treatment for Masonry & foundation 5 liters per sqm.2. back fill in immediate contact with foundation 7.5 litters /sqm3. Treatment of top surface of plinth filling 5 liters/sqm4. Treatment junction of wall and the floor 5 liters/sqm |
| 117 | Providing barbed iron wire fencingincluding stretchingfixing intothe post including all labor all material and T&P required for proper completion of the work the weight of hot dippedGIbarbedwirehaving12SWG-2plywiresand4pointsordinarybarbs@150mm (approx) CC should be 100gm per mtr. (Sl no. 9.913) |
| 118 | Finishing walls with water proofing cement paint of approved made like super snowcap orequivalentqualityonnewworkwiththreecoatsotgivenanevenshadeincluding supplyofallmaterialslaborT&Petc.requiredforpropercompletionofwork(Slno.660+661) |
| 119 | First class brick on edge floor laid dry. Joints sand filled. Including preparation of base to proper slope and its ramming including supply of all material labor & T&P etc required for proper completion of the work (Sl no. 12.08) |
| 120 | R.C.C.workswithcementapprovedcoarsesandand2cm(3/4)”:gaugeapproved stoneballastintheproportion1:1:5:3(1cement:6aggregateincolumnexcluding supplyofreinforcementanditsbendingthesamewith24SWGbindingwireand necessarycenteringandshutteringetc.andalsoincludingsupplyofallmaterials labours and tools and plants etc required for proper completion of works Strength of theconcrete shall no be less then M-150 (Sl no. 5.17) |
| 121 | Supplyandlayingof80mmthickcementconcreteinterlockingtilesgreycoloured shaped over 40 mm thick layer of local sand including supply of all material labor and T&P etc including cost of sand required for proper completion of the work. (Sl no.12.27) |
| 122 | Supply and installation of single phase submersible pump of 1 H.P. outlet 32mm dia or more head 78/30, discharge 1100/2800 LPH ofK.S.B. or equivalent makeIidia Marka handpump-IIincluding150mmdia70mdeepboringuptosecondstrataincluding supplyandlowering110mmto63mmdiaPVCpipe(4m110m&46m43mm,6 kg/sq/mtr.)withrequiredstrainer reducerjoining90mm dia longcylinder 32mm diaGI pipe 3m long including supply and filling of course sand of approved quality approx. 15 cu.m)includingdevelopingtheborewelltoaachiveclearandsandfreewaterfor continuous60min.includingcostofallmateriallabourandT&Panditscartagefor installationofhandpumpcompleteasperdrawingincludingexcavationofearthand laying25mmc.c.floor1:2:4withcementc.sandand20mmstoneballastwithwater proofing compound over 100mm thick c.c.1:6:12 with cement c sand and 40 mm brick ballast andmakingsideedge115mm thickand300mm deep withbrickwork1:4and plaster the same with 1:4 mix with neat cement finish also including 115mm wide drain in 1:4 brick work & plaster all around the peripheral of platform complete including supplyof all materials labour and T&P required for proper completion of the work. (Sl no. 22.80) |
| 123 | Oneprimingcoatandtwocoatoildistemperonnewworkincludingsupplyofall materials labor and T&P etc. required for proper completion of work (Sl no. 13.17+13.14) |
| 124 | Providing and laying of 10mm thick virtified floor tiles of approved brand and sample in size600*600mm offirst quality ofbell, Johnsonorequivalent makeshadecolor and patternasapprovedbyEngineerinchargelaidoverbasecementmortar1:4mix including finishing the joints etc required for proper completion of work. (Sl no. 12.26 a) |
| 125 | Flooring with 19mm thick ketastone or skirting over base cement mortal 1:4max and joined with grey cement slurry mixed with pigment to match the shade of slab including supply of all materials labor and T&P etc. required for proper completion of work. (Sl no.12.24) |
| 126 | Providing and fixing MS Holder bat clamps of approved design for H.C.I. 50 mm dia and lipe ambedded in and included cement concrete work 10cm*10cm (1 cement 2 course sand and 4 graded stone aggregate) including cost cutting holes and making good the walls including supply of all materials labour and T&P etc. required for proper completion of work. (Sl no. 27.33) |
| 127 | S/layingchickenmeshof(20mm) hexagonalheavy quality over roofsjoints ofroof asper direction of the Engineer in charge (Sl no. 27.33) |
| 128 | Supply andplantingEnglishroseplantsAshoka,pendula,mango,Neemetc.inbeds includingcost ofall materialslabor and T&P etc required for proper completionof thework. (Sl no. 23.13) |
| 129 | Diggingpitsof60cmdiaand60cmdeepinordinarysoilandrefillingthesamewith excavated earth mixed with manure of sludge in the ratio of 2:1 by volume and flooring withearth dressingincludingremoval ofrubishandSurplusearthifany withall leads and lifts etc (cost of manure and earth local sand to be paid separetely) (Sl no. 23.09) |
| 130 | Fixinggalvanizedcorrugatedironroofing24BWGinpositionincludingsupplyof material labour and T&P etc. required for proper completion of work. (Sl no. 23.09) |
| 131 | Fabrication,Supply & Fixxing of work information board in M.S frame made by 50 mm dia sqaurepipeofstainlesssteelgradeSS-304&16mmthickbaseplatewithback supporting of bracing by MS flat of 25x6 mm and 2.85 Mtr. Long supporting leg made from 65mm pipe SS-304 grade with proper grouting arrangement. The board should be Retro reflective type in green colour with white letters as required and shall be fixed at a height of 1.2 Mtr. from ground by providing 0.45x0.45x0.60 Mtr. cement concrete stone pad |
| 132 | Supply, Stringing, tensioning, jointing and binding of all sizes of G.I. / G.S. wire on Steel tubular poles. The binding of G.I. / G.S. wore shall be done with the specified size of G.I. wire or as per direction of Engineer-In-Charge on the specified countings on the poles. Weight of G.I. /G.S. Wire is to be determined by measuring taut horizontal distance between centres of two adjacent pole and compounding the weight of wire by using a standard table of weights of G.I. /G.S. wire. 2% extra may be added for sag at the direction of the Engineer-In-Charge. All inclusive of T& P, Men & material for proper completion of works as per direction of Engineer-In Charge of work/site and in street adhrence to Drg and Work No. UPSIDC/ED |
| 133 | Supply & grouting of stay rod, complete with all its components specified here-in -under and supply & fixing of stay clamps including all bolts, nuts, washers etc. to the polealong with binding nozzling and requisite tensioning of stay wire of under given size together T&P men & material for proper completion of work as per direction of Engineer- in-charge of work/site and strict adhrerrence to Drawing work no.UPSIDC/ED/ complete in all respect. |
Copyright © 2025 · All Rights Reserved. Terms of Usage | Privacy Policy