| 1 | Installation of Vertical Bored cast in situ RCC piles of following diameter in all types of soils, using Standardised Concrete Mix of following grade, with sulphate resistant Cement or OPC/PPC, etc and Crushed Stone Sand and 20mm and down graded HBGS jelly coarse aggregate. The rate includes cost for placing of reinforcement cage in bore hole in correct position, cost of boring to the required depth with Bentonite solution with temprory casing of required length, conveyance of RMC to site and pouring concrete using Tremine pipes, conveyance of all materials to the site including all tools and plants, shifting the plants and equipments from one point to another, excavtion of mud pits for circulation of Bentonite soultion, closing the mud pits to original level and mud removal with initial lead and lift but including dismantling the concrete above the cut off level etc complete as directed by the departmental officers including socketing. The reinforcement cage should be welded properly for lifting. The concrete cubes to be tested as per IS 456-2000. Acceptance criteria by clause 16.1. Frequency of testing as per 15.2.2. Testing to be conducted at both the ends at site as well as RMC plant. Pile driving depth should be decided by the departmental officers at site. The length of pile for payment shall be measured from top of shoe to the bottom of the pile cap.( Cost of Reinforcement provided for Pile and Welding charges shall be measured and Paid separately ) |
| 2 | 450mm Dia |
| 3 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrockrequiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum |
| 4 | Supplying and filling in foundation, basement, etc with filling crushed stone sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. |
| 5 | Supply and filling in foundation and basement with Gravel in layers of not more than 15cm.thick well rammed watered and compacted with surface vibrator, watered and consolidated etc. complete complying with standard specification and as directed by the departmental officers. |
| 6 | Providing of Granular Sub base using Grade I materials of table 400 -1 of Morth with minimum CBR 30 spreading in uniform layers with motor grader on prepared surface, mix in by palce method at OMC and compacting with Vibratory Roller to achieve the desired density including all labourcharges etc, complete as per technical specification and as directed by the departmental officers. Morth - Rev V No. 111,112,401,900 |
| 7 | ProvidingAnti-termite treatmentto soil adjecentand under building foundation, plinth periphery of the building by application of chemicals of IS 63613 part I to IV in stages to suit the progress of work consist as per the detailed specificationasbelow. Includingbreakingoftermite mounds, making holes with crow bar, closing the holes after the treatment and including cost of chemicals, labour charges, transport and storing etc., complete and as directedby the departmental officers. |
| 8 | Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers -Mixing by mechanical means |
| 9 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require onlynominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener,side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid). |
| 10 | Supplying and erecting centering for plane surfaces such as RCC Floor Slab, RoofSlab, Loft, Landing Slabs, etc with necessary supports and strutting upto 3.60m height in allfloors with all cross bracings using MS Sheets made of 10 gauge thick welded with MS angle of Size 25mm x 25mm x 3mm for boarding laid over steel adjustable span of size 2m x 2m (expandable upto 3.60m) and supported by Steel Adjustable Telescopic Props of Size 2m x 2m (expandable upto 3.60m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick) , etc complete complying with standard specifications. Steel adjustable span and Steel Adjustable telescopic props shall be provided as directed by the departmental Officers. (Payment for centering shall be given after the concrete is laid). |
| 11 | Supplying and erecting centering for plane surfaces such as RCC Floor/Roof Beam, Lintels, Cantilever Beams, Bed Blocks etc.. with necessary supports and strutting upto 3.60m height in all floors with all cross bracings using MS Sheets made of 10 gauge thick welded with MS angle of Size 25mm x 25mm x 3mm for boarding laid over Steel adjustable Span of Size 2m x 2m(expandable upto 3.60m) and Silver Oak Joists of Size 10 x 5 cm spaced at 50cm to 60cm c/c and supported by Steel Adjustable Telescopic Props of Size 2m x 2m (expandable upto 3.60m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick) Spaced at not more than 50 to 60cm c/c , etc complete complying with standard specifications. Steel adjustable span and Steel Adjustable telescopic props shall be provided as directed by the departmental Officers. (Payment for centering shall be given after the concrete is laid). |
| 12 | Supplying and erecting steelcentering including necessary supportsFor plane surfaces such as rectangular or square RCC columns etc. which require only nominal strutting using mild steel sheets made of 10 gauge thick welded with MS angle size 40mm x 40mm x 5 mm and supported by Steel Adjustable Telescopic Props of Size 2m x 2m (expandable upto 3.60m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick).etc..complete in all floors complying with standard specifcation. Steel Adjustable telescopic props shall berovidedas directed by the departmental Officers. (Payment for centering shall be given after theconcrete is laid). |
| 13 | Providing and laying in position, Standardised Concrete Mix M-25 Grade by insitu machine mix concrete adopting weighing batch method in accordance with IS:456-2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement content of 350 kglm3 and maximum water cement ratio of 0.50, including admixture (plasticiser / superplasticiser) in recommended proportions as per IS:9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability with about (5.0 Cu.m) 7730 kg. of 20mm machine crushed stone jelly and with about (3.3 Cu.m) 5156 kg. of 10-12mm machine crushed stone jelly and with about (4.79 cu.m’) 7670 kg. of crushed stone sand, but excluding cost of reinforcement grill and fabricating charges, centering and shuttering and also including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor/ roof slabs wherever necessary without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers. The coarse and fine aggregates to be used should comply with the requirements of IS Standards. (No separate payment will be made by the Department for the excess usage of materials). |
| 14 | Foundation and Basement |
| 15 | For Ground floor |
| 16 | Vibrated Reinforced Cement Concrete M25 (Design mix) using20 mm ISS HBG graded metalincluding cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for CC Pavement |
| 17 | Vibrated Reinforced Cement Concrete M25 (Design mix) using20 mm ISS HBG graded metalincluding cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for MAT CONCRETE |
| 18 | Vibrated Reinforced Cement Concrete M25 (Design mix) using20 mm ISS HBG graded metalincluding cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for SIDE WALL |
| 19 | Vibrated Reinforced Cement Concrete M25 (Design mix) using20 mm ISS HBG graded metalincluding cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete, working at heights, hire charges for Hire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for DECK SLAB |
| 20 | Suppling and fabricating and placing in position MS(or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost ofsteel and binding wire also in all floors. |
| 21 | Brick work in following Cement Mortar using best quality Burnt Clay Brick of size 9” x 4 3/8” x 2 3/4” with class designation of 7.5 conforming to IS 1077-1992 for foundation and basement including Cost of Mortar Plasticizer curing, etc.,completecomplying with standard specification and as directed by the departmental officers. Brickwork shall be done as per IS 2212-1991 adopting English Bond generally.other type of bond shall be done as directed by the Executive Engineer in charge. |
| 22 | Basement Floor |
| 23 | Ground Floor |
| 24 | Special ceiling plastering and finishing the exposed surface of all RCC items of work such as slabs, beams, sunshades, facia, canopy slab, staircase waist slab, landing slab etc., with Cement Mortar 1:3 (One Cement and Three Plastering Sand) 10mm thick including mortar plasticizer at 200ml per 50Kg of cement used, hacking the surfacesand curing, etc., in all floors complying with standard specification and as directed by thedepartmental officers |
| 25 | Plastering with Cement Mortar 1:5 (One cement and Five Plastering sand),12mmthick in all floors including mortar plasticizer at 200ml per 50Kg of cement used, curingetc. complete complying with standard specification and as directed by the departmentalofficers. |
| 26 | UPVC Window Specification:Supplying and fixing UPVC (Un-PlasticizedPolyvinyl Chloride) Windows of casement type (open) from the profile the size of outer frame 60mm x 58mm and shutter profile are reinforcementwithGI/1mm125GSMand100%corrosion free,theprofilesaremultichamberedsectionswithwall thick of 2mm. The EPDM rubber (black colour) covered with overalltheedgesofframeandshuttertheshutterwillbe providedwithEspagmultipowerpointlocksandalsoit operates as handle.The corners and joints should be welded andcleaned. Radiationsfreepinheadedplainorbrown colour glass 4mm thick should be provided to the shutter and itshouldnotallowleakageofwaterevenatmostranging storms and should have key lockable action, security protective hinges, strong locking systems and as per size for arrestingnoiseandenergyloss.Theconnectingmechanism betweensashandouterframethatenablesopeningofthe window.The window should be fixed to the wall with 100% packing with screws and silicon packing all round the frames. ThewindowshouldbegotapprovedfromtheExecutive Engineer before use on work. |
| 27 | Supplying and fixing Mild Steel grills for windows, ventilators etc.,complete complying with standard specifications and as directed by the departmental officers. |
| 28 | Painting the walls with two coats of cement paint over one coat of cement primer as instructed by the departmental officers including preparation of surface curing,etc., complete in all floors complying with standard specifications and as directed by the departmental officers. (The colour and shade of the cement paint shall be gotapproved by the Executive Engineer before use of work). |
| 29 | Supplying and laying of Interlocking Paver Block Stone 83mm thickOver a base layer of crushed stone sandfilling incl. Cost of materials laying and Labour charges etc complete complying with the standard specification and as directed by the departmental officers. |
| 30 | Supplying & Laying 200MicroN LDPE Sheet below RCC Flooring |
| 31 | Providing and fixing Bitumen Pad for Expansion joint in between pavement slabs to 20mm thick and fixed as shown in the drawing including cost and conveyence of expansion joints including shalimar pad and joint sealent etc, complete as per standard specification |
| 32 | Weathering course in brick jelly lime concrete using broken brick jelly of size 20mmuniform gauge in pure slaked lime (no crushed stone sand to be used) to the proportionof brick jelly to lime being 32:12.5 by volume and laid over the RCC roof slab in a single layer of required slope and finished by beating the concrete with wooden beaters ofapproved pattern, keeping the surface constantly wet by sprinkling lime jaggery water, etc., complete as per standard specification and as directed by the deparmental officers. |
| 33 | Finishing the top of roof with one course of machine pressed tiles of following size ofapproved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone Sand)12mm thick mixed with water proofing compound conforming to ISS at 2% by weightof cement used and the joints pointed neatly to full depth of tiles with the same cementmortar mixed with red oxide and water proofing compound including curing etc., completecomplying with standard specification and as directed by the departmental officers |
| 34 | Using Pressed Tiles of size 200mm x 200mm x 16mm to 18mm |