| 1 | Fitting one set AB switch and giving connection |
| 2 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP incl. conveyance of materials. |
| 3 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 4 | Providing one Earth using earth pipe incl. digging & backfilling pit and supply of charcoal, salt, sand etc. |
| 5 | Erection of Anchor clamp / dead end clamp for 11kV ABC of any size |
| 6 | Fitting and erecting one HT DP using PSC pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing earth leads. |
| 7 | Loading HT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 8 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole incl. digging & back filling pits. |
| 9 | Fitting and erecting one HT PSC Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 10 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit. |
| 11 | Fitting and providing one Strut using HT PSC pole incl. digging & back filling pit. |
| 12 | Providing one Coil Earth using GI earth wire, digging separate pit at standard distance away from the pole/structure & backfilling. |
| 13 | Fiting One no MVT on existing cross arm including 2 nos end termination (for One phase) of any rating for 11 kV AB Cable |
| 14 | Erection of suspension clamp for 11KV ABC of any size |
| 15 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading. |
| 16 | Stringing of 11 kV Aerial bunched cable of size 3 x 120 + 1 x 95 sqmm with bare/insulated Messenger through existing poles |
| 17 | Erecting one 100kVA Transformer to existing DP and giving connections, incl. loading & unloading, excluding transportation. |
| 18 | Transporting Transformers by hired vehicle upto 5km and upto 2 No. of 63 to 250kVA Transformers / RMUs excluding loading & unloading. |
| 19 | Fitting 5 channel cross arms, AB switch, DO fuse, LA, HT & LT connections on existing DP, 3 LT fuses. |
| 20 | Fitting one additional Fuse unit and giving connection from Transformer to fuse and DB to LT OH line. |
| 21 | Providing Transformer fencing , using 50x50x6mm Angle iron, 40 x 6 mm MS flat and 8 mm MS rod as specified, incl cost of transportation & foundation |
| 22 | Providing yard metalling with 6mm & 40mm thick blue metal as specified after constructing a curb wall. |
| 23 | Installing one DTR Meter with box on existing poles and giving the complete connections incl. conveyance of materials. |
| 24 | Loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 25 | Fitting and erecting one HT A type Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 26 | Fitting and erecting one HT DP using A type pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing earth leads. |
| 27 | Erection of suspension clamp for LT ABC of any size |
| 28 | Erecting one LT PSC Pole in position incl. digging & back filling pit. |
| 29 | Loading LT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 30 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 31 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 32 | Providing Stay for LT poles incl. digging & back filling pit. |
| 33 | Providing Strut using LT PSC pole incl. digging & back filling pit. |
| 34 | Installing One No. 4 way Satellite Connector of size Main :16 to 95, Tap:4 to 35 Sq.mm to the LT AB cable of Standard size |
| 35 | Transporting LT ABC by hired vehicle to a distance up to 5 km and carring up to 2 drum including loading and un loading using crane |
| 36 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 37 | Dismantling (without damage) one km LT Sph 2 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 38 | Dismantling (without damage) one km LT 3ph 4 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 39 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 40 | Installation of Pre-insulated straight through joints for 16sqmm cable |
| 41 | Installation of Pre-insulated straight through joints for 50sqmm cable |
| 42 | Installation of Pre-insulated straight through joints for 70sqmm cable |
| 43 | Dismantling and reconnecting Sph service connection from the OH line incl. lowering down the WP portion. |
| 44 | Dismantling and reconnecting 3ph service connection from the OH line incl. lowering down the WP portion. |