Tender For Construction And Dismantling Of 03 Nos Temporary Jetty(10X5)M At Andawa Pond Jushi For Durga Murti Visarjan 2023, Varanasi-Uttar Pradesh

Irrigation Department has published Tender For Construction And Dismantling Of 03 Nos Temporary Jetty(10X5)M At Andawa Pond Jushi For Durga Murti Visarjan 2023. Submission Date for this Tender is 09-10-2023. Earth Work Tenders in Varanasi Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

39941225
Tender For Construction And Dismantling Of 03 Nos Temporary Jetty(10X5)M At Andawa Pond Jushi For Durga Murti Visarjan 2023
Open Tender
Indian
Uttar Pradesh
Varanasi
09-10-2023

Tender Details

Tender For Construction And Dismantling Of 03 Nos Temporary Jetty ( 10X5 ) M At Andawa Pond Jushi For Durga Murti Visarjan 2023; 1 Earth Work In Scraping Of Side Slope Of Pond Inall Type Of Soil Including All Lead & Lift Etc Complete 2 Supplying , Stacking & Spreading Of Local Ganga Sand On Approches And Platformsas Per Site Requirment And As Per Direction Of Engineer-In-Charge. 3 Earth Work In Slope Cutting And For Making Stairs For Approach To Jetty With Its Disposal As Per Direction Of Engineer-In-Charge In All Types Of Soil Including All Leads And Lifts, Labour And T&P Etc. 4 Providing Beldar For Removing And Proper Disposal Of Sevarincluding Cost Of All Material, Labour, T&P Etc. Required For Proper Completion Of Works All Complete As Per Direction Of Engineer-In-Charge 5 Making Ballikhuntas On 125Mm ( 5 ) Dia Ballies For Piling With All Labour And T&P Etc. Required For Proper Completion Of Work As Per Direction Of Engineer-In-Charge But Excluding Cost Of Ballies. 6 Balli Piling With 125Mm ( 5 ) Dia Ballies In Grid As Per Drawing Including Cost Of All Material, Labour, T&P Etc. Required For Proper Completion Of Works All Complete As Per Direction Of Engineer-In-Charge But Excluding Cost Of Ballies. 7 Bracing On Driven Piles With 100Mm ( 4 ) Dia, Ballies Along And Across In Rectangular Grid With 6 Long Mallahi Nails Of Good Quality And Fixing Wooden Planks Of Size 2.00 M. ´ 0.25 M. Size, 5 Cm. Thick Over Bracing To Make Platform For Jetty Using 4 Long Good Quality Mallahi Nails Including Cost Of All Material, Labour And T&P Etc. Required For Proper Completion Of Work All Complete As Per Direction Of Engineer-In-Charge But Excluding Cost Of Ballies And Planks. 8 Barricading With 100Mm-120Mm Dia Balli In Two Rows Including Cost Of All Materials And Tying Arrangement With All Labour T&P. Etc. Required For Proper Completion Of Work As Per Direction Of Engg-In- Charge But Excluding Cost Of Ballies. 9 Supplying And Filling Plastic E.C. Bags With Local Ganga Sand And Stacking, Placing In Position For Making Stair , Laying Over Ldep Film Etc And At Other Places With All Leads Lifts Including Cost Of Materials, Labour And T&P Etc. As Per Direction Of Engineer-In-Charge. 10 Painting Two Coat Of Approved Superior Quality Ready Mixed Synthetic Enamel Paint On Old Painted Surface On125 Mm ( 5’’ ) Dia Balli , Khunta Vertical In Barricading Including Cost Of All Materials And Tying Arrangement With All Labour T&P. Etc. Required For Proper Completion Of Worksper R.M. 11 Painting Two Coat Of Approved Superior Quality Ready Mixed Synthetic Enamel Paint On Old Painted Surface On100 Mm ( 4 ) Dia Balli , Khunta Vertical In Barricading Including Cost Of All Materials And Tying Arrangement With All Labour T&P. Etc. Required For Propercompletion Of Worksper R.M. 12 Providing Beldar For Watching Of Jetty And Supervision Of Constructed J.T. During Durga Murti Viserjan. 13 Providing Carpentor For Watchingand Supervision Of J.T. During The Durga Murti Visarjan. 14 Providing Boatman With Boat For Watchingballi Piling Etc. And Removal Of Residue From Pond During Durga Murti Visarjan. 15 Carriage Of Stock Material From Beni Bundh Store To Working Place And Back To Store After Dismantling. 16 Making Arrangement For Removal Of Residue From The Pond After Durga Murti Visarjan. 17 Debaricading Of Ballies 100Mm- 120Mm In Two Rows And Stacking Including All Labour T&P Etc. As Per Direciton Of Engineer-In-Charge. 18 Deplainking And Debracing In Dismantling Of Jetty And Stacking For Proper Completion Of Work As Per Direction Of Engineer-In-Charge. 19 Depiling Of Ballies In Dismantling Of Jetty And Stacking For Proper Completion Of Work As Per Direction Of Engineer-In-Charge.

Key Value

Document Fees
INR 2354 /-
EMD
INR 25900.0 /-
Tender Value
INR 12.95 Lakhs /-

BOQ Items

Name of Work :Construction and Dismantlingof 03 Nos Temporary Jetty(10x5)Mat Andawa pond Jushifor Durga Murti Visarjan 2023
Sl. No. Item Description
1Earth work in scraping of side slope of pond inall type of soil including all lead & lift etc complete
2Supplying ,stacking & spreading of local Ganga sand on approches and platformsas per site requirment and as per direction of engineer-in-charge.
3Earth work in slope cutting and for making stairs for approach to jetty with its disposal as per direction of Engineer-in-charge in all types of soil including all leads and lifts, labour and T&P etc.
4Providing beldar for removing and proper disposal of sevarincluding cost of all material, labour, T&P etc. required for proper completion of works all complete as per direction of Engineer-in-charge
5Making BalliKhuntas on 125mm (5") dia ballies for piling with all labour and T&P etc. required for proper completion of work as per direction of Engineer-in-charge but excluding cost of ballies.
6Balli piling with 125mm (5") dia ballies in grid as per drawing including cost of all material, labour, T&P etc. required for proper completion of works all complete as per direction of Engineer-in-charge but excluding cost of ballies.
7Bracing on driven piles with 100mm(4") dia, ballies along and across in rectangular grid with 6" long Mallahi nails of good quality and fixing wooden planks of size 2.00 M. ´ 0.25 M. size, 5 cm. thick over bracing to make platform for Jetty using 4" long good quality Mallahi nails including cost of all material, labour and T&P etc. required for proper completion of work all complete as per direction of Engineer-in-charge but excluding cost of ballies and planks.
8Barricading with 100mm-120mm dia balli in two rows including cost of all materials and tying arrangement with all labour T&P. etc. required for proper completion of work as per direction of Engg-in- charge but excluding cost of ballies.
9Supplying and filling plastic E.C. bags with local Ganga sand and stacking, placing in position for making stair ,laying over LDEP film etc and at other places with all leads lifts including cost of materials, labour and T&P etc. as per direction of Engineer-in-charge.
10Painting two coat of approved superior quality ready mixed synthetic enamel paint on old painted surface on125 mm (5’’) dia balli ,khunta vertical in barricading including cost of all materials and tying arrangement with all labour T&P. etc. required for proper completion of worksper R.M.
11Painting two coat of approved superior quality ready mixed synthetic enamel paint on old painted surface on100 mm (4") dia balli ,khunta vertical in barricading including cost of all materials and tying arrangement with all labour T&P. etc. required for propercompletion of worksper R.M.
12Providing Beldar for watching of jetty and supervision of constructed J.T. during Durga Murti Viserjan.
13Providing Carpentor for watchingand Supervision of J.T. during the Durga Murti Visarjan.
14Providing boatman with boat for watchingballi piling etc. and removal of residue from pond during Durga Murti Visarjan.
15Carriage of Stock material from Beni Bundh store to working place and back to store after dismantling.
16Making arrangement for removal of residue from the pond after Durga murti visarjan.
17Debaricading of ballies 100mm- 120mm in two rows and stacking including all labour T&P etc. as per direciton of Engineer-in-charge.
18Deplainking and Debracing in dismantling of jetty and stacking for proper completion of work as per direction of Engineer-in-charge.
19Depiling of ballies in dismantling of jetty and stacking for proper completion of work as per direction of Engineer-in-charge.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail