| 1 | Earth work excavation for foundation in all types of soils and sub soils with an initial lead of 10m and lift of 2m including all labour charges for excavation in loose soil and hard stiff clay mixed with boulders offoundation etc, complete with std specification |
| 2 | Supply and filling of river sand from the approved quality quarry including filling charges etc., complete |
| 3 | Plain Cement concrete in 1:4:8 [one cement and four sand and eight aggregate ] using20 mm size ISS grade machine crushed chips including the cost of mixing, laying curing etc., complete complying with standard specification |
| 4 | Brick work in cement mortar 1:5 mix using country brick includingcost and conveyance of all materials from approved quarry and including all other labour charges etc, completed as per standard specification. |
| 5 | Plastering cement mortar 1:5 mix 12mmthick including cost and conveyance of all materials from approved quarry and including all other labour charges etc., completed as per standard specification. |
| 6 | Supplying and erecting steel centering for sides and soffits including supports and strutting upto 3.29M heights for plain surface such as RCC slab, rectangular tee beam (or) EII beams, lintel bed block, stair case waist slab and landing slab with all cross brasings etc., complete -Beam |
| 7 | Supplying and erecting steel centering for sides and soffits including supports and strutting upto 3.29M heights for plain surface such as RCC slab, rectangular tee beam (or) EII beams, lintel bed block, stair case waist slab and landing slab with all cross brasings etc., complete -Slab |
| 8 | Supplying, fabricating and placing in position of Steel Reinforcement using Mild steel or ribbed for steel rods, for all RCC worksas per the design given by the departmental officers including cost of steel and binding wire and all labour charges for cutting, bending, tying and placing in position etc, complete |
| 9 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - |
| 10 | Dadooing walls withGlazed tiles of sizes 305mm X 200mm X 6mm size of approved make and quality and colour Set in cement mortar 1:2 (One part of Cement and two part of Plastering Sand (P- Sand)) over 10 mm base layer plastering and pointing with white cement neatly as directed. |
| 11 | Floor finishing with colour ceramic tiles of size 305mmx305mmx6mm of approved quality & Colour laid in cement mortar 1:3mix 20mm thick and pointing with white cement using 0.40 kg/m2including cost and conveyance of all labour and materials charges etc., complete |
| 12 | Supply and Delivery of 1000 litresHDPE Tank as per ISI 1270 / 1996 etc, complete. |
| 13 | Painting two coats with approved Plastic Emulsion paint over cement plastered wall surface and ceiling includingcost of one priming coat, Cost of materials, all labour charges,brushes, cleaning preparing the surface and curing charges etc, complete as per SS. |