| 1 | Dismantling and removing Old tiled flooring including removing the base coarse and stacking the useful materials for reuse and removing the debris within 50m lead etc. complete as per direction of Engineer in charge. |
| 2 | Dismantling and removing cement concrete including stacking the useful materials for reuse and removing the debris within 50m lead etc. complete as per direction of Engineer in charge. |
| 3 | Dismantling brick or stone masonary in lime or cement mortar under 3m. Height including stacking the useful materials for reuse and removing the debris within 50m. lead etc. complete as per direction of Engineer in charge. |
| 4 | Dismantling and removing R.C.C Chajja, Shelves, fins and parapet including stacking the useful materials for reuse and removing the debris within 50m lead etc. complete as per direction of Engineer in charge. |
| 5 | Earth work inexcavation IN ALL KINDS OF SOILS by manual means overareas (exceeding 30 cm in depth, 1.5 m in width as well as 10sqm on plan)including disposalof excavated earth up to50 m and lift upto 1.5m with all lead and lift including shoring, shuttering & dewatering (if required) with cost of all Labour, Labour cess ,Hire & Running charges of thewater pumps, Sundries, T & P required for the work complete as directed by the Engineer- in- charge. |
| 6 | Supplying and filling in foundation trenches and plinth, ditches with sand well watered and rammed in layers not exceeding 23 cm. In depth with all lead and lift including cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labour, sundries, T&P required for the work etc. complete in all respect as directed by the Engineer-in-Charge. Measurement will be taken on finished compacted section only). |
| 7 | Providing and laying Plain cement concrete of proportion(1:3:6) in foundation and floors(i.e. below the base course of the flooring) using cement, 40mm. Size crusher broken H.G.Metal and screened and washed sharp river sand for mortar of approved quality and from approved quarry including hoisting, lowering and laying concrete to the required level, ramming,watering and curing etc. complete to required levels, laid in layers not exceeding 15cm thick in each layer including cost, conveyance, loading, unloading,royalities and taxes of all materials, cost of all labour,T&P required for the work including shoring,shuttering and dewatering(if required) including hire and running chargesof water pump required for the work etc. complete in all respect as directed by the Engineer-in-charge. |
| 8 | Reinforced Cement concrete RCC(1:2:4) with 12mm size (C.B.) broken hard granite chipsincluding hoisting and laying including hoisting, lowering, laying concrete, ramming, watering and curing etc. complete to required levels laid in layers not exceeding 15 cm. thick in each layer including cost, conveyance, royalties, taxes of all materials and cost of all labours, T&P etc complete as per the direction of the Engineer -in –charge. |
| 9 | Ground Floor |
| 10 | 1st Floor |
| 11 | Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materialscomplete in ground floor.(RCC foor and roof slabs, landings, balconies, projecting sun shades and chajjas upto 4.30m height) |
| 12 | Ground Floor |
| 13 | 1st Floor |
| 14 | Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materialscomplete in ground floor. (RCC foundation, plinth band and footings, bases of columns mass concrete pre-cast slabs etc.) |
| 15 | Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materialscomplete in ground floor. (RCC beams, columns, girder and bressmer, etc.) |
| 16 | Ground Floor |
| 17 | 1st Floor |
| 18 | Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materialscomplete in ground floor. (RCC Lintels, etc.) |
| 19 | Cutting,straightening coiled or bent up HYSD/TMT Reinfocement Bars welding or jointing if necessary ,bending, binding,tying the grills as required for R.C.C. works,providing Fan Hooks where necessary and hoisting,lowering and placing the same in proper position according to the approved designs and drawings in all floors including cost, conveyance, loading, unloading and taxes or HYSD/TMT Reinforcement Bars and Binding wieres of 18 to 20 gauge required for the work cost of all labour,T&P and scaffolding complete in all respect as directed by the Engineer-in-charge(Payment will be made according to the actual/proper weight of HYSD/TMT Reinforcement Bars and Binding wires consumed in the particular work only) fe 550 |
| 20 | Ground Floor |
| 21 | 1st Floor |
| 22 | Fly ash brick masonry using Fly ash bricks of size 25cm x 12 cm x 8 cm having crushing strength not less than 75 kg. Per Sqr. Cm. In cement mortar of mix(1:6) with cement and screened and washed sharp sand for mortar after immersing the bricks for 6 (six) hours in water before use in foundation, plinth, basement and for ornamental flower beds, plinth moulding and similar such type of works with all necessary projections, splays cutting, circular moulding, corbelling, chamfering, watering and curing etc. including cost, conveyance, loading unloading, royalties and taxes of all materials and cost of all labour, sundries, T & P required for the works etc. complete in all respect as directed by the Engineer-in-Charge. |
| 23 | Fly ash brick masonry using fly ash bricks of size 25 cm. x 12 cm. x 8 cm. having crushing strength not less than 75 kg. Per Sqr. Cm. in cement mortar of mix (1:6) with cement after immersing the bricks for 6 (Six) hours in water before use in superstructure including splays cutting, circular moulding, corbelling, chamfering and similar such type of works, watering and curing etc. including cost, coveyance, loading and unloading, royalties and taxes of all materials and cost of all labour, scaffolding, sundries, T&P required for the works etc. complete in all respect as directed by the Engineer-in-charge. |
| 24 | Ground Floor |
| 25 | 1st Floor |
| 26 | Providing 16mm. Thick cement plaster in cement mortar or mix(1:6) in all floors at all height with cement & screened and washed sharp river sand for mortar and finished smooth to the rough surface of the brick masonary walls after racking out the joints (alongwith providing grooves wherever necessary) including watering and curing,rounding of corners etc. complete with cost, conveyance, loading, unloading, royalities and taxes of all materials,cost of all labour,T&P, and scaffolding required for the work etc. as directed by the Engineer-in-charge. |
| 27 | Ground Floor |
| 28 | 1st Floor |
| 29 | Providing 12mm. Thick cement plaster in cement mortar or mix(1:6) in all floors at all height with cement & screened and washed sharp river sand for mortar and finished smooth to the rough surface of the brick masonary walls after racking out the joints (alongwith providing grooves wherever necessary) including watering and curing,rounding of corners etc. complete with cost, conveyance, loading, unloading, royalities and taxes of all materials,cost of all labour,T&P, and scaffolding required for the work etc. as directed by the Engineer-in-charge. |
| 30 | Ground Floor |
| 31 | 1st Floor |
| 32 | Providing6 mm thick cement plaster in cement mortar of mix (1:4)at all height using screened& washed sharpriver sandformortar with approved quality of cement tothe ceilingofthe Roof Slab, Staircase,Beams, Columns,Landings, Railings,Chajja ,Fins ,Walls ,Jallyand Shelves etc. including roughening, scraping, chiseling, cleaning, closed deep chipping with slurry treatment and finished smooth to allR.C.C. Surface including cost, conveyance, loading, unloading, royalties ,stacking and alltaxes , cost of all Labour,Labour cess ,Sundries, T&P, Scaffolding, Watering,Curing etc. complete in all respect as directed by the Engineer- in- charge. |
| 33 | Ground Floor |
| 34 | 1st Floor |
| 35 | Providing, Fitting&Fixing of Chequered tiles of thickness 8 mm. to 12mm conforming to IS specifications of 600mmX600mminfloors,treads,and landings at all heights on 25mm thick bed of cement mortar(1:1) to proper slope, line and level including cutting to required size and shape, fixing at corners and splays etc. including filling the joints with silicon sealant to match the shade ofChequered Tile as per the design & drawing including cost, conveyance, loading, unloading, stacking,royalties and taxes of all materials, cost of all labour, T & P, sundries, watering & curing etc. required for the work complete in all respect as directed by the Engineer-in-Charge. |
| 36 | Providing, Fitting&Fixingof 8 mm. to 12mm.thick Vitrified industrial Tiles conforming to IS specifications of 600mmX600mminfloors,treads,and landings at all heights on 25mm thick bed of cement mortar(1:1) to proper slope, line and level including cutting to required size and shape, fixing at corners and splays etc. including filling the joints with silicon sealant to match the shade ofVitrified Tile as per the design & drawing including cost, conveyance, loading, unloading, stacking,royalties and taxes of all materials, cost of all labour, T & P, sundries, watering & curing etc. required for the work complete in all respect as directed by the Engineer-in-Charge. |
| 37 | Ground Floor |
| 38 | 1st Floor |
| 39 | Providing vitrified Industrial tilesof premium grade having thickness of 8 to 10mm conforming to IS specifications of 600mmX600mm colour/printed series (homogeneous) of approved quality,colouror equivalent in dados & skirting on 12mm thick bed of cement mortar of mix (1:3) laid in proper slope and gradient with screened and washed sharp sand for mortar and grouted with required quantities of pigments of approved marks to match the shades of the vitrified tile if required watering and curing for 21 days including cost,conveyance,loading,unloading,royalties and taxes of all materials,cost of all labour,sundries,T & P required for the work complete in all respect as directed by the Engineer-in-charge. |
| 40 | Ground Floor |
| 41 | 1st Floor |
| 42 | Providing, Fitting&Fixingof 8 mm. to 12mm.thick Vitrified Tiles of printed series conforming to IS specifications of 600mmX600mminfloors,treads,and landings at all heights on 25mm thick bed of cement mortar(1:1) to proper slope, line and level including cutting to required size and shape, fixing at corners and splays etc. including filling the joints with silicon sealant to match the shade ofVitrified Tile as per the design & drawing including cost, conveyance, loading, unloading, stacking,royalties and taxes of all materials, cost of all labour, T & P, sundries, watering & curing etc. required for the work complete in all respect as directed by the Engineer-in-Charge. |
| 43 | Providing vitrified tilesof printed series having thickness of 8 to 10mm conforming to IS specifications of 600mmX600mm colour/printed series (homogeneous) of approved quality,colouror equivalent in dados & skirting on 12mm thick bed of cement mortar of mix (1:3) laid in proper slope and gradient with screened and washed sharp sand for mortar and grouted with required quantities of pigments of approved marks to match the shades of the vitrified tile if required watering and curing for 21 days including cost,conveyance,loading,unloading,royalties and taxes of all materials,cost of all labour,sundries,T & P required for the work complete in all respect as directed by the Engineer-in-charge. |
| 44 | Providing fitting, fixing of Al. Door with anodized Al. door section of 9202 as vertical member, 9201 as top, 9200 as bottom ad middle member with frame section as as 9221 with tappered clip No.4660 and the frame to be completed by means of jointing angle No. 1855 including all cost of labour, T&P, hire charges of drilling machine, labour charges etc. complete excluding cost of laminated board for the work complete in all respect as directed by the Engineer-in-charge. |
| 45 | Supplying, fitting, fixing up windows (sliding type) made up aluminium Section 9778 as windows frame section No. 4095, 4096 and 9777, 3994 as shutter frame with 5mm thick black glass as panel fitted with rubber beading including locking arrangement including all fitting including cost of materials, all taxes labour, T&P excluding cost of glass etc. complete as per direction of Engineer-in-Charge. |
| 46 | Providing and fixing fixed Glazed Powder coated Aluminium Louvers ventilators etc. complete as per direction of Engineer-in-Charge. |
| 47 | Providing, Fitting & Fixing ofPVC Door with Fiber Choukatwith cost, conveyance, royalties and taxes of all materials with cost of all labour, and T&P required for the work etc. complete in all respect as directed by the Engineer in charge. |
| 48 | Supplying, fitting and fixing of stainless steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipe with Balustrade of size 32mm x 32mm x 2mm @0.90 mtr. C/C and stainless square pipe bracing of size 32mm x 32mm x 2mm in rows in stair case as per approved design and specification, buffing, polishing etc with cost, conveyance, taxes of all materials, labour, T& P etc. required for the work complete in all respect as directed by Engineer-in-Charge. |
| 49 | Supplying and Fixing of M.S. Window Grill made out of M.S Flatconforming to IS 2062/2006 painted with Red Oxide Primer as per the design approve by E.I.C including cost,conveyance of all materials, priming,and labour for fitting fixing etc.complete as per the instruction of Engineer-in-Charge |
| 50 | Priming one coat with any approved primer including cost of primer over iron work etc. including cost, conveyance,taxesof all materials , cost of all Labour , Labour cess,scaffoldings, staging, sundries,T&P etc. required for the work complete as directed by the Engineer-in-charge. |
| 51 | Ground Floor |
| 52 | 1st Floor |
| 53 | Painting two coat with approved synthetic enamel paint to new wood & iron workincluding cost, conveyances, royalties of all materials and cost of all labour with T&P required for the work etc. complete as per specification & direction of Engineer in charge. |
| 54 | Ground Floor |
| 55 | 1st Floor |
| 56 | Finishing wall surface of walls with cement basedwall putty ( water based) of approved make and finished smooth and even surface to receive painting including cost, conveyance,taxesof all materials , cost of all Labour , Labour cess,scaffoldings, staging, sundries,T&P etc. required for the work complete as directed by the Engineer-in-charge. |
| 57 | Wall Priming one coat with water bound wall cement primer etc. complete including cost, conveyance,taxesof all materials , cost of all Labour , Labour cess,scaffoldings, staging, sundries,T&P etc. required for the work complete as directed by the Engineer-in-charge. |
| 58 | Wall painting two coats with Acrylic paint(plastic emulsion) of approved quality of premium brandof approved quality & colourat all heights to the interior surface of the wall to make an even finishedsurface includingsand papering, applying putty wherever necessary including cost, conveyance, loading, unloading, stacking,all taxes , cost of all Labour , Labour cess,scaffoldings, staging, sundries,T&P etc. required for the work complete as directed by the Engineer-in-charge. |
| 59 | Ground Floor |
| 60 | 1st Floor |
| 61 | Wall painting two coats with Weather coat paint (1st quality) exterior grade of approved make & with a approved quality primer to make an even finished surface in all floors and heights with all scaffolding and staging charges including cost, conveyance,cost of all labours, T & P, sundries etc. as required for the work complete in all respect as per the direction of the Engineer-in-Charge. |
| 62 | Ground Floor |
| 63 | 1st Floor |