Bharat Sanchar Nigam Limited-BSNL has published Tender For Procurement Of 7 M & 8 M Tubular Poles With Accessories, Installation Accessories & Fixtures For Adss Of Cable, Slinging Of Adss Cable And Associated Works Along With Testing And Commissioning Of Adss Cable Route On Turnkey Basis In Bsnl Arunac. Submission Date for this Tender is 21-07-2023. Clamps Tenders in Papum Pare Arunachal Pradesh. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Poles and Stay Arrangement |
2 | Galvanised steel pole of tubular in design and swaged of the length 7 meters with top cap welded and lightning spike @28 per Km with MUFF @14 per Km |
3 | Stay arrangement for 7M/8M steel poles |
4 | Installation Accessories & Fixtures for ADSS OF Cable: |
5 | Formed OFC Dead End & Termination fittings: conveyance of all materials and in |
6 | OFC Suspension fittings |
7 | DemountablePulley–1Set |
8 | Adjustable Cable Storage Bracket |
9 | FDMS Type-III |
10 | Joint Closure Kits(24F ADSS) |
11 | Down Lead Clamp |
12 | Pig Tail 20M FCPC |
13 | OFC Termination Box 24F |
14 | Spare OF cable Box |
15 | Services inclusive of all of the following: |
16 | Erection of 7 m / 8m poles including excavation, Construction of RCC foundation for mounting/erecting the poles/fixing of MUFF concreting, curing, Backfilling, Reinstatement, Compaction of earth, Stay arrangements etc. including obtaining Right-of-Way (RoW) permission and sign writing on poles with paint |
17 | Slinging / Laying and splicing of ADSS / AOF including fixing of installation accessories and fixtures etc. Splicing & Jointing of Optical Fibre Cable, Link Testing & Acceptance Testing and makeover of route with As Built Diagram (ABD) of installed Cable routes. This also includes cost towards collection of ADSS Cable / AOF Cable and accessories from BSNL’s Store Depot. |
18 | Installation of spare OF cable box, FDF and WSC, leading-in arrangement, jointing of Pig Tails and all other related activates for construction of ADSS /Aerial OFC route. |
19 | Optional Requirements |
20 | Construction of Joint Chambers of bricks, supply & Fixing of GI Pipe and PLB pipe for bringing down the OF Cable, supply of stone slab for covering the Chamber and sand for filling the chamber. |
21 | Coil earthing of poles |
22 | Laying of PLB pipes at appropriate depth, laying and splicing of underground OF cable |
23 | Laying of underground OF cable inside PLB Pipe / DWC Pipe, Concreting work on PLB Pipe / DWC Pipesincluding supply of cement, concrete and curing etc., laying and splicing underground OF cable along bridges, culverts etc. |
24 | Laying of OF Cable in PLB Pipe with protection of GI pipe/DWC pipe suspended by means of clamps outside the parapet wall of bridge including supply & fixing of clamps and associated work. |
25 | Supply of DWC pipe (63/51 mm) |