| 1 | Earthwork in all kinds of soil excavation by manual means in trenches for foundations, drains, pipes, cable etc. (not exceeding 1.5 in width) and for shafts, wells, cesspits and the like not exceeding 10 Sqm on plan, depth upto 1.5 Mtr including disposal of excavated earth upto 1 Mtr from cutting edge, disposed earth is to be levelled and neatly dressed 60% aks 20% or1o% hr |
| 2 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with: 1:5:10(1 cement : 5 coarse sand : 10 graded stone aggregate 20 mm nominal size) |
| 3 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 4 | P/l m-20 cc mix for R.C.C Wall |
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°,landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiralstair cases upto five level including curing but excluding the cost of centring, shuttering,finishing and reinforcement with 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete above plinth level |
| 7 | Centering and Shuttering walls |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form forSuspended floors, roofs, landings, balconies and access platforms. |
| 9 | Edges of slabs and breaks in floors and walls Under 20 cm wide |
| 10 | 50mm thk flooring m-20 cc mix |
| 11 | Fabrication /supply and fixing of 1 no doors complete job |
| 12 | white wash with lime on new works two or more coat to give an even shade |
| 13 | Providingand fixing of G.I pipe 20mm dia |
| 14 | constt of soak pit of size 1.20m X1.20m X 1.20m filled with bricks bat |
| 15 | Back filling of available excavated earth excluding rock out side the bunker wall and on roof in layer not exceeding 20 cm depth and consolidating by ramming and watering |
| 16 | Supply and laying of pvc sheet under earth cushion roof |
| 17 | supply and fixing of cgi roof sheet |
| 18 | supply of empty cement bags |
| 19 | Supply and Electricfication complete job |
| 20 | Carriage of material by Mechanical Transport including loading / unloading and stacking at site complete. |
| 21 | Carriage of Sand at an avg distance of 170 km by MT and 2.0 km HL |
| 22 | Carriage of Bajree 60 km by MT and 2.0km by HL |
| 23 | Carriage of Steel 20 km by MT 2.0 km by HL |
| 24 | Carriage of Cement 20.0km by MT 2.0Km by HL |