| 1 | Earthwork in excavations of foundation trenches in all kinds of soil including morrum, stoney earth and earth mixed with boulders except sheet rocks and boulders requiring blasting, including dressing and levelling the bed up to required level and depositing the excavated earth away from the site within 50 m initial lead and 1.5m initial lift, T & P centring and shuttering if required etc complete as directed by Engineer in charge. |
| 2 | Supplying, filling in foundation and plinth with clean course river sand including watering ramming with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge (measurement will be taken for finished complete section only) |
| 3 | CC (1:4:8) in foundation and floors using 40mm size crusser broken granite stone metal of approved quality from approved quarry including lowering laying of concrete, watering, curing etc, compacting to required level laid in layers not exceeding 0’-6” thick, with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 4 | RCC work with M25 Grade concrete with 20mm and down graded crusher broken chips having a minimum crushing strength in work test (150 kg/ sqcm) in 15 cm cubes after 28 days curing after mixing and test conducted in accordance with IS-456 and IS-516 including hoisting, lowering, laying concrete, compacting by using vibrators, centring and shuttering and finishing the exposed surface smooth, providing proves and beads wherever necessary with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 5 | In column footing |
| 6 | In column |
| 7 | In plinth beam |
| 8 | In tie beam |
| 9 | In slant of Gabble wall |
| 10 | Cutting, straightening, coiled or bend up MS rod or Tor steel, bending binding, cranking, hooking, welding or jointing if necessary and tying the grills and placing in position for RCC work in all floors and for proving fan hooks, hoisting lowering, laying for concrete with cost of reinforcement, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. (payment will be made on weigh of steel only basing on the coefficient of MS or Tor steel bar approved by competent authority and no separate payment will be made for cost of binding wires) |
| 11 | Fly Ash Brick masonary in (1.6) cmin foundation and plinth in ncluding scaffolding, watering, curing etc required for the work with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. (in foundation and plinth) |
| 12 | Fly Ashmasonary in (1.6) cmin superstructure in ncluding scaffolding, watering, curing etc required for the work with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. (in super strucure) |
| 13 | 16mm thick cement plaster (1:6) in all floors finishing smooth to brick walls after racking out joints etc, including watering, with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 14 | 12mm thick cement plaster (1:4) in all floors finishing smooth to brick walls after racking out joints etc, including watering, with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 15 | Supply of all materials, fabricating MS GRILLS as per direction & Fixing the same in position after cutting of brick work as required fixing the grills with concrete and making the suface good after fixing of MS grills |
| 16 | Supply of all materials for fabrication of MS windows with doube openble leafsmade out of iron member and iron sheets of required specifications as directed and fixing the same to required place as directed including executing all items of works for fixing the same and completing the work as per direction of engineer-in-charge . |
| 17 | Supplyand fixing of MS wiremesh with adequate MS member for fixingand fixing the same to required place as directed including executing all items of works for fixing the same and completing the work as per direction of engineer-in-charge . |
| 18 | Cement wash including watering with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 19 | Painting wall with two coats of cement paint with approved shade over a coat of cement wash including watering with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 20 | Paintingof primer coats on new surfaces including cost of paint and T&P and cost of all other materials such as scafolding, ropes etc and completing the work as per direction of engineer in charge |
| 21 | Wall painting 2 coats with Weathercoat paint of approvedshade on new work to give an even shade including cost of paint and T&P and cost of all other materials such as scafolding, ropes etc and completing the work as per direction of engineer in charge |
| 22 | Supplying and on site assembling and erecting trusses of approved design for main godown and cantilever trusses inplatform side only. This includes erection of trusses, purlins, BTR and false rafters, sleeves and placing of wind bracing etc with nuts and bolts with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 23 | Supply and fixing of Colour Coated Profile sheet 0.50 TCT in roof incuding fixisng of ridges and windties excluding cost wind-ties but including the cost of J hooks with cost, conveyance, taxes & royalties of all material and cost of all labour T&P required for the work etc., complete as directed by Engineer in charge |
| 24 | Supply and fixing of windties after drilling of holes as required and as directed by engineer in charge including all labour, material for hoisting and tying and completing the work in all respect |
| 25 | Supply of materials and executing the work of laying of wiremesh of sieve size 25*32 mm made out of 1.5 mm galvanised wire before floor concrete, fixing the same to floor rigidly to recieve floor concrete properly including cost of all labour, material for hoisting and tying and completing the work in all respect |
| 26 | Supply of all materials for fabrication of Rolling Shutters made out of iron member and iron sheets of required specifications as directed and fixing the same to required place as directed including executing all items of works for fixing the same and completing the work as per direction of engineer-in-charge . |
| 27 | Supply of all material and labour for the work Centring and shuttering for RCC Works and finishing the work in all respect as per direction of engineer-in-charge |
| 28 | Column footing |
| 29 | Column |
| 30 | Plinth beam |
| 31 | Lintel |
| 32 | In slant of Gabble wall |
| 33 | Painting of two coats with approved quality eanamel paint (Asian Paints) over iron workincluding cost of scafolding etc andcompleting the work in all respect as per direction of engineer in charge |
| 34 | CC (1:2:4) in flooring using 12mm size hard crusher broken granite chips including hoisting, lowering, laying concrete, providing and watering with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 35 | CC (1:2:4) in flooring using 6 mm size hard crusher broken granite chips including hoisting, lowering, laying concrete, providing and watering with cost, conveyance, taxes & royalties of all material and cost of all labour T & P required for the work etc., complete as directed by Engineer in charge. |
| 36 | Collection of non grinite stones for filling, size 15 cms minimum and stacking them at site for cinvinience in measureing in uniform sizes, including cost of materials labour etc hoisting and lowering if any and completing the work in all respect as per direction of engineer -in- charge, |
| 37 | Collection of morrum for filling, and stacking them at site for cinvinience in measureing in uniform sizes, including cost of materials labour etc hoisting and lowering if any and completing the work in all respect as per direction of engineer -in- charge, |
| 38 | Conveying from stacks and laying of morrum subbase and compacting with PRR in cluding watering including cost of material, labour and all other charges and completing the work in all respect as per direction of enginner in charge |
| 39 | Conveying from stacks and laying of morrum and stone base and compacting with PRR in cluding watering including cost of material, labour and all other charges and completing the work in all respect as per direction of enginner in charge |
| 40 | Supply of all materials abd executing the work of Tarfelting including cost of all material, labour, firewoor, hoisting and lowering of materials and cost of scaffoldings if any and completing the work in all respect as per direction of engineer in charge |