| 1 | Earth work in Excavation in foundation within initial lead and lift |
| 2 | Sand filling in F&P with well Watered and Rammed etc Complete |
| 3 | C.C (1:3:6) with 40mm size CB metal including all Cost , Conveyance, Royalty etc Complete |
| 4 | C.C (1:3:6) with 40mm size CB metal including all Cost , Conveyance, Royalty etc Complete |
| 5 | RCC work M20 grade with 20mm and down grade black hard granite stone chips including hoisting and laying |
| 6 | RCC work M20 grade with 20mm and down grade black hard granite stone chips including hoisting and laying |
| 7 | Rigid and Smooth Centering and Shuttering including all Cost, Conveyance and Royalty Etc complete RCC Foundation,plinth band,footing bases of column RCC Column from PL to RL |
| 8 | Column |
| 9 | Lintel Beam |
| 10 | Roof Beam |
| 11 | Slab |
| 12 | Fly Ash Brick Masonary in F& P with (1:6) cement mortar including all Cost, Conveyance and Royalty Etc Complete |
| 13 | Labour for Cutting , Bending, Tieng the HYSD Bar including placing and Positioning the bar etc Complete |
| 14 | 12mm thick C.P with (1:6) Cementmortar including all Cost Conveyance , Royalty etc complete |
| 15 | 16mm thick C.P with (1:6)Cement mortar including all Cost, Conveyance, Royalty etc Complete |
| 16 | Cost of M.S Door and Window |
| 17 | Supplyng,Fittings,fixing of two track UPVC Sliding windows of approved make with 6mm thick glass of approved quality complete withframe shutter & all fittings & fixtures including cost of conveyance of all material |
| 18 | Fitting, fixing, of door & windows including fixture & fittings etc as per the instruction of EIC |
| 19 | Painting 2coats over a coat of primer including cost of paints, labour& sundries etc complete |
| 20 | Finishing wall painting two coats with plastic emulsion paint of approved shade including all cost,conveyance,taxes etc. complete.(Data for 10 Sqmt)[AR-06, P99, Item-20] |
| 21 | Wall painting two coats with 100% acrylic emulsion paint(1st quality) exterior grade of approved make and shade manufactured by reputed manufacture like nerolac/Asian/Berger/Dulax or equivalent to make an even finished surface over a coat of primer with water bond cement primer in all heights with all scaffolding and stagging charges including cost,conveyance,taxes of all materials,cost of all labour T&P sundries etc, as required for the work. |
| 22 | Finishing wall surface of walls with Acrylic wall putty (water based) of approved make |
| 23 | Fitting Fixing of Vetrified Tiles With (1:4) Cement Mortar with neat cement Slurry on the 25mm thick bed Including all Cost, Conveyance, Royalty Etc Complete |
| 24 | S/F of 8 way double door D Box |
| 25 | MCBDP switch |
| 26 | Group-A.L.P.-18 F.P.-C. |
| 27 | Group-B. L.P.-36 F.P.-9 |
| 28 | Group-C, LP-7 F.P-7 CB |
| 29 | Group-A |
| 30 | Recessed submain wiring along with earth wire etc . Complete101 2wiring |
| 31 | 1x1.5 mm2(1.19.2.SOR-17)wiring |
| 32 | 2x2.5mm 2+1.5mm2(1.8.2.SOR-17)wiring |
| 33 | Supplying & fixing of modular G.I. Box of 18SWG on surface etc.. Complete |
| 34 | Supplying & fixing of modular stepped type regulator of ISI MARKED |
| 35 | S/F of 48\" AC Ceiling Fan |
| 36 | Modular Computor board with 4 nos of modular SP Switch & modular socket |
| 37 | S/F of 20W/18W LED Batten light ofCrompton /Havells make |
| 38 | S/F of Bakelite angel holder/batten holder of ISI marked conforming to IS-1258/1987 in place of ceiling rose |
| 39 | S/F of 9W/10W LED lamp ofCrompton /Havells make |
| 40 | Earthing |
| 41 | handrail |
| 42 | Moral Painting |
| 43 | Dual desks |
| 44 | Cost of Black Board 12’*4’ SIZE |
| 45 | Display board |