| 1 | Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed. |
| 2 | Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75m. In ground floor. Up to 150mm thick. |
| 3 | Scraping of moss, blisters etc.thoroughly from exterior surface of walls necessitating the use of scraper, wire brush etc.(Payment against this item will be made only when this has been done on the specific direction of the Engineer-in-charge). |
| 4 | Removing old scales, blisters etc. of interior surface of walls,ceiling by scraping etc. and preparing smooth and even surface with rendering or cement mortar (1:2) (as necessary), to make the surface suitable for receiving distemper. (Payment against this item will be made only when this has been done on the specific direction of the Engineer-in-charge). |
| 5 | Removal of rubbish, earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge. |
| 6 | Single brick flat soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with powdered earth or local sand. |
| 7 | Cement concrete (1:3:6 proportion) with graded stone ballast (40 mm. size) excluding shuttering. a) [Pakur Variety]. i) In Ground floor |
| 8 | 125 mm. thick brick work with 1st class bricks in cement mortar (4:1) . i) In ground floor |
| 9 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints or rougening of concrete surface, including throating, nosing and drip course where necessary. a) 20 mm. thick plaster (6:1). i) In ground floor |
| 10 | b) 15 mm. thick plaster (6:1) (i) In ground floor |
| 11 | b) 10 mm. thick plaster (4:1) (i) In ground floor |
| 12 | Wood work in door and window frame fitted and fixed in position complete including a protective coat of painting at the contact surface of the frame exluding cost of concrete, Iron Butt Hinges and M.S clamps. (The quantum should be correted upto three decimals). (c) with Sal : Siliguri. |
| 13 | Supplying, fitting and fixing M.S. clamps for door and window frame made of flat bent bar, end bifurcated with necessary screws etc. by cement concrete(1:2:4) as per direction. (Cost of concrete will be paid separately) (a) 40mm X 6mm, 250mm Length |
| 14 | Supplying, fitting & fixing 1st quality Ceramic tiles in walls and floors to match with the existing work & 4 nos. of key stones (10mm) fixed with araldite at the back of each tile & finishing the joints with white cement mixed with colouring oxide if required to match the colour of tiles including roughening of concrete surface, if necessary or by synthetic adhesive & grout materials etc.(A) Floor : With Sand Cement Mortar (1:4) 20 mm thick & 2 mm thick cement slurry at back side of tiles using cement @ 2.91 Kg/Sq.m & joint filling using white cement slurry @0.20kg/Sq.m. (b) Area of each tile above 0.09 Sq.m. (i) Coloured decorative. |
| 15 | (B) Wall : With Sand Cement Mortar (1:3) 15 mm thick & 2 mm thick cement slurry at back side of tiles using cement @ 2.91Kg/Sq.m & joint filling using white cement slurry @0.20kg/Sq.m. (b) Area of each tile above 0.09 Sq.m. (ii) Other than Coloured decorative including white. |
| 16 | Iron butt hinges of approved quality fitted and fixed with steel screws, with ISI mark.(vii) 100mm. X 58mm. X 1.90mm. |
| 17 | Anodised aluminium barrel / tower / socket bolt (full covered) of approved manufactured from extruded section conforming to I.S. 204/74 fitted and fixed with cadmium plated screws: (vi) 200mm long x 10mm dia. bolt. |
| 18 | Anodised aluminium Aldrop / Sliding bolts of approved quality manufacturedfrom extruded section conforming to I.S. specification (I.S. 2681/66) fitted and fixed complete. (i) 250mm x 16mm dia bolt. |
| 19 | Anodised aliminium D-type handle of approved quality manufactured from extruded section conforming to I.S. specification (I.S. 230/72) fitted and fixed complete: (vi) 150 mm grip x 10 mm dia rod. |
| 20 | Supplying solid flush type doors of commercial quality, the timber frame consisting of top and bottom rails and side styles of well seasoned timber 65mm wide each and the entire frame fitted with 37.5mm wide battens places both ways in order to make the door of solid core and internal lipping with Garjan or similar wood veneers using phenol formaldehyde as glue etc. complete, including fitting, fixing shutters in position but excluding the cost of hinges and other fittings in ground floor.: (a) 35mm thick shutter. |
| 21 | Rendering the surface of walls and ceiling with white cement based wall putty of approved make and brand(1.5mm thick) |
| 22 | Applying Interior grade Acrylic Primer of approved quality and brand on plastered or cencrete surface old or new surface to receive Distemper/ Acrylic emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer\"s specification and as per direction of the EIC. (In Ground Floor) (b) Two Coats.i) Water based interior grade Acrylic Primer |
| 23 | Applying Acrylic Emulsion Paint of approved make and brand on walls and ceiling including sand papering in intermediate coats including putty (to be done under specific instruction of Superintending Engineer) : (Two coats)i) Standard Quality. |
| 24 | Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer\"s specification and as per direction of the EIC. In grounf floor.(b) Two Coats |
| 25 | Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer\"s specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer.In Ground floor (Two Coat). b) Premium 100% Acrylic Emulsion. |
| 26 | ADD GST @18% (on total amount of Sl. No. 1 to 22) |
| 27 | ADD LABOUR WELFARE CESS @1% (on total amount of Sl. No. 1 to 23) |