| 1 | Supply Installation Testing and Commissioning of UL 864 and FM approved (or) any equivalent standard 2 Loop IP based Analog addressable Fire Alarm system, having the total panel capacity of 252 devices. The panel shall be able to give location of all fire and More Fire /fault and Isolation conditions of addressable units via the address codes.The panel shall have the capacity of storing upto 10000 events. Further, the panel must be able to automatically switch ON /OFF respective control module when ever any alarm is triggered. The panel should have inbuilt common Alarm, Fault and monitored sounder output. The panel shall have a built in power supply of 170 Watts and battery charger. Battery charger shall be able to charge the system batteries of up to 33 AH capacity. The Panel shall have the capacity of connecting additional 31 panels or Network terminals using network card. The panel shall have the capacity of connecting maximum 16 Remote terminals /16 remote displays or combined by using 2 X RS 485 Card; all as per specification and as directed by Engineer In Charge. |
| 2 | Supply Installation Testing and Commissioning of UL 268and FM approved (or) any equivalent standardIntelligent Addressable multi-criteria detector (optical and thermal sensors) complete with standard base, facility to mount in different comprehensive environment, Tri-color detector-status LED with 360 ° view, microprocessor circuitry with error check; detector self-diagnostics and supervision programs,Rate-of-Rise Detection: 15°F / min. (8.3°C / min.) - Fixed: 135°F (57°C) , Field programmable as rate-of-rise or fixed temperature, Polarity insensitive, Superior EMI and RFI immunity, RoHS compliant. Detector shall have in-built isolator for better reliability; all as per specification and as directed by Engineer In Charge. |
| 3 | Supply Installation Testing and Commissioning of Thermal Detectors shall be rated at 135°F (57°C) fixed temperature and 15°F (8.3°C) per minute rate of rise. Detectors shall be constructed to compensate for the thermal lag inherent in conventional type detectors due to the thermal mass, and alarm at the set point of 135 °F.The choice of alarm reporting as a fixed temperature detector or a combination of fixed and rate of rise shall be made in system software;all as per specification and as directed by Engineer In Charge |
| 4 | Supply Installation Testing and Commissioning of UL listed and FM approved (or) any equivalent standardIntelligent Addressable microprocessor based Multicriteria detector, Provides enhanced detection having two optical and two thermal sensors or two Optical One Thermal or equivalent multi criteria detector havingDifferentiates between deceptive phenomena and an actual fire (nuisance-alarm avoidance) and complying with NFPAas \"VEWFD\" high-sensitivity detector. Shall have Up to 22 application profiles. with five (5) possible field-selectable temperatures combined with four (4) rate-of-rise options.Tri color LED, Green for Normal, Amber /yellow for trouble and Red for alarm. Shall be Polarity Insensitive; all as per specification and as directed by Engineer In Charge |
| 5 | Supply Installation Testing and Commissioning of Conventional Sounder cum strobe having 2 different tone settings with range of 90 dbA and 95 dbA and field selectable 15/30/75/110 candelas; providing separte output module and 24 V DC power supply] with control module; all as per specification and as directed by Engineer In Charge |
| 6 | Supply Installation Testing and Commissioning of UL listed Intelligent addressable Class X type (Style 7) Manual Call Point, Single Action, Shock and Vibration Resistant, with built in dual isolator, polarity insensitive, Tri color LED for status (Green for Normal,Yellow for Faulty and RED for activation), T-45 Key Reset lockset for easy maintenance, Operating Temp and RH: 0-49degC and <=95%. MCP shall have in-built isolator for better reliability; all as per specification and as directed by Engineer In Charge |
| 7 | Supply and Installation of micro controller based Auto Dialer (GSM) based module to alert to mobile numbers through speech and SMS dialer; The Auto Dialer shall be capable of communicating to15 different mobile number during emergency call and shall capable of20 secounds recorded message to the each number shall be communicated for each message; all as per specification and as directed by Engineer In Charge |
| 8 | Supply and Installation of 2Cx1.5 Sq mm Armoured Cable; as per specification and as directed by Engineer In Charge |
| 9 | Removal of old 2C x 1.5 Sq mm armoured cables installed in various location, which includes removing of saddle support present in the cable, filling the removed portion of saddle with putty cement matching to the wall paint; the scope of work also includes removing of detector, Manual Call Point (MCP), sounder present in the loop etc... all complete as per directions and approval of Engineer-in-charge. |
| 10 | Providing Telescopic pole of 4.5 m + 1.13 m along with Detector Removal Tool Kit; Dispenser Kit and Aerosol A10S (Non Flammable) of total 10 Nos; all complete as per directions and approval of Engineer-in-charge. |
| 11 | Providing and fixing double scaffolding system (cup lock type) on the exterior side at all height made with 40mm diameter M.S. tube spaced @ 1.5 m centre to centre at both horizontal and vertical tubes, joining with cup and lock system with M.S.tube, M.S.tube challies, M.S clamps and M.S staircase system in the scaffolding for working platform etc., and maintaining it in a serviceable condition for the required duration as approved and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners connection with the building, etc., Wherever required for the inspection of work at required location with essential safety features for the workmen, etc., complete as per directions and approval of Engineer-in-charge. (Note: The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding.) |
| 12 | Carryingout IR testing for all the armourced cables installed in the locations irespective of the length of the loop not more than 200 m or 25 detectors; Testing of cables which includes removing the old detector/Manual Call Point/Sounder etc... present in the loop; interconnecting the cable between the detector to ensure the continuity in the cable; measuring the IR values in the loop by using insulation tester resistance meter, all complete as per directions of Engineer-in-charge. |
| 13 | Supply and fixing of20 mm Cassing and Capping; as per specification and as directed by Engineer In Charge |
| 14 | Supply and Fixing of Glanding on the Panel, Detector, Sounder, MCP along with proper termination; as per specification and as directed by Engineer In Charge |
| 15 | Supply and Laying of 3 core X 2.5 Sq.mm armoured cable; as per specification and as directed by Engineer In Charge |
| 16 | Supply and Installation of 10A 2 pole MCB with back box along with enclosure along with proper termination; all complete as per directions of Engineer-in-charge. |
| 17 | Removal of old existing panel installed in the substation; which includes dismantling of base frame, cablesand other accessories; all as per directions and approval of Engineer-in-charge. |