| 1 | Clearing Juliflora jungle without uprooting and disposing of the same as directed by the Engineer in charge of the works and as per technical specification. |
| 2 | Earthwork in all soils except hard rock requiring blasting and conveying earth by deploying earth moving machinery and tippers for formation of bundwith a lead of 1km in layers of suitable thickness, depending upon type of compaction equipment, and not exceeding 25 cm thickness, benching of slopes prior to placement of earth fill, breaking clods, watering to OMC (Optimum moisture content) and compaction of each layer to 95% Proctor density through deployment of appropriate compaction equipment (8-10 T power roller / vibratory power roller / short width (+/- 0.90n width drum) power roller or vibratory power roller / fuel-operated or electrically operated vibratory plate compactors, ensuring compaction of designed bund section and also ensuring compaction of earth fill and side slopes through the deployment of hydraulic excavators with steel plate fixtures attached to their booms/ heavy power rollers capable of including 11/2(H):1(V) slope including side slopes as directed by the engineer in charge of works and as per technical specifications.with a lead of 1km |
| 3 | Supplying demarcation R.C.C. pre cast posts inCement concrete of grade M20 with well graded aggregates and the nominal maximum size of coarse aggregate of size 20 mm of size 0.15 x 0.15 x 1.20 M and fixing the post 40 Cm depth below ground level, the post includes using 4 numbers of 10 mm RTS main rod to a length of 1.325 M, using 8 mm MS 10 numbers as strips with steel centering and painting the post with enamel paint to a height of0.80 M around the post etc. complete and conveying the post to the site of demarcation boundary such as tank bund and foreshore including earth work excavation for foundation in HSC having the base plain cement concrete of 10 cm of grade M10 concrete using hard blue granite broken stone of40mm , complete as directed by the Engineer in charge of works and as per the technical specifications. |
| 4 | Dismantling, clearing away and carefully stacking material and without disturbingnearby structure useful for reuse for any thickness of brick or stone masonry in Lime Mortar walls under 3 (Three) meters high etc, complete as directed by the Engineer in charge of works and as per the technical specifications. |
| 5 | Dismantling, clearing away and carefully stacking material and without disturbing nearby structure useful for reuse for any thickness of plain Cement Concrete etc, complete as directed by the Engineer in charge of works and as per the technical specifications. |
| 6 | Earth work excavating and depositing on bank with a initial lead of 10 m & initial lift of 2 m in Hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size of boulders hard gravelly soil as directed by the Engineer in charge complying with standard specification and as directed by the departmental officers.SS20B Sl.No.D62 (cut open bund) |
| 7 | Earthwork excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size of boulders hard gravelly soil inclusive ofshoring to full depth strutting and bailing out water wherever necessary and refilling the sides of foundation with excavated soil other than sandin layers of not more than 15 cm thick, well rammed, consolidated and depositing the surplus earth in places as shown by the departmental officers with an initial lead of 10 (Ten) metres and initial lift of 2 (Two) metres and clearing, levelling the site etc., complete complying with standard specification and as directed by the departmental officers. |
| 8 | Supplying and filling with theM Sandin 15 cm thick layer including watering compacting cost and conveyance materials etc.complete complying with the standard specification and as directed by the Engineer in charge of the works For sluices ,weirs sand Retainig wall Specificatiion complete. |
| 9 | Providing and placing Plain Cement Concrete M 15 grade using well graded aggregates of nominal maximum size of 40mm and downgraded to I.S specified grading ( To achieve the specified charaterstics strength of 10N/mm² in 28 days ) and mixing the ingredients in approved mixer including dewatering of the placement site by bailling / pumbing and diverting wharever necessary, placing concrete in layers, watering, curing, finishing the surface with all leads and lifts etc., complete as directed by the Engineer in charge of works and as per the technical specifications.- 10m3 |
| 10 | Providing and placing Plain Cement oncrete M 15 grade (1:2:4) using well graded aggregates of nominal maximum size of 60% of 40mm and 40% of 20mm I.S specified grading ( To achieve the specified charaterstics strength of 10N/mm² in 28 days ) and mixing the ingredients in approved mixer including dewatering of the placement site by bailling / pumping and diverting wharever necessary, placing concrete in layers, watering, curing, finishing the surface with all leads and lifts etc., complete as directed by the Engineer in charge of works and as per the technical specifications. |
| 11 | Providing and placing Plain Cement oncrete M 20 grade (1:1½:3) using crusher broken hard coarse aggregate (well graded) of nominal maximum size of 20mm and downgraded to I.S specified grading (To achieve the specified characteristic strength of 20N/mm2 in 28 days) and mixing the ingredients in approved mixer including dewatering of the placement site by baling / pumping and diverting wherever necessary, placing concrete in layers and vibrating, water curing, finishing the surface with all leads and lifts etc., complete as directed by the Engineer in charge of works and as per the technical specifications. |
| 12 | Supplying and erecting water tight steel centering for sides and soffits including necessary supports and shuttering including strutting for retaining wall and all RCC works such as column, footing, plinth beam, etc., upto 3.29m height and all cross bracings using mild steel BG 10 sheets of size 90cm x 60cm gauge stiffeded with welded mild steel angles of size 25x25x3mm for boarding laid over silver oak ( country wood ) joits of size 10x6.5cm spaced at about 90cm centre to centre and suitably supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre including cost of materials etc., complete complying with standard specification as directed by the departmental officers the payment for centering shall be given after the concrete is laid and the retrived materials should be taken back the contractor.with strutting |
| 13 | With strutting |
| 14 | Supplying and fixing new cut stone fully dressed to size all faces and set in cement mortar 1:3 (One cement and three sand by volume) mixed using mixer machine including all incidental charges such as finishing, curing etc., complete as directed by the Engineer in charge of works and as per technical specifications. |
| 15 | Fabricating andsupply of country woodplug size of 40 x 40 cm to 60 cm height. The plug rod with 20 mm dia mild steel rod size of 3.0m to 4.50 m height, The plugtop side, middle, centre and bottom side covered iron strap - 3 nos. Plate thickness size 3 mm steel plate. The plug hole size 10 cm to 25 cm dia.etc., including cost of rod , wroughtand put up and fixing in correct alignment in position. The plug painted with two coats of Varnish, the rod painted with two coats of best anti-corrosive paint and conveyance to the work site including loading, unloading.The rates shall be inclusive of all taxes and duties and including fixing charges etc. complete complying specification and as directed by the Engineer. |
| 16 | Supplying , Laying and fixing in position of R.C.C. Hume pipesof NP3 class of 1200mm Dia with suitable collars including labour charges and jointing materials etc., complete complying with standard specification and as directed by the departmental officers complying with standard specification and as directed by the departmental officers 900mm dia Hume pipe NP3 |
| 17 | Refilling with excavated earth (other than sand) complying with standard specification well rammed with water and as directed by the departmental officers. |
| 18 | Gravel packing for apron and revetment of 15cm thick including the cost of gravel at site of work, mixing with water so as to form into stiff plastic balls and laying and finishing etc., complete complying with standard specification. |
| 19 | Rough stone dry packing for revetment andapron using available Hard granite stones obtained from approved sources including the cost of new wedges for filling thegaps etc, complete as directed by the Engineer in charge of works and as per the technical specifications. |
| 20 | Providing and placing Reinforced Cement oncrete M 20 grade (1:1½:2) using hard well graded aggregates withthe nominal maximum size of coarse aggregate of 20mm; weigh batching the ingredients and mixing in approved mixers/batching plant (to produce concrete of the specified characteristic strength of 20N/mm2 at 28days) including dewatering of placement site by bailing/pumping and by diverting wherever necessary laying the concrete in layers and in bays, Vibrating, compacting andfinishing, adequatewater curing so as to attain the profile and strength specified in the approved drawing and specifications etc, complete as directed by the Engineer in charge of works and as per the technical specifications |
| 21 | Supplying, fabricating and placing in position of HYSD ( High Yeild Strength ) bars for all reinforced cement concrete works including cost of binding wire, steel rods, conveyance charges and labour charges etc., complete, complying with standard specifications and as directed by the Engineer in charge of work |
| 22 | Earthwork in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machineries and tippers including benching, formation of bunds, breaking clods, sectioning etc. |
| 23 | Earthwork excavating and depositing bank with an initial lead of 10m. and initial lift of 2m in sand , silt or orher loose soil , wet soil or silt not under water , light black cotton soil , sandy loam and ordinary soil including excavated earth etc complete as directed by the Engineer in charge of works and as per the technical specifications. (SS 20B) |
| 24 | Plastering with cement mortar 1:4 (One cementand four sand) 20 mm thick including curing, finishing etc., complete complying with the standard specification |
| 25 | GST 18% |