Ministry Of Road Transport And Highways has published Tender For Consultancy Services For The Preparation Of Feasibility Studies And Detailed Project Report For The Work Of Rehabilitation Upgradation And Widening Of Existing Highway To 2 Lane With Paved Shoulder Of Shegaon Sangrampur From Km.55.000 To K. Submission Date for this Tender is 26-12-2023. Highway Construction Tenders in sangrampur Maharashtra. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 20-Dec-2023 | Corrigendum 3(Date) | Date | 26-12-2023 |
Sl. No. | Item Description |
1 | Key Personnel |
2 | Team Leader cum Senior Highway Engineer |
3 | Senior Bridge Engineer |
4 | Highway cum Pavement Engineer |
5 | Material-cum-Geotechnical Engineer- Geologist |
6 | Senior Survey Engineer |
7 | Traffic and Safety Expert |
8 | Environmental Specialist |
9 | Quantity Surveyor/ Documentation Expert |
10 | Land Acquisition Expert |
11 | Utility Expert |
12 | B: Sub Professional Staff (To be assessed by Consultant as per requirement of assignment and one sub-professional be a fresh graduate) |
13 | To be filled by Consultant |
14 | To be filled by Consultant |
15 | To be filled by Consultant |
16 | To be filled by Consultant |
17 | Support Staff |
18 | Office Manager |
19 | Typist |
20 | Office Boy |
21 | Night Watchman |
22 | The vehicles provided by the Consultants shall include the cost for rental, drivers, operation, maintenance, repairs, insurance, etc. A. For Consultant: Mahindra Bolero or Equivalent (Not more than 2 years old) |
23 | Innova or Equivalent (Not more than 2 years old) (Fixed Costs) |
24 | Office Rent (Fixed Costs) The rent cost includes maintenance, Cleaning, repairs, etc. |
25 | VI. Office Supplies, Utilities and Communication ( Fixed Costs ) |
26 | Office Supplies Drafting |
27 | Supplies computer |
28 | Running Costs |
29 | Domestic and International Communication |
30 | Office Furniture and Equipment ( Rental ) |
31 | Office Furniture and Equipment |
32 | VIII.Reports and Document Printing |
33 | Monthly Report (3 per month) |
34 | Inception Report & QAP |
35 | Environment and Social Impact Screening Report |
36 | Draft Feasibility Report |
37 | Final Feasibility Report |
38 | Strip Plan with L.A. Reports |
39 | Draft LA and Clearances I Report |
40 | Final LA and Clearances I Report |
41 | Draft Environmental Assessment report & RAP |
42 | Final Environmental Assessment report & RAP |
43 | Draft Detailed Design Report & Drawings etc. |
44 | Draft EMP |
45 | Draft Bidding Documents |
46 | Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings ,etc |
47 | Final EMP |
48 | Final Bidding Documents |
49 | Draft 3(a) ,3(A) and 3(D) notification for land acquisition ( 3 copies each) |
50 | LA & Clearances II Report |
51 | IX Survey and Investigation |
52 | Topographic Survey including hire charges for equipment and supply of survey Teams comprising of project survey field staff etc. inclusive of cost of materials , labourer. |
53 | Detailed topographic surveys using Air Borne Tomography and Air Borne LiDAR Technology |
54 | B. Investigation (Fixed cost) |
55 | Road and Bridge Inventory |
56 | FWD Test and Pavement Evaluation |
57 | Roughness Survey |
58 | Axle Load Survey |
59 | Material Survey and Investigation |
60 | Sub-grade Investigation |
61 | Traffic Survey |
62 | Socio-economic & Census Survey/ Studies |
63 | Land Acquisition Studies |
64 | Any other investigations/surveys |
65 | C. NET WORK SURVEY AND GPR |
66 | Net work Survey of the existing Highways as a responsitory for civil work as per direction from Authority |
67 | GPR Survey for detection of under ground utilities |
68 | Cost of supply and fixing boundary pillars |
69 | Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967:Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed at an interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval. (lumpsum ) |
70 | Land acquisition Team including support staff and logistics/transportation |
71 | Ex-Land revenue inspector/officer or equivalent |
72 | EX-kanoogo/Girdwar or equivalent |
73 | Ex-Patwari or equivalent |
74 | typist |
75 | peon |
76 | Estimate of Costfor Expatriate Consultants (INR) Remuneration of Exptriate staff including per diem allowances |
77 | Staff 1 |
78 | Staff 2 |
79 | Staff 3 |
80 | Staff 4 |
81 | Staff 5 |
82 | Staff 6 |
83 | International Airfares (Fixed Cost) Mobilization andDemobilization |
84 | Position 1 |
85 | Position 2 |
86 | Position 3 |
87 | Position 4 |
88 | Inland Travel in Home Country (Fixed Costs) |
89 | Airlines |
90 | Other Miscellaneous expenses (like DA, internal travel expenses other incidentals) |
91 | Income Tax (Expariate)( as per prevaling Norms) |
92 | Other Taxes / Duties (if any) Specify clearly |
93 | Goods & Service Tax( as per prevaling Norms) |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail