| Sl. No. | Item Description |
| 1 | IConstruction of Control Room with electrification |
| 2 | Clearing juliflora jungle with uprooting including all labour lead lift etc., complete. |
| 3 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m inhard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders. |
| 4 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m in soft disintegrated rock laterite soft rock or kankar not requiring blasting, etc., complete. |
| 5 | Earthwork excavation in medium rock and dense medium rock requiring blasting. (As instructed by the Engineer at site) |
| 6 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete.(As instructed by the Engineer at site) |
| 7 | PCC 1:3:6 mix using 40mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. |
| 8 | PCC 1:3:6 mix using 20mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. |
| 9 | RCC 1:1.5:3 using 12 to 20mm (machine crushed) metal for raft foundation without formwork including cost of all materials, labour lead, lift, etc., complete |
| 10 | RCC 1: 1.5:3 using 12-20mm HBS metal (machine crushed) metal for concretewith centering shuttering form work including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement.. |
| 11 | Column up to Basement |
| 12 | Grade Beam |
| 13 | Column above basement, upto GF roof level |
| 14 | Plinth beam PB |
| 15 | Lintel beam |
| 16 | sun shade |
| 17 | Roof beam |
| 18 | Brickwork in CM 1:5 mix using II class chamber bricks of size 9\"x 4 3/8\"x2\"3/4\" for super structure including cost of all materials, labour, lead, lift, curing, etc., complete. |
| 19 | Basement |
| 20 | Super Structure |
| 21 | Flooring with PCC 1:3:6 mix using 40 mm HBS metal for flooring150mm thick (machine crushed metal) including cost of all materials labour lead, lift, etc., complete. |
| 22 | RCC 1:1.5:3 using 12 to 20mm (machine crushed) metal for Control Room flooring concrete 100 mm thick with formwork including cost of all materials, labour lead, lift, etc., complete. but excluding cost of steel reinforcement |
| 23 | RCC1:1 1/2:3 using 12mm to 20 mm HBS metal (machine crushed) for roof slab concrete of 130 mm thick with formwork including cost of all materials, labour, lead, lift, centring shuttering , curing, etc., complete. But excluding cost of steel reinforcement. (Ground roof slab) |
| 24 | Plastering with CM.1:5 mix using 12mm thick for inside & outside walls, including cost of all materials, labour, lead, lift, etc., complete. |
| 25 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. |
| 26 | White washing two coats with White cement approved qualityover a primary coat for ceiling, exposed surfaces of wall, beam, slab, sunshade, lintel, etc, including cost of all materials, lead, lift, etc, complete. |
| 27 | Colour washing two coats with Exterior Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor outside wall including cost of all materials, labour, lead, lift, etc., complete. |
| 28 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 29 | Providing UPVC (Un-Plasticized Polyvinyl Chloride) Door: Providing and fixing casement doors fabricated from un-plasticized polyvinyl chloride (uPVC) sections. Profiles: The profiles should be three chamber system which provides high insulation properties with outer frame 60mm x 55mm with an outer wall thickness of 2.4mm. The window unit should be designed with all corner joints mitred and fusion welded. Windows should be steel reinforced with 25 x 24 x 25mm steel reinforcement with a thickness of 1mm to have dimensional stability. The sash should be of 60 x 102mm. The mullion should be of 60 x 74mm. The profiles should have co-extruded seals. |
| 30 | Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride) Windows of casement type (open) from the profile the size of outer frame 60mm x 58mm and shutter profile are reinforcement with GI/1mm 125GSM and 100% corrosion free, the profiles are multi chambered sections with wall thick of 2mm. The EPDM rubber (black colour) covered with over all the edges of frame and shutter the shutter will be provided with Espag multi power point locks and also it operates as handle. The corners and joints should be welded and cleaned. Radiations free pin headed plain or brown colour glass 4mm thick should be provided to the shutter and it should not allow leakage of water even at most ranging storms and should have key lockable action, security protective hinges, strong locking systems and as per size for arresting noise and energy loss. The connecting mechanism between sash and outer frame that enables opening of the window. The window should be fixed to the wall with 100% packing with screws and silicon packing all round the frames. The window should be got approved from the Executive Engineer before use on work. (As instructed by the Engineer at site) |
| 31 | Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride) Louvered Ventilators of from the profile the size of outer frame 60mm x 58mm and shutter profile size of 60 x 78mm both profiles are reinforced with GI/1mm 125GSM and 100% corrosion free, the profile are multi chambered sections with wall thick of 2mm. The EPDM rubber (black colour) covered with all over the edges of frame and shutter. The corners and joints should be welded and cleaned. Radiations pin headed glass 4mm thick should be provided in the louvers. The window should be fixed to the wall with 100% packing with screws and silicon packing all round the frames. The ventilator should be got approved from the Executive Engineer before use on work. |
| 32 | M&F in position of PVC door shutter made ofSingle Panel laminated Plastic sectionand PVC extracted shutter frame of size 24 x 60 mm including cost of 3 nos 85 mm butt hinges for single leaf door of size 0.80 x 2.00 m with 2 No aluminium handle and 2 nos 150 x 2 mm aluminium towel bolt hinges etc., complete. |
| 33 | Supplying and fixing of two side polished 20-30mm tk.cuddapah slab for cupboard, kitchen platform etc., including cost of all materials, labour, lead, lift, etc., complete |
| 34 | Dadooing with glazed tiles of best approved quality of make johnson, neycer etc, over CM 1:3, 12mm thick including cost of all materials, labour, lead, lift, etc., complete. |
| 35 | Flooring with approved Vitrified tiles 600x600mm of approved Quality, design & colour (Johnson or equivalent make)laid in cement mortar 1:3 - 20mm thick including pointing with same coloured cement using 0.4kg/sqm, finishing the joints, including cost of all materials, water charges,labour, lead, lift, etc. complete. |
| 36 | Flooring with approved acid proof tiles over cement mortor 1:3 20mm thick in floor including pointing with white cement finishing the joints flush pointing the surface etc including cost of all materials, water charges labour, lead, lift, etc. complete.(Battery Room) |
| 37 | Providing one coarse of pressed tiles of 20x20x2cm embedded with CM 1:3 mixed with crude oil at 10% by weight of cement and pointed with same oiled mortor including all material, labour, lead, lift etc complete |
| 38 | Supplying and fixing in position of GI angle 50x50x6mm@ 75cm c/c to the required length for supporting the cable in the duct, as per the direction of site Engineer including cost of all materials, lead, lifts, and cutting the GI angle required length and labour for fixing etc., complete. |
| 39 | Supplying and fixing in position of MS channel 110 x 50mmrequired length for fixing the cable duct side wall, as per the direction of site Engineer including cost of all materials, lead, lifts, and cutting the MS channel required length and labour for fixing etc., complete. |
| 40 | Supplying and laying PVC pipe 110 mm outer die 6kg / cm2 ISI make for laying the Sewer line including cost of pvc pipe coupling labour for cutting laying fixingtightening etc. including earth work excavation and refilling trench etc complete |
| 41 | 110mm dia PVC pipe |
| 42 | 110mm dia PVC Bend |
| 43 | 110mm dia Pvc TEE |
| 44 | 100mm dia PVC Cowl |
| 45 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 46 | Supplying and fixing in position of 25mm dia pvc pipe of 10 kg/sq.cm pressure from the approved manufacturer apollo, chemplast, avanplast, valarmathi, usha, vimal etc., confirming to IS 4985 of 1968, 4984 of 1970 including cost of all special fixtures labour lead, lift, etc., complete. |
| 47 | Supplying and fixing of 1000 lit capacity sintex tank of approved quality including cost of labour for fixing etc., complete |
| 48 | Supplying and fixing of 15mm high quality brass Chromium plated screw down bib cock (Heavy Type) such as leader, zeolite and zenith of any other approved quality cost of all materials, labour, lead, lift, etc., complete. |
| 49 | Refilling with excavated soil other than sand in foundation and sides of masonry, consolidation as per std. specn. With water including all labour, lead, lifts. etc, complete. |
| 50 | Removing the excess earth to the basement area as instructed by field engineer including all labour lead, lift, etc., complete. |
| 51 | Supplying and filling of Red gravel in the basement filling stacking to the department gauge, labour for filling, watering and consolidation, including cost of all materials, lead, lifts, labour, etc, complete. |
| 52 | Supplying and fixing of RCCB safe trip of appd LEGRAND , ISI make , 25amps with suitable box including cost of all materials labour, lead, lift, etc., complete as per standard specification. (As instructed by the engineer at site) |
| 53 | Wiring with 2x1.50 sq.mm PVC unsheathed copper multistandcable of 1100 V grade in suitable pvc rigid pipe in wall or ceiling with pvc accessories with TW switch box in flush with wall covered with hylum sheet of 3mm thick with painting of suitable colour with continuous earthwire connection of 14 SWG TC wire for light and Fan points(SD 23) |
| 54 | Wiring with 2x1.5 sq.mm (22/0.3) PVC insulated SC unsheathed Cu.conductor of 1100 V grade in suitable PVC rigid pipe concealed in wall and ceiling with PVC accessories in in flush with wall, with 150mm x 100mm x 113mm TW switch box with 3 mm thick hylum sheet cover for 5 A 3 Pin non interlocking CS plug with continuous earth wire connection of 14 SWG TC wire and making good of the concealed portion with suitable colour for concealed PVC Plug point. (As instructed by the engineer at site) |
| 55 | Supply and fixing of 40 W LED industrial type fitting \"INDURA\" (Philips /Crompton) complete with conduit pipe suspension, with PVC unsheathed copper leads from the terminals to the fittings with LED lamps. (As instructed by the engineer at site) |
| 56 | Wiring with 2x4 sq.mm Pvc unsheathed copper multistand cable of 1100 V grade in suitable pvc rigid pipe in wall or ceiling with pvc accessories with 150mm x 100mm x 75mm T.W switch box in flush with wall covered with 3mm tk. Hylum sheet for 15 amps 3pin flush typenon interlocking C.S plug including pin top with painting of suitable colour with continuous earth wire connection of 14 SWG T.C. wire for plug point.(As instructed by the engineer at site) |
| 57 | Supplying and fixing of 23 cm angular holderwith EI fancy shade glass with 9 W LED bulb. |
| 58 | Supplying and fixing of 1400mm (56\") sweep AC ceiling fan with regulator with Suitable down rod on the existing clamps of crompton / rally / Orient including cost of all materials lead, lift etc., complete. SD(114) |
| 59 | Supplying and fixing of water tight Bulk head fitting with guard(philips, bajaj, k-lite, cromption greaves) suitable for incandescent lamp with guard and 8W LEDbulb. |
| 60 | Supplying and fixing of 375mm (15\") sweepheavy duty AC Exhaust fan with MS/Fibre louvers shutters arrangements of approved ISI quality complete with necessary wall opening and making good of the wall |
| 61 | Supplying and fixing of digital LED Wall Clock of approved quality such as Ajantha / Seiko/ Citizen etc including transport, fixing charges etc complete. |
| 62 | Supplying and fixing of 4pole32 Amps Isolator 1 No with MCB box 4 poleincludingterminal block for testing purpose at Controlroom, cost of all materials, lead, lift, labour charge, etc., complete. |
| 63 | Earthing as per standard specification complete with necessary masonry work. SD(221) |
| 64 | Providing and fixing sanitary fitting consisting of Neycer / parryware of oriya pattern Water Closet 45cm with P/S trap connecting with PVC ventilating shaft and Y bend complete, including cost of all material, labour, lead, lift, etc, complete. |
| 65 | Providing and fixing sanitary fitting consisting of Neycer / parryware of European Water Closet with \"P\" or \"S\" Trap with Double Flapped Seat and Seat Cover with Brass Hinges and 10 litre capacity PVC Low Level Flusing Tank with all internal fittings including cost of all material, labour, lead, lift, etc, complete. |
| 66 | Supplying and fixing of best quality of mirror of size 300 x450mm mirror with soap tray, towel stand, screw and fixing near the wash basin, teak wood round block, including cost of all material,labour, lead, lift, etc, complete. |
| 67 | Supplying and fixing 100x50mm PVC floor trap in bath room with one pvc door bend shoe of 50mm.dia including cost of all etc., complete |
| 68 | Supplying and fixing of wash basin of size 500x400 mm of approved quality neycer / parrys ISI including cost of wash basin with pedestal cock fixing using rag bolt and nut 15mm dia pvc connecting hose and outlet using 50mm dia pvc waste water pipe for outlet CP angle valve with all accessories including cost of all materials, labour, lead, lift, etc., complete. |
| 69 | Supplying and fixing of approved quality of Brass Chromium plated towel rod of size 90cm and fixing the same over the teak wood round block and soap tray (pvc) in bath room including cost of all materials, lead, lift, etc., complete. |
| 70 | Providing PVC down fall pipe using 110mm dia 4 Kg / Sqcm, PVC pipe and pvc clamp line supreme etc., including fixing PVC washer type door bend & shoe, in correct position and connecting from the roof slab including cost of all materials, labour, transport lead, lift, etc., complete, including pvc accessories and washers. |
| 71 | Construction of septic tank arrangements with inspection chambers including cost of all materials, labour, transport lead, lift, etc., complete. |
| 72 | II Lighting Pole plinth works |
| 73 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m inhard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders. |
| 74 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m in soft disintegrated rock laterite soft rock or kankar not requiring blasting, etc., complete. |
| 75 | Earthwork excavation in medium rock and dense medium rock notrequiring blasting. |
| 76 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete.(As instructed by the Engineer at site) |
| 77 | PCC 1:3:6 mix using 20mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 78 | PCC 1:2:4 using 12 to 20 mm HBG machine crushed metal for plinth with formwork including costof cement all materials,labour,lead lift, curing etc., complete. - PCC wall with form |
| 79 | PCC 1:2:4 using 12 to 20 mm HBG machine crushed metal for plinth with out formwork including costof cement all materials,labour,lead lift, curing etc., complete. - PCC wall with form |
| 80 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. (As instructed by the Engineer at site) |
| 81 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 82 | Assembling of various plinth templates for providing concrete including transporting from one plinth toanother, alingningfixing to corrrect leveland dismatlingthe templete after concreting including cost of labour, cost of template, lead, lift, etc., complete. |
| 83 | III Providing Breaker pinth (GC, LV & Feeders) |
| 84 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m inhard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders. |
| 85 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m in soft disintegrated rock laterite soft rock or kankar not requiring blasting, etc., complete. |
| 86 | Earthwork excavation in medium rock and dense medium rock notrequiring blasting. |
| 87 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete.(As instructed by the Engineer at site) |
| 88 | PCC 1:3:6 mix using 20mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 89 | PCC 1:2:4 using 12 to 20 mm HBG machine crushed metal for plinth with formwork including costof cement all materials,labour,lead lift, curing etc., complete. - PCC wall with form |
| 90 | PCC 1:2:4 using 12-20mm HBS metal for support structures concrete without formwork including cost all materials lead, lifts, labour curing etc complete |
| 91 | RCC 1:1.5:3 using 12 to 20mm(machine crushed) metal for raft concrete without formwork including cost of all materials, lead, lift, etc., complete. (As instructed by the Engineer at site) |
| 92 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. (As instructed by the Engineer at site) |
| 93 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 94 | Assembling of various plinth templates for providing concrete including transporting from one plinth toanother, alingningfixing to corrrect leveland dismatlingthe templete after concreting including cost of labour, cost of template, lead, lift, etc., complete. |
| 95 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 96 | IVProviding support structures pinth (Gantry Pole, LAS, switch pole, strung bus pole) |
| 97 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m inhard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders. |
| 98 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m in soft disintegrated rock laterite soft rock or kankar not requiring blasting, etc., complete. |
| 99 | Earthwork excavation in medium rock and dense medium rock notrequiring blasting. |
| 100 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete.(As instructed by the Engineer at site) |
| 101 | PCC 1:3:6 mix using 20mm HBS machine crushed metal for foundation without form work including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 102 | PCC 1:2:4 using 12-20mm HBS metal for support structures concrete without formwork including cost all materials lead, lifts, labour curing etc complete |
| 103 | PCC 1:2:4 using 12 to 20 mm HBG machine crushed metal for plinth with formwork including costof cement all materials,labour,lead lift, curing etc., complete. - PCC wall with form |
| 104 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. (As instructed by the Engineer at site) |
| 105 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 106 | V Yard Filling |
| 107 | Supplying and filling of Red gravel in the basement filling, labour for filling, watering and consolidation, including cost of all materials, lead, lifts, labour, etc., complete.( As instructed by the engineer at site) |
| 108 | VI Construction of Cable Duct |
| 109 | Earthwork excavation in hard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders and hard gravelly soil for foundation(As instructed by the Engineer at site) |
| 110 | Earthwork excavation in soft disintegrated rock laterite soft rock or kankar not requiring blasting, etc, complete |
| 111 | MR and DMRrequiring blasting (As instructed by the Engineer at site) |
| 112 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete.(As instructed by the Engineer at site) |
| 113 | PCC 1:3:6 mix using 40mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 114 | RCC 1:1.5:3 using 12 to 20mm(machine crushed) metal for raft concrete without formwork including cost of all materials, lead, lift, etc., complete. (As instructed by the Engineer at site) |
| 115 | Brickwork in CM 1:5 mix using II class chamber bricks of size 9\"x 4 3/8\"x 23/4\" for basement and superstructure including cost of all materials, labour, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 116 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 117 | RCC 1:1.5:3 using 12 to 20 mm HBG machine crushed metal for Precast slab, including cost of cement and all lead, lift, curing, etc., complete but excluding cost of steel reinforcement. (As instructed by the Engineer at site.) |
| 118 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. (As instructed by the Engineer at site) |
| 119 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 120 | Labour charges for transporting from casting yard to curing tank, curing tank to cable duct , aligning and laying ofRCC pre cast slab as directed by the site engineer including all labour lead lifts etc complete. |
| 121 | Supplying and fixing in position of MS Angles in required length for fixing the cable duct side wall, as per the direction of site Engineer including cost of all materials, lead, lifts, and cutting the MS Angles required length and labour for fixing etc, complete.(As instructed by engineer at site.) |
| 122 | Supplying and laying UPVC pipe 100 mm outer dia 6kg / cm2 ISI make for cable duct including cost of UPVC pipe, labour for cutting laying fixingetc complete(As instructed by engineer at site) |
| 123 | VI Road Crossing |
| 124 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m inhard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders. |
| 125 | Earthwork excavating and depositingon bank withinitial lead of 10m & initial lift of 2m in soft disintegrated rock laterite soft rock or kankar not requiring blasting, etc., complete. |
| 126 | Earthwork excavation in medium rock and dense medium rock notrequiring blasting. (As instructed by the Engineer at site) |
| 127 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete.(As instructed by the Engineer at site) |
| 128 | PCC 1:3:6 mix using 40mm HBS machine crushed metal without formwork including cost of all labour, materials, lead, lift, curing, etc., complete. |
| 129 | RCC 1:1.5:3 using 12 to 20mm (machine crushed) metal for raft foundation without formwork including cost of all materials, labour lead, lift, etc., complete. |
| 130 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 131 | RCC wall 1:1.5:3 using 12-20mm HBG metal for Culvert wall with form work including cost of all materials, form work including cost of all materials, labour, lead, lift, etc. complete. |
| 132 | VII Transformer pinth |
| 133 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m - In Hard Gravely Soil |
| 134 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-MR and DMR not requiring blasting |
| 135 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-Hard rock requiring blasting |
| 136 | PCC 1:2:4 using 12-20mm HBS metal for support structures concrete without formwork including cost all materials lead, lifts, labour curing etc complete |
| 137 | PCC 1:2:4 using 12 to 20 mm HBG machine crushed metal for plinth with formwork including costof cement all materials,labour,lead lift, curing etc., complete. - PCC wall with form |
| 138 | RCC 1: 1.5:3 using 12-20mm HBS metal (machine crushed) metal forColumn concrete up to basement level with cantering shuttering form work including cost of all material, lead, lift,etc, complete, but excluding cost of steel reinforcement(As instructed by the Engineer at site) |
| 139 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. (As instructed by the Engineer at site) |
| 140 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 141 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 142 | Supply andfixing of MS rails (90 LBS )in transformer plinth to requiredlevelandalignmentasdirectedbythe engineer incharge at site with all labour lead lift etc complete |
| 143 | VIII Road works |
| 144 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m - In Hard Gravely Soil |
| 145 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-MR and DMR not requiring blasting |
| 146 | WMM 1:3:6 mix using 40mm HBS machine crushed metal for road including cost of all labour, materials, lead, lift, curing, etc., complete. |
| 147 | PCC 1:3:6 mix using 40mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 148 | PCC 1:2:4 using 12 to 20 mm HBG machine crushed metal for plinth with formwork including costof cement all materials,labour,lead lift, curing etc., complete. - PCC wall with form |
| 149 | RCC 1:1.5:3 using 12 to 20mm (machine crushed) metal for raft foundation without formwork including cost of all materials, labour lead, lift, etc., complete |
| 150 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 151 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. (As instructed by the Engineer at site) |
| 152 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 153 | IXRoad Culvert |
| 154 | Earthwork excavation in hard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders and hard gravelly soil for foundation(As instructed by the Engineer at site) |
| 155 | Earthwork excavation in soft disintegrated rock laterite soft rock or kankar not requiring blasting, etc, complete |
| 156 | MR and DMRrequiring blasting (As instructed by the Engineer at site) |
| 157 | Supplying and filling with good M sand for foundation including cost of all materials, labour, lead, lift, etc. complete.(As instructed by the Engineer at site) |
| 158 | PCC 1:3:6 mix using 40mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 159 | RCC 1:1.5:3 using 12 to 20mm (machine crushed) metal for raft foundation without formwork including cost of all materials, labour lead, lift, etc., complete |
| 160 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 161 | RCC wall 1:1.5:3 using 12-20mm HBG metal for culvert with form work including cost of all materials, form work including cost of all materials, labour, lead, lift, etc. complete. |
| 162 | xFencing |
| 163 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m - In Hard Gravely Soil |
| 164 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-MR and DMR not requiring blasting |
| 165 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-Hard rock requiring blasting |
| 166 | PCC 1:3:6 mix using 40mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 167 | PCC 1:2:4 using 12 to 20 mm HBG machine crushed metal for plinth with formwork including costof cement all materials,labour,lead lift, curing etc., complete. - PCC wall with form |
| 168 | Supplying and fixing in position of GI angle 50x50x6mm of required length for fixing the cable duct, as per the direction of site Engineer including cost of all materials, lead, lifts, and cutting the GI angle required length and labour for fixing etc, complete.( As instructed by engineer at site) |
| 169 | Supplying and laying of chain link fencing of 2\" x 2\" of 10 Gauge galvanised ironincluding cost of all materials,labour, lead, lift etc complete as directed by the engineer at site. |
| 170 | XI Entrance gate works with wing walland wicket gate |
| 171 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m - In Hard Gravely Soil |
| 172 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-MR and DMR not requiring blasting |
| 173 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-Hard rock requiring blasting |
| 174 | PCC 1:3:6 mix using 40mm HBS machine crushed metal for foundation including cost of all labour, materials, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 175 | Brickwork in CM 1:5 mix using II class chamber bricks of size 9\"x 4 3/8\"x 23/4\" for basement and superstructure including cost of all materials, labour, lead, lift, curing, etc., complete. (As instructed by the Engineer at site) |
| 176 | RCC1:1.5:3,using12to20mmHBGmachine crushed metal for column, plinth beam and grade beam with out form work includingcostofcementandalllead,lift,curing etc.,completebutexcludingcostofsteel reinforcement. |
| 177 | RCC1:1.5:3,using12to20mmHBGmachine crushed metal for column, plinth beam and grade beam with form work includingcostofcementandalllead,lift,curing etc.,completebutexcludingcostofsteel reinforcement. |
| 178 | Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete. |
| 179 | Plastering with CM. 1:3 mix 12 mm thick for fol, bath, RCC pillars, sunshade, loft, etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete. (As instructed by the Engineer at site) |
| 180 | Colour washing two coats with Plastic Emulsionpaint over one coat of Plastic Emulsion primerfor inside wall including necessary plaster of parrys two coats cost of all materials, labour, lead, lift, etc., complete. |
| 181 | Supplying of 5 Mtrs wide MS grill gate and 0.90m wide MS wicket gate as Per drawing and as per direction of Engineer at site cost including all materials,T&P lead,lift Painting with two coats of approved enamel paint over one coat of red oxide primer paint etc complete |
| 182 | Supply and fixing of Entrance gate light with CFL bulb fittings including cost of all materials,labour etc complete |
| 183 | Providing projected border of 10cm width including cost of materials, labour, lead, lift etc., complete |
| 184 | XII Retaining Wall |
| 185 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m - In Hard Gravely Soil |
| 186 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-MR and DMR not requiring blasting |
| 187 | Earthworkexcavationinalltypeofsoilswithan initial lead of 10m and lift of 2m-Hard rock requiring blasting |
| 188 | Supplying and filling of M sand in foundation and basement with well watering and consolidation as per specn. including cost of all materials labour, lead, lift, etc., complete. |
| 189 | PCC 1:3:6, using 40mm HBG machine crushed metal forfoundationpaddingconcreteincludingcostof cementandallmaterials,curing,lead,liftetc.,complete. -WITH OUT FORM WORK |
| 190 | Brickwork in CM 1:5 using chamber bricks for wing wall including cost of all materials,labour,lead,lift etc complete |
| 191 | Plasteringwith CM1:3, 12mmthick for walls including cost of all materials, labour, lead, lift etc., complete. |
| 192 | Colourwashingtwocoatsoutsidewalls byusing Exterior emulsion paint over a primer one coatof approved quality with suitable colourincluding cost of all materials, labour, lead, lift, curing etc., complete. |
| 193 | XIII Bore well Works |
| 194 | Drilling bore well of 150mm dia 6” in all soils, hard rock etc., including transporting of machineries with equipments and all necessary T & P’s labouretc.,completeas per specification -Upto 100 Mts |
| 195 | Drilling bore well of 150mm dia 6” in all soils, hard rock etc., including transporting of machineries with equipments and all necessary T & P’s labouretc.,completeas per specification -100-200 Mts. |
| 196 | Supply and erection of 180mm (7”) dia rigid PVC casing pipe, having 6kg/cm² including cost all materials,lead, lift, re-boring the holes to required depth etc., complete with cover at the top of the bore well. |
| 197 | Supply and erection of 3 HP sumersiblemotor of any reputed makehaving ISI make withsingle phase(or) as approved by the Board Engineer at site to pump water to a height of 300mts.and delivery unit with foot valve v-belt arrangement including cost of all materials, labour, erection charges, 3 HP, 400/440V L&T makestarter to suit the sumersiblemotorincluding the cost of all materials, labour, lead and as per the instruction of Engineer in charge at site complete in all respects. |
| 198 | Supply and erection of 3 phase 30/32 Amps ICTP switch with fuse arrangements to suit the compressor with cost of all materials, labour, lead and lift etc., complete in all respects. |
| 199 | Supply and erection of 32mm diaUPVC pipe having ISI mark and as per IS 4985 2000 (10 Kg/CM²) in and outside of the bore well including cost of all materials, labour, lead,lift etc., complete. |
| 200 | Supplying and laying of 4 core 6 Sq mm power cable from nearest power pointto 3 HP motor including earth work excavation ,laying power cable in the pit and top covered with country bricks and refilling with excavated earth, lead. lift ,etc.complete |
| 201 | Charges for geophysical survey for invetigation of borewell point at various location in the SS site |
| 202 | XIVWater Line to Earthpits |
| 203 | Providing and laying PVC high density pipe including costofallmaterialsviz.bend,labourforcutting threading fixing and tightening necessary excavation etc., complete. -40 mm dia pipe.10kg/cSq.m |
| 204 | Providing and laying PVC high density pipe including costofallmaterialsviz.bend,labourforcutting threading fixing and tightening necessary excavation etc., complete. -32 mm dia pipe.10kg/cSq.m |
| 205 | Supplying and fixing in position of 25mm dia pvc pipe of 10 kg/sq.cm pressure from the approved manufacturer apollo, chemplast, avanplast, valarmathi, usha, vimal etc., confirming to IS 4985 of 1968, 4984 of 1970 including cost of all special fixtures labour lead, lift, etc., complete. |
| 206 | SupplyingandfixinginpositionofGMgatevalve best qualityincluding cost of all special fixtures lead, lift,etc., complete. -40 mm dia GM Gate valve |
| 207 | SupplyingandfixinginpositionofGMgatevalve best qualityincluding cost of all special fixtures lead, lift,etc., complete. - 32 mm dia gate valve |
| 208 | Supplyanderectionof20mmPVCTapforearth pits. |
| 209 | XVProvision of sand drums |
| 210 | Supply and fixing of sand drums with conical cover including cost of material, transport, labour, lead, lift,etc.,complete. |
| 211 | XVIProvision of Msand |
| 212 | Provision of one Load of Msand atsubstation including cost of Material and transport charges etc (One load) |
| 213 | XVIILevelling the SS yard with 12-20mm HBG metal and quarry chips to a height of 200mm and 100mm from the final GL. |
| 214 | Supplying and filling ofstone chips 12 mm to 20 mm HBG metal withrequired thickness all lead and lift including and all other T&P etc., complete. |
| 215 | Supplying and filling ofstone dustwith required thickness all lead and lift including and all other T&P etc., complete. |
| 216 | XVIIISupply of steel furnitures |
| 217 | Supply offurnitures manufactureincluding cost of all materials, labour,lead and lift etc., complete as directed by the Enginer at site -S Type chair with nylon seated |
| 218 | Supply offurnitures manufacture including cost of all materials, labour,lead and lift etc., complete as directed by the Enginer at site.- Steel side rack open type |
| 219 | Supply offurnitures manufactureincluding cost of all materials, labour,lead and lift etc., complete as directed by the Enginer at site.- Steel table 45\"\"x24\"\"x30\"\" |
| 220 | Supply offurnitures manufacture including cost of all materials, labour,lead and lift etc., complete as directed by the Enginer at site .- steel stool |
| 221 | Supply offurnitures manufacture including cost of all materials, labour,lead and lift etc., complete as directed by the Enginer at site .- Steel half bench |
| 222 | Supply offurnitures manufacture including cost of all materials, labour,lead and lift etc., complete as directed by the Enginer at site . -PVC armed Chair of reputed make |
| 223 | Supply of Personal Computer and Laserjet Printer with the following specifications Intel Core i3 (13th Generation or higher) processor, 8GB DDR4 RAM or later version (expandable to 32 GB) , Storage 256 NVMe SSD & 1 TB 7200 rpm SATA (or) 512 GB NVMe SSD, 21.5\" LED Monitor, Full HD or Higher , TCO certified, Anti glare, Integrated graphics with DirectX 12 support, minimum 8 USB ports (USB 3.2 or above) of which 2 in the front, HDMI & VGA displayport,1 Universal Audio or Mic port, Networking Integrated Gigabit Ethernet, Wi-Fi 6, Operating system: Genuine windows 11 pro (64bit) witha latest SP preloaded, Antivirus: Licensed Enterprise-grade Antivirus Solution with minimum 3 years subscription , Warranty Minimum 3 years onsite comprehensive warranty.Reputed make Monochrome Laserjet Printer : Compatible Operating Systems : win XP, Windows 7, Windows 8, Windows 10 and Windows 11, Interface: USB 2.0 Hi-Speed, Paper size : A4,A5,B5,Legal,Letter: Paper Handling Trays : Input Tray, Manual Tray & Face down Tray ( for paper) : Power and operating requirement : input voltage - 220 to 240 V AC , 50 Hz.: Features : suitable toner catridge , Installation software & power Adapter |
| 224 | Supply of 1000V/2000Mohm hand operated Megar |
| 225 | Supply of Digital multi meter of reputed make ( Fluke ) |
| 226 | Supply of power clamp meter 400 A AC/DC with accessories |
| 227 | SGST & CGST (If applicable quote the value, if not enter \"0\") |
| 228 | IGST (If applicable quote the value, if not enter \"0\") |
Copyright © 2025 · All Rights Reserved. Terms of Usage | Privacy Policy