| 1 | Earth work in hard soil or gravelling soil for excavation of foundation including dressing and levelling of beds and depositing the soil away from the work side with alllead & lift including cost of all labour, T & P, dewatering,shorring and shuttering for the work etc. complete& as per direction of Engineer in charge |
| 2 | Supplying and Fillingin foundation and plinthwith sand , well watered and rammedwith all leads and lifts, cost convenience and royalty and all taxes of materials , cost of labour, T & P, dewatering,required for the works etc, complete in all respect as directed by engineer-in-charge. |
| 3 | Cement concrete of proportion (1:4:8) with using 40 MM size hbg metal free from weathered and skin with including cost, convenience, royalty and taxes of all materials, labour etc including curing, dewatering if required in all respect including centering and shuttering etc.complete& as per direction of Engineer in charge |
| 4 | Fly ash brick(25cmx12cmx8cm) masonery in CM(1:6)for superstructre infoundation and plinthhaving a crushing strenghth of not less than 75 kg/sqcm including splays cutting, circular moulding,chamfering and curbing and watering, curing etc including cost, convenyance, royalty and all taxes of materials with cost. of labour, T& P etc. complete requiredfor the work complete in all respect as directed by the engineering -in-charge.In foundation & plinth. |
| 5 | In superstructre . |
| 6 | Reinforcement cement concrete M-20 grade with 20 mm nomial size down graded nomial size aggregate mechanically mixed and vibrated in foundation and bed protection of speciation for road and Bridge work& Direction of the Engin chargethe work etc complete as direction by the engineering-in-charge. |
| 7 | Suppling, coiled M.S rod or HYSDsteel (Fe-415),cutting, bending,cracking,hooking,olding or jointing (if required) reinforcement including labour charges forcutting, bending, binding and straightening and tying the grills and placing in position including cost ofbinding wire 18 to 20 gauge as per drawing and technical specificaiton as directed by the engineering-in-charge. |
| 8 | Rigid and smooth centering shuttering for Rc.c works A. column foundation and plinth |
| 9 | B,. Column and beam |
| 10 | c,Lintel |
| 11 | d.Chajja and Roof slab |
| 12 | Fixingof vertifiedtiles in floors ,600 mmx600 mmof approved treads and landings on 25 mm thick bed of cementmortar (1:1) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile |
| 13 | Fixing tiles in dados ,skirting and in rises of steps on 12mm thick bed of cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing including cost of tile |
| 14 | supplying fitting and fixing cheqered tilein floor treads of step and landing25 mm thick bed of c.c (1:1)(1 cement ,1 sand ) jointed |
| 15 | Supply ftting granite tile in floor treads of stepand landingof 25 mm thick bed of c.m (1:1) |
| 16 | supply and fitting and fixing ceramic tilesin floor of size 600mm x600 mm of approved |
| 17 | 12 mm thick cement plaster in C.M. (1:6) finishing smoothto outer sidebrickwork after ranking out the joints including watering and curing with cost, conveyance, royalty of all materials , labour with T & P required for the work including all taxes etc. complete in all respect all floors as directed by engineering-in-charge. |
| 18 | 16 mm thick cement plaster in C.M. (1:6) finishing smoothto inner sidebrickwork after ranking out the joints including watering and curing with cost, conveyance, royalty of all materials , labour with T & P required for the work including all taxes etc. complete in all respect all floors as directed by engineering-in-charge. |
| 19 | 20 mm thick cement plaster in C.M. (1:6) finishing smoothto outer sidebrickwork after ranking out the joints including watering and curing with cost, conveyance, royalty of all materials , labour with T & P required for the work including all taxes etc. complete in all respect all floors as directed by engineering-in-charge. |
| 20 | 6mm thickcement plaster in cm (1:4) as ceiling plaster with all cost conveyance royality etc |
| 21 | Supplying fitting & fixing of M.S shutter in cluding cost of all materials etc .complete as per direction of in charge |
| 22 | finishing eall surface with Acrylic wall putty water base approved make and finished smooth |
| 23 | priming one coat with primer |
| 24 | Distempering two coats to walls with distemper of approved shade on new work to give an even shade including cost of disteper |
| 25 | Providing and applying paint over external plastered surfaces with 2 coats of weather coat of approved quality and shade using the required quantity of paint |
| 26 | Wall painting two coat with plastic emulision Paint |
| 27 | finishing wall with water proofing cement paint of approved shade |
| 28 | 20 mm thick c.p in cm (1:4) on roof slab for slab grading |
| 29 | painting two coat with approved paint over one coat of priming |
| 30 | Provison of Disply board (4 ft x3ft) |
| 31 | primer 1 coat with any approved primer |