| 1 | Part 1 : Providing Paver Block Pavement at Devinaytakkenpatty AD Pudhu Colony(Kannammal house to Bharathi house) in Kuttam PanchayatEstimate Amount : Rs. 4.45 Lakhs |
| 2 | Earthwork excavation and depositing on bank with an initial lead and lift in all classes of soils and sub soils except in hard rock including all labour charges etc . Complete. |
| 3 | Cement concrete 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all matials to site and all labour charges etc., complete. |
| 4 | Supply & erection of centering for sides & soffits of all R.C.C. worksincluding cost & conveyance of all materials to site and all labour charges etc., complete. |
| 5 | Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all matials to site and all labour charges etc., complete. |
| 6 | Construction of Granular Sub base by providing with graded materials of size 9.5mm to 4.75mm metal in 66% & 2.36mm in 34% including spreading in uniform layers with motor grader on propared surface, mixing by mix in place method with rotavator at OMC and |
| 7 | Providing and Laying of Interlocking Concrete Block (Surface Textured) Pavements having thickness 60mm and compacted over a thin bedding sand layer of 30 mm thickness and joints shall be filled by fine sand of specified grading as per table 1500.6 of Spec |
| 8 | Provision for Name board |
| 9 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |
| 10 | Part 02 : Improvements to Samathuva burial ground at Thasiripatty (Compound wall(25m), Waitingshed, CC Pavement(25m)water supply with Sintex tank in Kuttam panchayatEstimate Amount : Rs.7.43 Lakhs |
| 11 | Waiting shed |
| 12 | Earth work excavation and depositing on bank with initial lead and lift in hard gravelly soil as per SS20 B for foundation etc complete |
| 13 | Cement Concrete in 1 : 4 : 8 mix using 40 mm metal including cost and conveyance of all materials to site and labour charges etc complete |
| 14 | Refilling the basement with excavated earthother than sandcomplying the Standard specification |
| 15 | Brickwork in Cement mortar 1 : 5 mix using new II class bricks including cost and conveyance of all materials to site and labour charges etc complete. |
| 16 | Supplying and errecting shuttering including necessary support for plane surface in Foundation Basement and Roof slabs strutting upto 3.29 M height for plane surfaces for floors for RCC column footings columns plinth beam and connected with foundations grade beams, raft slabs stair case steps, bed blocks, critical pier, etc beams roof slabs, using mild steelsheets of size 90 x 60 cm and 10 gouge stiffened, welded with steel angles of size 25 mm x 25 mm x 3mm for boarding laid over silver oak (country wood) joists of 10 cm size x 6.5 cms size spaced at about 90 cms center to center and supported causorina props of 10 cm to13 cms spaced at 75 cms to center to center etc., complete complying with standard specification and as directed (SI - 155)for column |
| 17 | Column and Sunshade |
| 18 | …Do.. For Slab and Beam |
| 19 | Supplying, fabricating and placing in position mild steel or ribbed tor steel and all reinforced cement Concrete works as per the design given including cost of steel and binding wire in all floors etc complete complying with Standard (MS rods or RTS rod |
| 20 | R.C.C. 1:1.5:3-using 20mm ISS HBGS metal including cost and conveyance of materials and labour charges etc. complete |
| 21 | Supply ing and appl ying of two coats of p utty of 3 mm thick over the exposed RCC surfaceofceilingincludingfinishingthejointssmoothywithgrindingmachine andthesurfaceshallbethoroughlycleanedoutofdustandscrubbing. |
| 22 | Plastering with C. M 1:5 mix, 12 mm thick including cost and conveyance of all materials to site and labour charges etc complete. |
| 23 | C.C. 1:2:4-using 20mm ISS HBGS metal including cost and conveyance of materials and labour charges etc. complete |
| 24 | Painting two coats with approved PlasticEmulsion Paint over one coat of Primaring coat of Cement Paint over cement plastered wall surface, ceiling and other new surface including cleaning, preparing the surface, curing, scaffolding charges etc., complete complying with standard specifications |
| 25 | Compound wall |
| 26 | Earthwork excavation in all clauses of soils and depositing on bank with initial lead and lift for foundation as per ss20B |
| 27 | Cement concrete 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all matials to site and all labour charges etc., complete. |
| 28 | Supplying and erecting centering for sides and soffits including support and strutting cost and conveyance of all materials & all labour charges etc., complete. |
| 29 | RCC 1:11/2:3 mix using 20 mm ISS HBG metal including cost & conveyance of all materials to site and all labour charges etc., complete. |
| 30 | Supplying and fabrication of steel rods including cost & conveyance of steel as per std. Specification etc., complete. |
| 31 | Brick work in c.m 1:5 mix using country bricks including cost & conveyance of all materials to site and all labour charges etc., complete. |
| 32 | Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials & all labour charges etc., complete. |
| 33 | Painting two coats with ready mixed Plastic emulsion of first qualitypaint and Approved colour over priming coat including thorough Scrapping clean removal of dirt etc complete |
| 34 | Provision for CC Pavement |
| 35 | Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation. |
| 36 | Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. |
| 37 | Supply and errection of centering and shuttering charges for all PCC Works including all cost and conveyance of all materials and all labour charges etc complete |
| 38 | Cement concrete 1 : 2 : 4 mix using 20mm HBG metal including all cost and conveyance of all materials and all labour charges etc complete |
| 39 | Provision for bitumenpad charges including all cost and conveyance of all materials and all labour charges etc complete |
| 40 | Provision for Water Supply |
| 41 | 63mm PVC Pipe |
| 42 | 63mm PVC Elbow |
| 43 | HDPE Tank (1000Ltr) |
| 44 | 63mm PVC MTA |
| 45 | 63mm PVC Balvalve |
| 46 | labour charges for constructin of sintex tank pedastel arrangements including cost of masonrymeterialsand labour etc., complete. |
| 47 | Earth work excavation hard stiff clay and hard rock earth and pipe laying , jointing and refilling the trench with excavation soils For Pipeline |
| 48 | Labour charges for Laying of PVC Pipe and specials fixing charges etc., complete. |
| 49 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |
| 50 | Part 03 : Construction of Thresing Floor at Thasiripatty in Kuttam PanchayatEstimate Amount : Rs.9.21 Lakhs |
| 51 | Earthwork excavation for foundation in all clauses of soils and subsoils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring, struting and bailing out water wherever neccessary and refilling the sides of founda |
| 52 | Cement concrete 1:4:8 mix using 40mm ISS HBG metal for foundation including watering whenever necessary and laid in layers not more than 15cm thick compacting etc., complete complying with std. Specifications and as directed. Rate for 10 cum. |
| 53 | Supply and Filling of Conveyed earth including all cost and conveyance and all labour charges etc complete |
| 54 | Supply and Filling of M Sand including all cost and conveyance and all labour charges etc complete |
| 55 | Cement Concrete 1:3:6 mix using 40mm metalincluding all cost and conveyance and all labour charges etc complete |
| 56 | Brick work in c.m 1:5 mix using country bricks including cost & conveyance of all materials to site and all labour charges etc., complete. |
| 57 | Supply and erection of Centering and Shuttering including all cost and conveyance and all charges etc complete |
| 58 | Cement concrete 1:2:4 mix using 20mm ISS HBG metal including all cost and conveyance of all matirials and all labour charges etc complete ., |
| 59 | Plastering with cement mortar 1:5 mix to 12mm thick including curing, cost and conveyance of all materials & all labour charges etc., complete. |
| 60 | Supply Fabrication and erction of Steel Structure including cost and conveyance of all materials & all labour charges etc., complete. |
| 61 | Granolithic pattern floor finishing with CC 1:2:4 mix using 10-12mm ISS HBG Chips conveyance of all materials & all labour charges etc., complete. |
| 62 | Supplying and fixing colour galvalume sheet roof of 0.47mm thickand steel tubular box section of 100x50x3mm of 1meter interval including priming coat fixing in position with all necessary accessories complete complying with standard specification and as directed by the departmental officers. |
| 63 | Provision for Name board |
| 64 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |