| 1 | Jungle Clearance in borrow area, building premises, flanks and slopes on the roads, canals and embankment by removing the grass and jungle bushes from the top including weeding out shrubs including roots and levelling etc. complete as per direction of E/I SOR WRD 5.1.3.1 |
| 2 | Earthwork in stripping by hydraulic M/C in grade A & B soil including moorum soil,soil mixed with kankar, pebbles and boulders upto 300 mm size and disposal of the same along with all organic materials in the country side beyond 1.0km upto 2.0km in all by tipper etc. do… as per specification and direction of E/I (WRD SOR-5.1.7) |
| 3 | E/W in dam fill in semi previous or imperviours zone excavation by Hudraulic Excavator and carriage by Tipper Truck making dam in proper design section including earth to be laid in layers of not more than 225 mm thick and breaking of clods to maximum 36 m cube with all lifts including construction and maintenance of haul road etc. all complete as per specification and direction of E/I. (WRD SOR. 5.1.22.2) LEAD BEYOND 1.5km but upto 1.0km |
| 4 | Labour for rolling and compacting the earth in layers of 225mm thick at OMC by sheep foot roller driven by tractor to achieve minimum 95% of maximum dry density including sprinkling the required quantity of water and carriege of water in all leads and lifts finishing the surface with proper camber grade super elevation including the hire charge of compaction as per specification and direction of E/I (Mode of measurment sectional measurmenet of compacted earth) WRD SOR - 5.1.33 |
| 5 | Earth work in excavation of foundation trenches in ordinary soil (vide classification of soil item-A) and disposal of excavated earth so obtained (50m away from edge of trenches) with initial lead of 150m andaverage lift of 1.5Mas per specification and direction of E/I.(vide WRD SOR item No. 6.1.8) |
| 6 | Extra for earthwork in marshy soil, Slush and Daldal (vide classification of soil item-F)all complete as per specification and direction of E/I WRD SOR 6.1.10 |
| 7 | Providing coarse clean sand in filling in foundation trencehes or in plinth including ramming and watering in layer not exceeding 150mm thick with all leads and lift including cost of all material ,labour ,royality and taxes all complete as per building specification and direction of E/I (Mode of measurment compacted volume) BCD SOR 5.1.10 |
| 8 | Providing brick flat soling with designation 75 A onebricks flat soling joints filled with local sand including cost of watering taxes royality all complete as per building specification and direction of E/I(BCD SR item No 5.6.1) |
| 9 | Plain/Reinforced Cement concrete in open foundation complete as per drawing and technical specification PCC M15 using Batching Plant & Manual placing RCD SOR 12.08 CASE II |
| 10 | Providing Random Rubbel masonary in cement mortar (1:3) in foundation complete as per drawing and technical specificationRCD SOR-12.07 B |
| 11 | NP2 RCC Hume Pipe with collar as per ISS 458 - 1971300mm dia WRD SOR-M300 (V) |
| 12 | Labour for laying, fitting and fixing NP2 hume pipe with collors in line, level and grade, as well providing approved jointing materials and joints properly filled to make them water proof, all complete job as per specification and direction of E/I 300 mm dia Pipe (SOR-7.6.1.3) |
| 13 | Earth work in filling of masonary structure with semi pervious or suitable earth in layer not exceeded 150mm thick well watered, rammed and fully compacted and finally dressed with earth obtained after cutting from borrow pits with initial lead of 30m and initial lift if 1.5m as per specification and direction of E/I WRD SOR 6.1.17 |
| 14 | Carriage of materials: (A) Cement |
| 15 | (B) Sand |
| 16 | (C ) CHIPS |
| 17 | (D) Bricks |
| 18 | ( E ) Boulder |
| 19 | Goods and Services Tax @12% |
| 20 | Labour cess@1% |