Dakshinanchal Vidyut Vitran Nigam Limited-DVVNL has published Tender For Work Of Increasing Capacity Of Transformer, Installation Of New Transformer, 11 Kv/Lt Line Erection And Strengthening Of Other Work In The Area Of Edc Etah Under Business Plan 2024-25 On Semi Turnkey Basis.. Submission Date for this Tender is 01-06-2024. Transformer Supply Tenders in etah Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 27-May-2024 | Date_extention_5 | Date | 29-05-2024 |
2 | 29-May-2024 | Date Extention_2018 | Date | 01-06-2024 |
Sl. No. | Item Description |
1 | Supply of The Line Material as per Relevent ISS :- |
2 | Copper L Piece 50x225x10 mm |
3 | TF Holding Clamp |
4 | MS T Channel with Clamp |
5 | MS Top Channel |
6 | Stone Pad |
7 | Dropper Channel 100x50x2028 |
8 | 11 KV Fuse Set |
9 | 11 KV F Clamp |
10 | Nut and Bolts off size |
11 | Suspension Clamp |
12 | Dead and Clamp |
13 | I Hook |
14 | AB Cable 1x16+1x25 sq mm |
15 | 3 Phase Distribution Box |
16 | 3 Phase DO Distribution Clamp |
17 | PRC Connecter |
18 | LT Clamp |
19 | MS Angle (TF Base Angle) with Clamp. |
20 | Clamp for TF |
21 | LT PVC Cable 4x16 sq mm |
22 | LT PVC Cable 3.5x70/35 sq mm |
23 | PVC Alluminium Cable 1x120 sq mm |
24 | I Bolt for Service Cable |
25 | GI Wire 10 SWG |
26 | Erection Work :- |
27 | Safe carriage of line material from store center Etah to pit site in distance range 0 to 60 km including loading & unloading at both ends. |
28 | Safe Carriage of 8.5 Mtr Long PCC Pole from Electricty store center Etah/nearest 33/11 KV S/S to direect Pit site in distance range 0 to 60 Kms.Including loading and unloading at both side |
29 | Safe Carriage of 11 Mtr Long ST Pole from Electricty store center Etah/nearest 33/11 KV S/S to direect Pit site in distance range 0 to 60 Kms.Including loading and unloading at both side |
30 | Safe Carriage of following TF from Electricty store center Etah/nearest 33/11 KV S/S to direect Pit site in distance range 0 to 60 Kms.Including loading and unloading at both side. |
31 | 16 KVA TF |
32 | 25 KVA TF |
33 | 63 KVA TF |
34 | 100 KVA TF |
35 | 250 KVA TF |
36 | Erection of 8.5 mtr long PCC Pole as single support including fixing of HT/LT accessories etc complete, pole should be gruted properly as per DVVNL/Respo norms. |
37 | Erection of 8.5 mtr long PCC Pole as Double Pole/Section Pole including, drilling, cutting etc and fixing of all HT/LT accessories with TPMO etc complete, pole should be grouted properly as per DVVNL/RESPO norms. |
38 | Erection of 11 mtr ST Pole as single support including fixing of all HT/LT accessories etc. complet, pole should be grouted properly as per DVVNL/RESPO norms. |
39 | Erection of 11 mtr ST Pole as Double Pole/Section Pole including fixing of all HT/LT accessories etc. complete, pole should be grouted properly as per DVVNL/RESPO norms. |
40 | Laying sagging stringing, binding, jumpering & fixing of all accessories etc of following conductor on the newly/old erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carrier etc required for proper completion of work. |
41 | ACSR Weseal Conductor |
42 | AB Cable 1x16+1x25 sq mm |
43 | AB Cable 3x50 sq mm |
44 | AB Cable 3x95 sq mm |
45 | LT XLPE Cable 1x400 sq mm |
46 | LT XLPE Cable 1x240 sq mm |
47 | LT XLPE Cable 3.5x150 sq mm |
48 | Stone Pad |
49 | Suspention Clamp |
50 | Erection and grouting of stays as per RESPO Norms and as per direction of supervising engineer. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
51 | Earthing Complete |
52 | 3 Phase Distribution Box with clamp |
53 | Dead end Clamp |
54 | PRC Connector A&B Type |
55 | LT PVC Cable 4x16 sq mm |
56 | LT PVC Cable 3.5x70/35 sq mm |
57 | PVC Alluminium Cable 1x120 sq mm |
58 | Copper L Piece 50x225x10 mm |
59 | 11 KV Fuse Set |
60 | GI Wire 10 SWG |
61 | Installation of 250 KVA T/F on newly constructed Plinth in proper alignment direction & making HT/LT connection all Cost of labour and T&P which required for completion of work |
62 | Providing and fixing of welded wire mesh fencing around transformer plinth with MS Angle of size 40x40x6 mm length and 1.20 mtrs height. Such panels shall be supported on MS angle from of size 40x40x6 mm having 04 nos corner supports of height 1.65 mtrs including extended legs for grouting which will be used as a door for entry of the personnel or removal/shifting of transformer with welded hinges, sliding belt etc for lockingarrangement as per drawing and specifications. The fencing will be painted in the green colour synthetic enamel paint after painting with one coat of red oxide primer. The rates should be inclusive of all materials required for completion of above work. (Length of each fencing approx. 11 mtrs) with T& P labour etc. |
63 | Pipe earthingup to water level of 250 KVA medium Power Transformers |
64 | Mounting offollowing TF on D/P including making of the connection etc. complete. |
65 | 16 KVA TF |
66 | 25 KVA TF |
67 | 63 KVA TF |
68 | 100 KVA TF |
69 | 250 KVA TF |
70 | Carriage of following old material from pit site to JE store/store center Etah in distance range 0 to 60 km. including loading & unloading and proper stacking. |
71 | 10/16 KVA TF |
72 | 100 KVA TF |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy