| 1 | Earthwork in foundation excavation up to1.5m, ramming bressing both sides backfilling and dosposal of surplus soil within lead of 50m |
| 2 | Cement concrete in foundation and plinth with stone ballast size 40 mm including curing and compaction etc in1:4:8 mix |
| 3 | Brick work in foundation and plinth using brick of class designation 75 in CM 1:6 |
| 4 | DPC with RCC 1:1:5:3 mix |
| 5 | Brick work in Superstructure using brick of class designation 75 in CM 1:6 |
| 6 | reinforced cement concrete work including curing compaction , finishing with rendering in cement sand martar 1:3 and making goods and joints excluding cost of centering shutiering and reinforcement in 1:1:5:3 |
| 7 | Providing and fabricating reinforcement for RCC work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) in foundationand super structure up to 4.5m height aboveplinth level hot rolled deformed (IS: 1139) cold twisted (IS: 1786) bars |
| 8 | Centering and shuttering with plywood or steelsheets including strutting, propping, bracingboth ways with wooden members andremoval of from work |
| 9 | p&f cement concrete on roof |
| 10 | S&f Mosic tiles on roof |
| 11 | 20mm thick plaster 1:6cm including curing and racking of joints. Etc. |
| 12 | Providing and applying white cement basedputty over plastered surface to prepare thesurface even and smooth complete (PWDBSR-2022 - Less-10%) |
| 13 | Finishing walls with Acrylic Smooth exteriorpaint of required shade including all scaffolding.New work ( Two or more coat incuding base coat of water proofing cementpaint) -(PWD BSR -2022 Less-10%) |
| 14 | Wall painting with plastic emulsion paint of required shade including all caffolding.New work ( Two or more coat incuding base coat ofwater proofing cement paint) -(PWD BSR-2022 Les-10%) |
| 15 | s&f iron door |
| 16 | fixing of iron door |
| 17 | Providing and fixing steel glazed doors windows and ventilator shutters of standard rolled steel section (IS 1038-1983): (PWD BSR-2022Less-10%) |
| 18 | s&f wire mesh on section window |
| 19 | s&f ironbars on section window |
| 20 | enamel painting on door and window |
| 21 | earth work in filling with ordinary soil |
| 22 | carriage of earth lead one km |
| 23 | Cement concrete in foundation and plinth with stone ballast size 40 mm including curing and compaction etc in1:6:12 mix |
| 24 | s&f polished kota stone flooring |
| 25 | s & f glaze tiles on wall |
| 26 | sok pit Earthwork in foundation excavation up to1.5m, ramming bressing both sides backfilling and dosposal of surplus soil within lead of 50m |
| 27 | Brick work in foundation and plinth using brick of class designation 75 in CM 1:6 in cm 1:6- 112mm thick |
| 28 | brick work in foundation and plinth using brick of class designation -75 in cm 1:6 |
| 29 | 20mm thick plaster 1:6cm including curing and racking of joints. Etc. |
| 30 | reinforced cement concrete work including curing compaction , finishing with rendering in cement sand martar 1:3 and making goods and joints excluding cost of centering shutiering and reinforcement in 1:1:5:3 |
| 31 | Providing and fabricating reinforcement for RCC work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) in foundationand super structure up to 4.5m height aboveplinth level hot rolled deformed (IS: 1139) cold twisted (IS: 1786) bars |
| 32 | wiring for fan/light pinots in pvc condut pipe as per specification |
| 33 | wiring for circuit /submain as per specification |
| 34 | s&f pvc water storage tank |
| 35 | s&f bib cock |
| 36 | s&f wash basin |
| 37 | providing and fixing chlorinated polyvinyl chloride pipes having thermal stability for hot and cool water supplyincluding at all CPVC plain &brass threaded fitting i/c fixing the pipe with clamps at 1 metr spacing . This including joints of pipes & fitting with one step CPVC solvent cement and testing of joints complete as per direction of engineer in charge 20mm normal size |
| 38 | s&f fully way value 20mm |
| 39 | s&f sink |
| 40 | providing and fixing granite stone slab mirror polished and machine edge cut in walls pillers step shelvers sillsabove 3600cm tiles |
| 41 | s&f urinal |
| 42 | s&f pvc pipe 110 mm |
| 43 | s&f europain wc plan |
| 44 | s&f cistern |
| 45 | yojna board and contingency charges |
| 46 | between pipe & flange, rubber washer & nut bolts etc. complete in all respect. 80mm dia |