| 1 | Construction of Shed. Heading |
| 2 | Excavation in Foundation As Per DSR 2.6 |
| 3 | Sand Filling in Foundation and plinth DSR 2.27 |
| 4 | 1:4:8 ( 1 Cemet: 4 fine sand derived from natural sources : 8 grade stone aggregate 40mm nominal derived form natural sources. DSR 4:2:8. |
| 5 | Brick work with common burnt clay F.P.S ( non modular) bricks of class designation 7.5 in foundation and plinth in 1:6 (1 Cement : 6 coarse sand) DSR 6.1.2 |
| 6 | Brick work with common burnt clay F.P.S ( non modular) bricks of class designation 7.5 in Super structure above plinth level up to floor V level in all shape and size in 1:6 (1 Cement : 6 coarse sand) DSR 6.4.2 |
| 7 | Ezcavating, supplying stacking and filling of the local earth (including royality) by machanical transport upto a lead of 5 km dse 2.25(a) |
| 8 | Providing and laying in position cement concrete 1:1.5:3 (1 cement : 1.5 corse sand derived from the natural sources : 3 graded stone aggregate 20mm nominal derived from natural sources) dsr 5.1.2 |
| 9 | R.C.C work in wall (any thickness), including attached pilasters butteresses, plinth and string courses, fillests, columns, pillars, piers etc 1:1.5:3 (1 cement : 1.5 corse sand derived from the natural sources : 3 graded stone aggregate 20mm nominal derived from natural sources) dsr 5.2.2 |
| 10 | R.C.C work in wall (any thickness), including attached pilasters butteresses, plinth and string courses, fillests, columns, pillars, piers etc 1:1.5:3 (1 cement : 1.5 corse sand derived from the natural sources : 3 graded stone aggregate 20mm nominal derived from natural sources) dsr 5.2.2 |
| 11 | R.C.C work in beam, suspended floors, roofs having slope upto 15% landing, balconies, shelves, chajjas, lintels, band with 1:1.5:3 mix etc complete. DSR 5.3 |
| 12 | Mild steel or iron in plane work such as reinforced concrete Si dsr 5.22a.4 |
| 13 | 12mm thick plaster 1:6 Cement & Fine sand dsr dsr |
| 14 | Finishing of wall textured exterior paint of required shade dsr 13.45.1 |
| 15 | Providing and laying vitrified floor tiles in different size (thickness to be specified by the manufacturer) with 20mm thick cement morter 1:4 Cement and c sand including grouting the joints etc complete. Dsr 11:41:2 |
| 16 | ANTITERMITE TREATMENT dsr 2.32.1+2.35.1 |
| 17 | PROVIDING AND LAYING INTEGRAL CEMENT BASED WATER PROOFING TREATMENT INCLUDING PREPARATION OF SURFACE AS REQUIRED FOR TREATMENT OFF ROOFS ETC DSR 22.7.1 |
| 18 | Centering shuttering including strutting, propping etc and removal from for dsr 5.9.1 |
| 19 | Centering shuttering including strutting, propping etc and removal from for dsr no 5.9.5 |
| 20 | S/F of sign board |
| 21 | Electric Work |
| 22 | Parikarma marg- Interlocking Work |
| 23 | Bench |
| 24 | LED Light with Pole |
| 25 | Water Kiosk |