| 1 | Construction of 01 nos. 132 KV Solar bay & modification of existing bus for Amplus Tungbhadra Solar Generation plant at 132 KV Pashi S/S |
| 2 | Preparing of earthmat by laying of 40mm dia M.S. round bar 800 mm below ground level insoil including cutting, bending straightening, welding & painting excavation of trench, its back filling& all other associated work to complete the work satisfactorily as per drawing & technical specification excluding the cost of round bar. |
| 3 | Pecking of 3 mtr. Long electrode vertically inside the ground with top 800 mm below ground level and its welding with main Earthmat and painting as per relevantPaint. |
| 4 | Erection of Lattice type main and auxiliarystructures (ATMS, AXM,BTM,ALP,BCT,BBL,BTI etc. at 132 KV Sub Station,Pashi including sorting, shifting, matching of hole and other associated work to complete the job as per technical specification of UPPTCL including shifting of material from store to erection site. All men and T&P required for satisfactory completion of work shall be arranged by the contractor. |
| 5 | Sl Description Nos. Unit Weight (MT) Total Unit Weight i.132 KV BTM 20.721.44ii. 132 KV PI & LA - ALP 7 0.121 0.847iii. 132 KV Column-ATMS51.231 6.155iv. 132 KV Beam - AXM50.8124.06v. 132 KV Peak- XPM50.084 0.42vi. 132 KV Mast – YMM50.022 0.11vii. 132 KV Isolator- BBL 6 0.5013.006viii. 132 KV CT/PT-BCT180.1793.222ix. 132 KV TI-BTI 2 0.584 1.168 |
| 6 | Erection of following new equipment as per instruction manual of various equipments including its shifting from the store to the site job including other associated works to complete the job satisfatorily. |
| 7 | 132 KV CB |
| 8 | 132 KV BI with insulator |
| 9 | 132 KV LI with insulator |
| 10 | 132 KV TI with insulator |
| 11 | 132 KV CT |
| 12 | 132 KV CT junction box |
| 13 | 132 KV PT |
| 14 | 132 KV PT junction box |
| 15 | 132 KV LA |
| 16 | 132 KV PI |
| 17 | 132 KV control Panel as per technical specification of SAS Simplex type control and relaypanel for 132 KV Feeders . |
| 18 | Earthing of structure and equipment byMS flat (provided by department) including cutting straightening bending laying 800 mm below inside the ground with main earthmat including painting of joints with non corrosive paint on flat,. painting at the flat on structure with the Bus green paint after one coat of red oxide primer and back filling of excaveted tranch along with proper ramming and all associated work. |
| 19 | Earthing by 75x10 mm MS Flat. |
| 20 | Earthing by 25x6 mm MS Flat. |
| 21 | Earthing by 50x6 mm MS Flat. |
| 22 | Laying of following size of unarmoured control cable in the cable trench on perforated tray from the control relay panels to the various equipment junction box etc. in switchyard as per cable schedule, its saddling in proper distance with al. saddle of size 25x3 mm including carriage of cable drums from the store to the laying site and other associated work to complete the job satisfactory. |
| 23 | 2Cx2.5mm2 |
| 24 | 4Cx2.5mm2 |
| 25 | 6Cx2.5mm2 |
| 26 | Termination of following size control Cable as said above as per cable schedule including making necessary holes in gland plate of box wherever required supply and fixing of cables glands ferrul of appropiate size and nos. respectively for each core of cable and its terminationwith crimping type lugs and all associated work to complete the job satisfactory. ( One no. equal to both side termination of one core ) |
| 27 | 2Cx2.5mm2 |
| 28 | 4Cx2.5mm2 |
| 29 | 6Cx2.5mm2 |
| 30 | Stringing of 132 KV extension buses( main bus I,II) of all the three phases (R,Y,B) with ACSR Moose conductor including shifting from store to workingplace. Fitting of all trension clamp, hosting of insulators and proper clamping |
| 31 | Stringing of 132 KV extension bus( Transfer bus, jack bus) of all the three phases (R,Y,B) with ACSR Panther conductor including shifting from store to workingplace. Fitting of all trension clamp, hosting of insulators and proper clamping |
| 32 | Baywise Inter-connection of equipment with specifiedconductor (Jumpering with equipments and buses) with PG Clamp, T-Clamp, Isolator Clamp & CTClamp, wherever necessary, and other associated work to complete the job as per technical specification of UPPTCL including shifiting of material/ equipments from store to erection site and including all other associated work to complete the job. |
| 33 | 132 KV solar bay |
| 34 | Delta earthing of 120 KV LA consisting of 06 nos. electrode ,its placing inside the ground and connecting all three electrodes with m.s. flat and connecting the same with main earthmat at two places required excluding cost of MS strip and MS round bar. |
| 35 | Shifting of P.T. from existing main bus I & II to extendedbus I & II area by crane and make all connections including earthing for proper operation . |
| 36 | Installation of 1.5 Ton branded split Air conditionerwith stabilizer in kiosk room with all electrical items for proper connections. |
| 37 | Lighting Enhancement workincluding erection of pole and installation of LED fittings and other associated works to complete the work satisfactorily at extended switchyard of 132 KV Pashi substation. |