| 1 | During Shutdown period by making proper earthing on both side and then opening of both end Jumpers of 132 KV C.B installed at 40MVA T/F No. bay at 132KV S/S Mohaddipur old,Gorakhpur under ETD-1, Gorakhpur with all cost of men, T&P etc, required for the completion of work.(401876) |
| 2 | Dismantling of 132 KV, 1250 Amp. Crompton Greaves make SF6 Gas circuit Breakerinstalled at 132/33KV 40MVA T/F Bay at 132KV S/S Mohaddipur old,Gorakhpur under ETD-Ist, Gorakhpur by opening of support column, operating drive porcelain column, nuts, bolts, cable connection for Dc, Ac. tripping post and pre close supervision after due idertification, earthing with all cost of men T&P vehicle etc.(400090) |
| 3 | Shifting of complete dismantled parts up to designated place at store including marshalling box and other accessories with all cost of men, vehicle, crane etc.(500543) |
| 4 | Modification in existing 132 KV CB old foundation base (As per new available breaker drawing) of different make by providing ofMS Channel of size 150x75x6.5x10 mm of 4 Meter long required for each CB including all cost of channel, cutting in required size, making hole of 20/25 mm dia. with gas cutter and proper paintingwith all cost of T&P,material etc. required for the completion of work.(401426) |
| 5 | Providing and fixing of500x500x12 mm M.S. plate for each CB after painting of MS Plate by All. Paint in two coats at 12 hours interval including all cost of channel cutting in required size making hole of 20/25mm dia with gas cutter and smoothing with the help of grinder along with carriage up to site with all cost of men, T&P, material etc. required for work to complete the work satisfactorily.(301155) |
| 6 | Providing of 20/25 mm dia 150 mm long HAG nut, bolt, washer for proper fastening of plate and channel as per site required with all cost of men, T&P material etc.(300777) |
| 7 | Concereting of modified foundation base in ratio 1:1:5:3 with cement, sand, ballast in a size (4x0.5x0.5 m-01 Cub M) for each circuit breaker and curing for seven days with all cost of men, T&P material etc, required for the completion of work.(301341) |
| 8 | Erection of 132 KV different make SF-6 CBs at 132 KV C.B of 40MVA T/F bay at 132KV S/S Mohaddipur Old,Gorakhpur Under ETD-Ist,Gorakhpur including shifting of materials from storage place to site and all other associated work required for its proper erection with all cost of men T&P, materials, vehicle, crane (work will be done under Strict Supervision of Curcuit Breakers Service Engineer and Engineer in charge).(200057) |
| 9 | Jumpering of newly erected circuit breaker at both end originally with old conductor or either new conductor after cutting, shifting. etc. required for the completion of work.(401956) |
| 10 | Termination of dismantled old/Newly laid various sizes control cables including making necessary hole in gland plates where required. Supply and fixing of cable gland of appropriate size. Supply and providing ferrulesfor each core of cable and its termination with all cost of men, materials, T&P etc.(402145) |
| 11 | Earthing of breakers with existing earth mat by cutting bending, welding by 50x6 mm earthing strip (provided by the contractor) then its painting by green color in two coats including the cost of men power.(400717) |