| 1 | Construction OfKitchen Shed @ Ponnagaram Govt High School in Manamelkudi Panchayat. |
| 2 | Earth work excavation in all classess soil with initinal lead and lift as per SS 20B etc complete. |
| 3 | Filling with M sand including cost and conveyance of sand to work site including all labour charges for filling etc complete - rate for 1 cu.m |
| 4 | Cement concrete 1:4:8 mix using 40mm HBG metalincluding cost and conveyance of all materials to site including all labour charges for filling etc complete - rate for 10 cu.m |
| 5 | Centring for sides and soffits including cost and conveyance of all labour charges etc complete. |
| 6 | Supplying, fabricating and placing in position mild steel/Ribbed tor steel rods for all RCC works including cost of steel and binding wire also in all floors, complete complying with standard specfication. |
| 7 | R.C.C. 1:1.5:3 mix using 20mm HBG metalincluding cost and conveyance of all materials to work site and all labour charges etc.complete - rate for 10 Cu.m |
| 8 | BRICK WORK in cement mortar 1:5 (One cement and five sand) using second class country bricks of size 23cm x 11cm x 7cm for the following including curing etc., complete complying with standard specifications. |
| 9 | SPECIAL CEILING PLASTERING and finishing all the RCC exposed surfaces such as RCC slabs, sunshades, canopies, staircase steps, landing slabs, etc. with cement mortar 1:3,10mm thick and including hacking the surfaces and provid |
| 10 | PLASTERING with cement mortar 1:5 (one cement and five sand)12mm thick in all floors complying with standard specifications. |
| 11 | Providing Granolithic Pattern Floor finish with plain cement concrete 1:2:4 using 10-12 mm ISS HBG metal and top rubbed smooth etc., complete complying with standard specification as directed. (25mm thick) |
| 12 | Weathering Course Concrete to 80 mm thickness (average) using 20mm size Brick jelly with slacked lime in the proportion 32:12:50 (No sand to be used) including cost and conveyance of all materials to work site and all labour charges etc., complete. |
| 13 | Finishing the roof with one course of pressed tiles size 23x23x2cm and top of pointing with c.m 1:3 mix including all labour charges etc complete. |
| 14 | Distember two coats over one coat of primary coat including cleaning preparing the surface one coat of primer. For Inner and ceiling |
| 15 | Emulsion two coats with Exterior emulsion over one coat of primary coat including cleaningpreparing the surface |
| 16 | Painting two coats using Ist quality readymix enamel paint of approved colour over new iron work including cost and conveyance and all labour charges etc. |
| 17 | Towards the cost of steel door of size 0.90 m x 2.10 m including all charges etc. |
| 18 | Towards the cost of paneled window of size0.90 m x 1.30 m including all charges |
| 19 | Wiring with 2x1.50 Sq.mm (22/0.30) PVC insulated SC unsheated Copper conductor cable of 1100V grade in suitable PVC rigid pipe concealed in wall and ceiling with PVC accessories inflush with wall with 3mm thick PVC concealed Light Point / Fan Point |
| 20 | Wiring with 2x1.50 Sq.mm (22/0.30) PVC insulated SC unsheated Copper conductor cable of 1100V grade in suitable PVC rigid pipe concealed making good of the Concealed portion with suitable colour for PVC concealed Light Point / Fan Point SD 38 |
| 21 | Supply and run of 2 of 6 Sq.mm (22/0.3) PVC insulated SC unsheated copper conductor of 1100 V grade on 7/20 GI bearer wire for service connection mains SD 62 |
| 22 | Supply and run of 2 of 1.5 Sq.mm (22/0.3) PVC insulated SC unsheated copper conductor of 1100 V grade in 25mm dia GI Pipe (Class \"B\") suitably bent at both ends withmains SD 67 |
| 23 | Supply and delivery and fixing of PVC tank as per IS 12701 / 1996 including loading, unloading, transportation and labour charges for fixing of the GI pipes and specials for pipe connection works including cutting, threading and fixing charges etc., |
| 24 | Supply and Fixing of tube light |
| 25 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) |