| 1 | Safe carriage, loading and unloading of following material from ESC Daliganj, Lucknow to work site/J.E. dump store. |
| 2 | 11/0.4 K.V. 250 K.V.A. Transformer. |
| 3 | LT XLPE Aluminum cable size 3.5X400 Sq.mm. |
| 4 | LT XLPE Aluminum cable size 1X400 Sq.mm. |
| 5 | 11 K.V. LT XLPE Aluminum cable size 3x70 Sq.mm. |
| 6 | Cable LT ABC (3X120+1X95+1X16 Sq.mm.) |
| 7 | S.T. Pole 09 Mtr. Long. |
| 8 | 11 K.V. out door Jointing Kit for 3x70 Sq.mm. XLPE cable. |
| 9 | 11 K.V. Pin with Nut & Pin Insulator. |
| 10 | Top Channel for D.P. 125X65X3200 mm. with clamps. |
| 11 | Tailless Fuse Unit 500 Amp. |
| 12 | Fabrication, Erection of Sub-Station type Double Pole on 11 mtr. long S.T.P. pole with necessary clamps, accessories required including fixing of Top Channel 125X65X6 mm. (2240 mm long) one No., Dropper Channel 100X50 mm. (2028 mm long) 01 Nos. with arrangment of fixing of 06 Nos. Pin Insulator. Sub-Station base angle of 65X65X6 mm. (2250 mm.) channel 02 Nos. Grouting with cement, sand and brick ballast in ratio 1:4:8making plinth upto width of 300 mm.Painting of poles with primer and enamel paint as per RESPO specification complete in all respect. |
| 13 | Erection of Single Pole structure on 11 mtr. STP with fixing of necessary clamps and other accessories required for stringing along with plinthing & grouting of STP with cement, sand and brick ballast in the ratio 1:4:8 (0.9 Cu.Mtr each)upto the height of 300 mm. from the ground level. |
| 14 | Construction of masonary plinth suitable for 250 K.V.A. Transformer of size 2X2X1.2 Mtrs with complete civil material & 02 Nos.,100X50 mm, M.S Channel 2.0 Mtr. long and M.S Bar 8/10 SWG as per RESPO norms complete in all respect as per RESPO norms. |
| 15 | Disconnection of existing 100 KVA Transformer from system shifted upto safe place to the nearest 33/11 K.V. Sub-Station of Division or required place. |
| 16 | Placement of 250 K.V.A Transformer on plinth making L.T& H.T side conection of both side by fixing of Lugs, L-piece and other material required for completion of work including cariage of Transformer from store to site. |
| 17 | Lay down the LT PVC cable of different sizes for making the both side, connection of Transformer after fixing the necessary clamps Lugs and other material required for completion of work including carriage from store center. |
| 18 | Earthing of 11/0.4 K.V Distribution Transformer body/neutral by way of boring and lowering of ISI marked two Nos. G.I pipe 1.5\" dia 20 m deep from the groung level with solid cone at the lower end of G.I pipe. One end of G.I strip of size 50X6 mm. will be connected with neutral and body of the Transformer & other end will be clamped & welded with G.I Pipe as per UPPCL norms (All the material will be arranged by contractor at their own cost.)Including painting of Earth Strip with red oxide paint and 02 coat of bus grey paint of Burger/Asian make. |
| 19 | Fabrication and erection of wire mesh fencing 02 Mtr. height with a gate and with retaining wall including grouting of fabricated M.S. Angle 65X65X6 mm. support (05 Nos. in a Sub-Station). Painting of fencing/support with all material as per specification/drawing complete in all respect. |
| 20 | Repairing and painting of the damaged wiremesh fencing of L.T. Sub-Stations in the area, along with all the required materials. |
| 21 | Laying of 11 K.V. XLPE cable size 3X70 mm2 in single circuit as per ISS norms including all the required material (eg.18 nos 1st class Brick,2 nos stone slab, 0.3 Cu.Mtr local sand as per requirement per meter) (11 K.V. XLPE Cable will be provided by deptt. only) |
| 22 | AB Conductor Stringing & sagging of 3 phase with necessary clamps, Eye hook, Suspension clamp, A-B type connector etc. on ABC New line as per RESPO specification and direction on E/I. ABC shall be supplied by department. |
| 23 | Note :-1- All the material provided by contractor shall be as per norms of UPPCL/RESPO.2- One carriage including loading/unloading from dump site to pit site is included in scope of work.3- During execution of work all risk will be of the contractor.4- Contractor will provide all T & P, vehicle and man power.5- All the old and used material should be taken on book.6- GST will be paid extra as legally applicable. |