| 1 | first floor R.C.C.(M-20) using 12mm. Size C.B.chipsincluding hoisting and laying nad compacting etc complete with centering and shuttering excluding cost of steel etc complete as directed by the Engineer-In -Charge. (Column ) |
| 2 | Lintel |
| 3 | Chajja |
| 4 | beam |
| 5 | Roof Slab |
| 6 | Supplying,fitting and placing TMT bar conforming to fe-500/415 reinforcement complete with cost of all. |
| 7 | Providing fly ash brick masonry in cement mortor(1:6) in superstructure using approved quality of brick etc. Super structuer 10\" wall 1st floor |
| 8 | first floor Providing 16 mm thick cement plaster with cement mortar of mix (1:6) |
| 9 | first floor 12mm thick in C.M.(1:6) over brick masonary to the smooth surface including all costs etc. complete. |
| 10 | Providing 6mm thick CP (1:4) to RCC surfaces finished smooth including closed deep chiping and slurry treatment etc complete |
| 11 | Fixing vetrified tile in floor on 20mm thick bed (1:4) c.m. complete including cost of tiles. |
| 12 | Fixing ceramic tile in floor on 12mm thick bed (1:4) c.m. complete including cost of tiles. |
| 13 | first floor Wall priming one coat |
| 14 | first floor Wall painting with 2 coat weather coat paint of approved shade on new work to give an even shade including cost of paint etc complete. |
| 15 | first floor Wall painting with 2 coat Plastic emulsion paint of approved shade on new work to give an even shade including cost of paint etc complete. |
| 16 | Supplying, fitting, fixing up window (sliding type) made up aluminum Section 9778 as windows frame section No.4095,4096& 9777,3994 as shutter frame with 5mm thick black glass as panel fitted with rubber beading including locking arrangement including all fitting including cost of materials all taxes labour, T&P etc.complete as per direction of Engineer-incharge. |
| 17 | Supplying and Fixing of G.I. Grills, M.S.Doors, M.S. Gate etc including cost,conveyance of all materialsand labour for fitting fixing etc.complete as per the instruction of Engineer-in-Charge |
| 18 | first floor enamel paint |
| 19 | Supplying, fitting and fixing of Stainless steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipe with Balustrade of size 32mm x 32mm x 2mm @ 0.90mtr. C/C and stainless square pipe bracing of size 32mm x 32mm x 2mm in 3 rows in stair case as per approved design and specification, buffing, polishing etc with cost, conveyance, taxes of all materials, labour, T&P etc. required for the complete in all respect. |
| 20 | TOILET Earthwork in all kind of soil including all cost etc within initial leads and lifts complete. |
| 21 | TOILET Filling foundation and plinth withsand well watered and rammed including all costs etc complete. |
| 22 | TOILET Providing and laying Cement concrete(1:3:6) in foundation and floors & using 4mm size clean hard broken granite metal of approved quality etc. complete . |
| 23 | TOILET Cement Concrete (1:2:4) using 12 mm size H.G.chips ( crusher broken ) well rammed including cost, conveyance, royalty, taxes of all materials, etc complete as per the direction of the Engineer-in-charge. |
| 24 | TOILET Fly ash brick workin cement mortar (1:6) in F&P using fly ash bricks of approved quality including cost, conveyance & royalty of all metarials etc complete as per direction of the Engineer-in-charge. |
| 25 | TOILET R.C.C.(M-20) using 12mm. Size C.B.chipsincluding hoisting and laying nad compacting etc complete (Column Footing) |
| 26 | Column upto R.L |
| 27 | Plinth Beam |
| 28 | Wall beam |
| 29 | Roof slab |
| 30 | TOILET Supplying,fitting and placing TMT bar conforming to fe-500/415 reinforcement complete with cost of all. For GF |
| 31 | TOILET Providing fly ash brick masonry in cement mortor(1:6) in superstructure using approved quality of brick etc. |
| 32 | TOILET 12mm thick in C.M.(1:6) over brick masonary to the smooth surface including all costs etc. complete. |
| 33 | TOILET 16 mm thick plasterwith cement mortar (1:6) overstone/brick masonary including allcost, conveyance & royalty etc complete as per direction of the Engineer-in-charge. |
| 34 | TOILET Providing 6mm thick CP (1:4) to RCC surfaces finished smooth including closed deep chiping and slurry treatment etc complete |
| 35 | TOILET Fixing vetrified tile in floor on 20mm thick bed (1:4) c.m. complete including cost of tiles. |
| 36 | TOILET Fixing ceramic tile in floor on 12mm thick bed (1:4) c.m. complete including cost of tiles. |
| 37 | TOILET Wall priming one coat |
| 38 | TOILET Wall painting with 2 coat weather coat paint of approved shade on new work to give an even shade including cost of paint etc complete. |
| 39 | TOILET Wall painting with 2 coat Plastic emulsion paint of approved shade on new work to give an even shade including cost of paint etc complete. |
| 40 | TOILET Supplying and Fixing of G.I. Grills, M.S.Doors, M.S. Gate etc including cost,conveyance of all materialsand labour for fitting fixing etc.complete as per the instruction of Engineer-in-Charge |
| 41 | TOILET Enamel paint |