| 1 | Work items identified; |
| 2 | Supply, installation, testing and commisioning of100 kVA ,11/0.433kV, 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Level-2, Aluminium wound , and with LV Cable Box having detachable Aluminium Gland plate 11/0.433KV, 3-phase(EE Level-II)complete in all respect as perStandards. |
| 3 | Supply, installation, testing and commisioning of 9 mtr (410 SP-33) long Steel Tubular Poles complete with base plate(350x350x5mm), top cap, Earthing Channel(75x40x6mm) including digging of pitpositioning etc, complete in all respect as per Standards. |
| 4 | Supply, installation, testing and commisioning of 8 mtr(410 SP-15) long Steel Tubular Poles complete with base plate(350x350x5mm), top cap, Earthing Channel(75x40x6mm) positioning etc, complete in all respect as perStandards. |
| 5 | Supply, laying, stringing, tensioning, binding of 50 Sqmm ACSR Conductor complete in all respects as per standards. |
| 6 | Supply, laying, stringing, tensioning, binding of 30 Sqmm ACSR Conductor complete in all respects as perstandards. |
| 7 | Supply,Carraige upto site and fixing ofGI V cross-arm with top Bracket including clamp duly fabricated as per site requirement including clamps(50x8 mm),GI Nuts & Bolts,washers etc complete in all respects as perstandards. |
| 8 | Supply,Carraige upto site, fixing and installation of GI Channels of different sizes including clamps and braces. |
| 9 | Supply,Carraige upto site,Installation,testing and Commissioning of 11kV Polymeric composite Pin Insulators 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mmcomplete in all respects as per standards. |
| 10 | Supply and fixing of Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6) mm, nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete in all respects as per standards. |
| 11 | Supply,Carraige upto site,Installation,testing and Commissioning of 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mmcomplete in all respects as per standards. |
| 12 | Supply, Carraige upto site, installation, testing and Commissioning of Gapless Surge Arrestor 9 kV, 10 kA, LA with polymer housing, Stn. Type complete in all respects as perstandards. |
| 13 | Supply, Carraige upto site, installation, testing and Commissioning of 11 kV G.O AB Switch 3-phase, 3 pole 200-Amp, vertical Type with fittings complete in all respects as perstandards. |
| 14 | Supply, Carraige upto site, installation, testing and Commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200Acomplete in all respects as perstandards. |
| 15 | Supply, Carraige upto site, laying, stringing, tensioning, binding of 120/185mm² (1Ckt )1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type cable complete in all respects as per standards. |
| 16 | Supply,Carraige upto site, fixing ofAluminium Thimbles of size 120/185 Sqmm. |
| 17 | Supply,Carraige upto site, fixing and Commissioning of Aluminium Solderless Clampsof size 120/185 Sqmm. |
| 18 | Supply, Carraige upto site, installation, testing and Commissioning ofLT Distribution Box for - i) 63 kVA DTR with 100 Amp MCCB 3P 16 kA for incomer & 100 Amp MCCB 3P 16 kA 1 No. and 63 Amp MCCB 3P 16 kA 1 No.s for Outgoing Circuits. ii)100 kVA DTR with 160 MCCB 3P 16 kA for incomer & 100 Amp MCCB 3P 16 kA 2 No.s for Outgoing Circuits..complete in all respects as per standards. |
| 19 | Earthing of substation-Excavation ofearth pit of dia650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 25 mmx3 mm, for connection of transformer body,G.O set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover complete in all respects as per standards. |
| 20 | Supply,Carraige upto site, fixing of G I Muky Clamps. As per standards |
| 21 | Supply,Carraige upto site, fixing of45 KN Shackale insulators as per standards. |
| 22 | Cement bottoming 1:2:4 mix as per Standards 0.5cum/0.45 cum pole comlete in all respects. |
| 23 | Earthing of steel tubular poles complete by GI pipe 40mm or GI rod 20mm 3.0 mtr long through GI strip 25x3 as per standards. |
| 24 | Painting of Poles with one coat of Red Oxideand two coats of alimunium paintto give uniform shine. |
| 25 | Supply and fixing ofGI barbed wire Anti climbind Device with clamps complete in all respects as perStandards |
| 26 | Supply and fixing of danger plates with clamps complete in all respects as perStandards |
| 27 | Paint mark of scheme |
| 28 | NOTE: 1.The rates quoted by the bidder for all the items shall be inclusive of GST/freight/insurance/storage/installation/testing and any other charges FOR Creation of 100 kVA/63 new Substations along with HT/LT networkunder the jurisdiction of ED Budgam, KPDCL. |