| 1 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. Depth upto 1.5 m |
| 2 | Providing and laying lean cement concrete 1:4:8 in Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in concrete mixer, laid manually, compacted with surface vibrator, finishing and curing complete as per clause 601, 112 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. |
| 3 | Random rubble stone masonry work in cement mortar with mechanical mixer in foundation (at any level) complete as per drawing and technical specification and as per clause 1000 and 1400 of MoRT&H specification including all scaffolding material, labour, machinery but excluding pointing and plastering.In cement mortar 1:3 (1 cement : 3 coarse sand) |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level :1:1½:3 (1 Cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size). |
| 5 | Reinforcement for R.C.C. work at all levels including straightening, cutting, bending, placing in position and binding all complete.Cold twisted bars |
| 6 | Kota stone slab flooring 25mm thick over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) :Area of each slab 900 to 2000 sqcm |
| 7 | Centring and shuttering with plywood or steel sheet upto two stories ( each story of height upto 3.5 metre from floor level) including strutting, propping etc. and removal of form for :Lintels, beams, plinth beams, girders, bressumers and cantilevers |