| 1 | Electrical Items : |
| 2 | CT Clamp |
| 3 | PP & CLAMP WITH N&B ST POLE SP-55 |
| 4 | STAY CLAMP FOR SP-23 WITH NUT & BOLT |
| 5 | BRACING CLAMP BOTTOM WITH N&B SP-55 |
| 6 | BRACING CLAMP TOP WITH N&B SP-55 |
| 7 | PG Clamp for Panther |
| 8 | STAY CLAMP FOR SP-55 WITH NUT & BOLT |
| 9 | 11 KV H/S JOINTING KIT 120 SQ MM (I/D) |
| 10 | 11 KV H/S JOINTING KIT 120 SQ MM (O/ D) |
| 11 | GI Strip size 35x6mm |
| 12 | Isolator Clamp 33 KV |
| 13 | 8 SWG GI Wire |
| 14 | SERVICE (LABOUR) |
| 15 | 2.7.3 (DSR CODE 2014) |
| 16 | 2.25 (DSR CODE 2014) |
| 17 | 7.1.1 (DSR CODE 2014) |
| 18 | 7.2.1 (DSR CODE 2014) |
| 19 | 10.2 (DSR CODE 2014) |
| 20 | 10.29.1 (DSR CODE 2014) |
| 21 | 12.50 (DSR CODE 2014) |
| 22 | 13.4.2 (DSR CODE 2014) |
| 23 | 13.44.1 (DSR CODE 2014) |
| 24 | 15.2.1 (DSR CODE 2014) |
| 25 | 16.42 (DSR CODE 2014) |
| 26 | 1.14.6 (DSR CODE 2014) |
| 27 | EXCAVATION OF PIT FOR STAY SET |
| 28 | ERECTION OF 11 KV STAY SET |
| 29 | GROUTING OF STAY SET |
| 30 | EXCAVATION OF PIT FOR POLE |
| 31 | ERECTION OF SP-23 DOUBLE POLE |
| 32 | ERECTION OF SP-55 DOUBLE POLE |
| 33 | ERECTION OF SP-55(11KV/33 KV) FOUR POLE |
| 34 | GROUTING OF POLE |
| 35 | DISMANTLING OF 25 KVA DTR |
| 36 | PAINTING OF YARD |
| 37 | FENCING OF DTR |
| 38 | INST. OF 250 KVA DTR ON PLINTH |
| 39 | LAYING OF DOG CONDUCTOR IN HT LINE |
| 40 | FIXING OF 11 KV XLPE JOINTING KIT |
| 41 | CARTAGESP-21/23 POLE, 71-100 KM |
| 42 | CARTAGESP-55 POLE, 71-100 KM |
| 43 | CARTAGE OF PANELS, 71-100 KM |
| 44 | CARTAGE 33/11 CT/PT/ISOLATOR, 71-100 KM |
| 45 | HEADLOAD CARTAGE OF 25 KVA DTR(0-1 KM) |
| 46 | HEADLOAD CARTAGE OF 250 KVA DTR(0-1 KM) |
| 47 | MANUAL SHIFTING OF 33 KV VCB |
| 48 | MANUAL SHIFTING OF 33 KV ISOLATOR |
| 49 | MANUAL SHIFTING OF 33 KV CT/PT COMBINED |
| 50 | GROUTING OF STRUCTURE IN CC 1:3:6 |
| 51 | INSTALLATION OF 33 KV CT WITH ALL CONN. |
| 52 | ERECT.33 KV CONTROL PANEL(FDR/T/ F) |
| 53 | ERECTION OF 33 KV VACCUM CIRCUIT BREAKER |
| 54 | CEMENT CONCRETING WORK DTR PLINTH |
| 55 | Laying of 11KV Cable in Trench all work |
| 56 | Testing of 33 KV VCB |
| 57 | DISMANTLE OF EXITING TPMO/GO/ ISOLATOR |
| 58 | CARTAGE OF 33 KV VCB |
| 59 | INSTALLATION / FIXING OF 33 KV ISOLATOR |
| 60 | MAKING OF TRENCH COVER |
| 61 | LAYING OF CONTROL CABLE |
| 62 | PROVIDE AND FIX JAW OF 33 KV ISOLATOR |
| 63 | PROVIDE AND FIX BLADEOF 33 KV ISOLATOR |