| 1 | Electrical Work |
| 2 | Dismantling of existing damage O/D metering unit & related parts then Loading carriage & unloading of outdoor C.T./P.T. unit (Old/Damage) from Work Site to Kesco Store. |
| 3 | Loading carriage & unloading of outdoor C.T./P.T. unit (New) from Kesco Store to Work Site. |
| 4 | Erection of new O/D metering unit on base channel/angle on double pole including fixing with complete work in all respect. And also energized with KESCo. mains(All accessories provided by contractor as per GTP Approved) |
| 5 | Safe Carriage 11 KV I/D or O/D Cable Box from Store to work site. |
| 6 | Making & mounting of 11 KVI/D or O/D Cable box suitable for 3x70, 3x120 and 3x185sqmm XLPE Cable with complete connections in all respect as per site requirement. |
| 7 | Loading, carriage, unloading and tacking out from drum of XLPE cable size 3x70/120/185from store to work site up to average distance of 20 km.for Double Metering System with Infra |
| 8 | Loading carriage & unloading of A.C.S.R.Wease conductorfrom store to work site up to average distance of 20 km.for Double Metering System with Infra |
| 9 | Loading carriage & unloading of old and Used ST POLEfrom store to work site up to average distance of 20 km. for Double Metering System with Infra |
| 10 | Laying of 11 KV XLPE Cable by digging trench including cost of bricks and sand as per standard specifications of RESPO. |
| 11 | Laying of 11 KV XLPE cable in air as per RESPO. |
| 12 | Laying, Stringing & Jumpering of A.C.S.R.Wease conductor with complete work as per site requirement. |
| 13 | Erection of Single Pole alongwith grouting & making plinth by digging of pit. Including all fitting (All accessories excluding M.S. angle/channel provided by contractor) |
| 14 | Erection of Double Pole alongwith grouting & making plinth by digging of pit. Including all fitting (All accessories excluding M.S. angle/channel provided by contractor) |
| 15 | Erection of Earth Rod complete & Earthing connection of pole or O/D metering unit |
| 16 | Panting of pole with one coat of Red oxide Two coat AL Paint including cost of 1st class Enamel paint. |
| 17 | Loading, carriage & Unloading of M.S. Items (8040 Kg.) from kesco store to site and work site to store for Double Metering System with Infra |
| 18 | Fabrication/modification of different M.S. Item as per site requirement. |
| 19 | Installation and Commissioning of 11 kv.H.T. T.V.M. with TOD Facility with L.P.R. as per site requirementfor Double Metering System with Infra |
| 20 | Erection of Stay Set complete. |
| 21 | Earthing of Pole for double metering work. |