| 1 | Earthwork in excavation of foundation in hard soil with all leads and lifts including dressing the sides and levelling the bed of the foundationincluding cost of all labourrequired for the work etc. complete with all other machineries required for the work and stacking the excavated materials away from the working area as directed by the Engineer-in-Charge including 1% Cess. |
| 2 | SINGLE UNDREAMEDPILE FOUNDATION WITH RCC M20 USING 20MM SIZE CBHG CHIPS INCL LABOUR AND MATERIALS RATE EXCLUDING HYSD BAR ETC |
| 3 | Supplying and filling foundation and plinth with sand well watered & rammed with cost, conveyance, royalty and taxes of all materials labour required for the work as per specification anddirection of the Engineer-in-Charge including royalty of materials including 1% Cess. |
| 4 | Providing Cement Concrete (1:4:8) in foundation with 4cm nominal size of hand broken hard granite metal of approved quality from approved quarry including hoisting, lowering, and laying in postition in layers not exceeding 150mm. thick with proper packing and ramming to proper slope and level including watering, curing with cost, conveyance, royality, taxes, labour, T&P and all other materials required for the work, finishing the exposed surface smooth, providing grooves and beads where ever necessary etc. complete in all respect as per the specification and including 1% cess as per direction of the Engineer-in-Charge |
| 5 | Providing Cement Concrete (1:2:4) in foundation with 12mmsize of crusher broken hard granite chips of approved quality from approved quarry including hoisting, lowering, and laying in postition in layers not exceeding 150mm. thick with proper packing and ramming to proper slope and level including watering, curing with cost, conveyance, royality, taxes, labour, T&P and all other materials required for the work, finishing the exposed surface smooth, providing grooves and beads where ever necessary etc. complete in all respect as per the specification and including 1% cess as per direction of the Engineer-in-Charge ground Floor |
| 6 | Fly ash. brick works in cement mortar (1:6) after immersing brick for six hours in water before use with good quality kiln buntbrick of 9\"sizes having crushing strength not less than 75Kg./Sqm including splays cutting ,circular moulding and similar such type of work with necessary projections, chamfering and corbelling, watering and curing etc. complete including cost, conveyance , royalties of all materials with cost of all labours,all taxes with T&P articles required for the work etc. complete as per specification and direction of the Engineer-in-charge.(In foundation and Plinth) |
| 7 | Fly ash. brick works in cement mortar (1:6) after immersing brick for six hours in water before use with good quality kiln buntbrick of 9\"sizes having crushing strength not less than 75Kg./Sqm including splays cutting ,circular moulding and similar such type of work with necessary projections, chamfering and corbelling, watering and curing etc. complete including cost, conveyance , royalties of all materials with cost of all labours,all taxes with T&P articles required for the work etc. complete as per specification and direction of the Engineer-in-charge.(In superstructure) |
| 8 | R.C.C. work of M-25 grade with 20mm and down grade black hard granite (crusher broken) of approved quality and from approved quarry including hoisting, lowering, laying and compacting concrete watering, and curing for four weeks finishing the exposed surface and ceiling smooth, providing grooves or beads where necessary including cost, conveyance royalties and taxes of all materials and labour with T&P required for the work etc. complete in all respect but excluding the cost of M.S. rods or Tor steel and binding wires of 18 to 20 gauge and labour charges for straightening, cutting, bending, binding etc. of the M.S. rods or tor steel and binding wires and tying the grills and placing in proper position in all floors.as per the specification and direction of the EIC. |
| 9 | Supplying, fitting,fixing & placing Uncoated HYSD bar reinforcement complete. RCC |
| 10 | Rigid and smooth centering ,shuttering for R.C.C. work including false works and dismantling them after casting. PILE CAP/Grade bean |
| 11 | Lintel Ground Floor |
| 12 | Wall Beam Ground Floor |
| 13 | Roof slab Ground Floor |
| 14 | Column |
| 15 | Supplaying, fitting & fixing Vetrified tiles ofsize 600mm x 600mm x 10mm ofapproved make in floors, treads or steps and landing on 25 mm thick bed of cement mortar 1:1 (1 cement: 1 sand) jointed with neat cement slury mixed with pigment to match the shades of the tiles including rubing and polishing with cost,coveyance of all materials etc. completeas directed by the Engineer-in-Charge.. |
| 16 | Providing with fitting and fixing in position of M.S. windows and door openings and stair case railings and parapet railing including making holes in walls andRCC structures or wood work etc. in proper position, making good to the damages of walls or RCC or other structurals complete including mending or cutting size or groovesin choukaths with cost and conveyance of all materials and labour with T&Prequired for the work taxes and royalties etc. complete ( including cost of screws) in all floors as per direction of the Engineer-in-charge..Group Floor |
| 17 | 12mm (½\") thick cement plaster in cement mortar (1:4) finished smooth to external brick walls after racking out the joints of brick work with watering curing and cost conveyance, royality taxes of all materials all labour T&P etc. complete in all respect in floors etc. complete as per specification and direction of the EIC.(Including cement punning and bitumen paint) Ground Floor |
| 18 | 16mm (5/8\") thick cement plaster (1:6) finished smooth to external brick wall surface after racking out joints including watering and curing with the cost and conveyance of all materials and labour with T&P required for the work with all taxes and royalties etc. complete in all respect as per specification and direction of the EIC. Ground Floor |
| 19 | Priming one coat of Wall cement Primer (Water bound) including cost of primer all labour T&P etc complete.Ground Floor |
| 20 | Finishing wall with Weather coats of approved shade on new work two coats to give even shade including cost, conveyance, taxes with all labour and T&P required for the work etc. complete as per direction of the EIC.Ground floor |
| 21 | Wall Painting two coats with Plastic of approved shade on new work to give an even shade including cost of pain all labour T&P etc complete. ( Data for 10 Sqm) A/ R Page - 99, Sl.(20) Ground Floor |
| 22 | Painting two coat with any approved paint on Iron work over a coat of priming including all cost,carriage,royalty etc omplete. |
| 23 | Finishing Wall surface of wall with Acrylic wall putty(water based) of approved make and finished smooth and even surface to received painting including cost of scaffolding staging charge with cost of all materials taxes, labour T&P etc complete. Ground Floor |
| 24 | 2.5cm thick grading concrete (1:2:3) on roof slab 6mm size hard granite chips,including hoisting,lowering,and laying in position in layer not exceeding 150mm.thick with proper packing and ramming to propre slope and level including watering,curing with cost,conveyance, royality,taxes,labour, T&P and all other materials required for the work,finishing the exposed surface smooth,providing grooves and beads where ever neceserry etc. complete in all respect as the specification and including 1% cess as per direction as per direction of the enginess-in-chaerge First Floor |
| 25 | Cost of Sign Board (1.50Mtr x 1.80Mtr) complete as directed by Engineer-in-Charge |