Tender For Carrying Out Different Works Under Business Plan Scheme In The Area Of Ee, Eudd Iii, Mathura Under The Jurisdiction Of The Superintending Engineer, Electricity Urban Distribution Circle, Mathura, mathura-Uttar Pradesh

Dakshinanchal Vidyut Vitran Nigam Limited-DVVNL has published Tender For Carrying Out Different Works Under Business Plan Scheme In The Area Of Ee, Eudd Iii, Mathura Under The Jurisdiction Of The Superintending Engineer, Electricity Urban Distribution Circle, Mathura. Submission Date for this Tender is 03-04-2023. Bolts Tenders in mathura Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

36967087
Corrigendum : Tender For Carrying Out Different Works Under Business Plan Scheme In The Area Of Ee, Eudd Iii, Mathura Under The Jurisdiction Of The Superintending Engineer, Electricity Urban Distribution Circle, Mathura
Open Tender
Indian
Uttar Pradesh
mathura
03-04-2023

Tender Details

Carrying Out Different Works Under Business Plan Scheme In The Area Of Ee, Eudd Iii, Mathura Under The Jurisdiction Of The Superintending Engineer, Electricity Urban Distribution Circle, Mathura-2 St Pole / Pcc Pole ( 11 / 9 / 8.5 Mtr. Long ) 3 250 Kva T / F. 4 11Kv Xlpe Cable Of Size 3X300 / 240 / 185 / 120 / 70 Sq.Mm. 5 33 Kv Xlpe Cable Of Size 3X300sq.Mm. 6 Lt Xlpe / Pvc Cable 1Cx630 / 400 / 240 Sq.Mm. 7 Acsr Dog / Weasel / Ins. Weasel Conductor 8 Other Line Material Such As Cross Arm, Ms Top Channel, Bottom Channel, Tee-Channel, Clamps, Suspension Clamp, Dead End Clamp, Cross Arm Holding Clamp, Danger Board, Pin Insulator, Disc Insulator Nut & Bolts Etc. 9 Opening Of Jumper, Connection & Earthing Of Body And Neutral Of 5 Mva Transformer And Dismantling Of Neutral Earthing Frame, Cable Frame. 10 Safe Shifting Of 5 Mva T / F. From Plinth To Yard Corner. 11 Re-Fixing Of 33 Kv Cable, Jumper & Earthing ( Neutral & Body Earthing Connected By Electric Welding ) ., Erection Of Neutral Earthing Frame, Cable Frame 12 Earthing Of Power T / F 13 Water Level Earthing 14 Pipe In Pipe Gel Earthing 15 Digging Of Pit & Erection Of New Double Stp 09 Mtr. Long For Chair Mounted Plinth Structure Including Grouting Of Pole And Fixing Of All Clamps, Cross Arm, Pin / Disc Insulator & Other Accessories With Providing Stone Pad As Per Relevant Drawings. Any Fabrication If Required For Above Support. 16 Digging Of Pit & Erection Of New Double St / Pcc Pole ( 11 / 9 / 8.5 Mtr. Long ) Including Grouting Of Pole And Fixing Of All Clamps, Cross Arm, Pin / Disc Insulator & Other Accessories With Providing Stone Pad As Per Relevant Drawings. Any Fabrication If Required For Above Support. 17 Digging Of Pit & Erection Of New Single Pole 11 Mtr. Long For Tri Pole Including Grouting Of Pole And Fixing Of All Clamps, Channel, Bracing, Pin / Disc Insulator & Other Accessories With Providing Stone Pad As Per Relevant Drawings. Any Fabrication If Required For Above Support. 18 Earthing Of St / Pcc Pole / Body Earthing Of T / F. By M.S Earth Rod. 19 Painting Of St Pole. 20 Digging Of Pit & Erection Of Stay Rod With Grouting Cement Sand And Brick Ballast Including Nuzzling, Binding Complete. 21 By Excavation Land Upto 6 Mtr. And Removing 33 Kv Xlpe Cable Upto 50 Mtr. 22 Laying Of 33 / 11Kv / Lt Line On Dog / Weasel Conductor On Erected Poles. 23 Laying Of Lt Pvc / Xlpe Cable 1Cx630 / 400 / 240 Sq.Mm. 24 Digging Of Trench By Excavation Of Earth 0.90 / 1.5 Mtr. Deep Put Brick On Both Side, Filling Of Sand & Brick On Cable & Earth Ramming And Dressing Properly With Complete Job For Laying 33 / 11 Kv Xlpe Cable In Trench 25 Laying Of 33 / 11 Kv Xlpe Cable In Trench / Double Pole Structure & Air And Filling Of Cable Jointing Kit With Proper Dressing. 26 Installation Of Lt Protection System For Distribution T / F With All Fittings 27 Providing & Fixing Of Aluminium Lug 70 / 150 / 240 / 400 / 630 28 Straight Through For 33 Kv Cable Underground 29 Jointing Of Cable With Another Cable / Overhead Line At The D / P Structure Through 33 / 11 Kv Outdoor & Indoor Cable Jointing Kit 30 Removal Of Old ( 250 / 160 Kva ) Transformer With All Connected Accessories From Existing Plinth. 31 Removal Of Old Transformer ( 100 / 63 / 25 / 16 Kva ) With All Connected Accessories From Existing Double Pole. 32 Construction Of Chair Mounted Plinth With Fabrication & Angle Clamp Etc. 33 The Construction Of New Plinth Of Size 5’X5’X4’ Aboveground Level And One Ft. Below The Ground Level For 400 / 250 Kva Transformer 34 Installation Of Following Transformer On Plinth / Double Pole With All Connecting Accessories Jumering Etc. Including Carriage Of Transformers From Store Centre, Mathura To Work Site. 35 250 Kva Transformer On Plinth 36 Erection Of Tail Less Unit Complete 37 Construction Of M.S Angle Fencing Of Size ( 3M X3m X2m ) Around The Plinth Of 400 / 250 Kva Transformer And Gap Between The M.S Angle Should Not Be More Than 65Mm. 38 Complete Chemical Earthingof 11 / 0.4 Kv 250 / 400 Distribution Transformer By Digging Pits 6” Dia Upto 3 Mtr. Deep Including Chemical Filled Pipe In Between ( Pipe-In-Pipe ) Isi Mark B Grade & Connecting With G.I Strip Of Size 50Mm X 6Mm With Neutral / Body Of 11 / 0.4 Kv Distribution Transformer To Above Pipe-In-Pipe ( Pip ) And Filling Of Chemical Crystalline Conductive Mixture Containing Highly Conductive Material Around The ( Pipe-In-Pipe ) Up To 3 Mtr. Including Making Of Chamber At The Top Of The Earthing. Other Details Are As Below:-1.Earth Pipe Material – Mild Steel, Galvanised.2-Main Electrode Diameter – 42.4Mm.3-Auxiliary Electrode Pipe, Diameter – 76Mm.4-Wall Thickness Of Main Electrode :- 2.6Mm.5-Wall Thickness Of Auxiliary Ist Whole:- 3.2Mm.6- Length Of Earthing Electrode ( Pip ) :- 3 Meter. 39 Safe Carriage With Loading And Unloading Of Removed T / F And Lt Cable From Work Side To 132 Kv S / S Store Center Mathura 40 Dismantling Of 33 / 11Kv Line And Cartage Of Material From Work Site To Store Centre, Mathura.

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 31-Mar-2023 CORRIGENDUM 1 Date 03-04-2023

Key Value

Document Fees
INR 1000 /-
EMD
INR 10000.0 /-
Tender Value
INR 9.07 Lakhs /-

BOQ Items

Name of Work : Carrying out different works under Business plan scheme in the area of EE, EUDD-III, Mathura under the jurisdiction of the Superintending Engineer, Electricity Urban Distribution Circle, Mathura.
Sl. No. Item Description
1Cartage of following material from Store centre, Mathura to work site.
2ST Pole/PCC Pole (11/9/8.5 mtr. Long)
3250 KVA T/F.
411KV XLPE cable of size 3x300/240/185/120/70 Sq.mm.
533 KV XLPE cable of size 3x300Sq.mm.
6LT XLPE/PVC cable 1cx630/400/240 sq.mm.
7ACSR Dog/Weasel/Ins. Weasel conductor
8Other line material such as cross arm, MS top channel, bottom channel, Tee-channel, clamps, Suspension Clamp, Dead End Clamp, Cross Arm Holding Clamp, Danger Board, Pin Insulator, Disc Insulator nut & bolts etc.
9Opening of Jumper, Connection & Earthing of Body and Neutral of 5 MVA Transformer and Dismantling of Neutral Earthing frame, cable frame.
10Safe shifting of 5 MVA T/F. from Plinth to yard corner.
11Re-fixing of 33 KV Cable, Jumper & Earthing (Neutral & Body Earthing connected by electric welding)., Erection of Neutral Earthing frame, Cable frame
12Earthing of Power T/F
13Water Level Earthing
14Pipe in Pipe Gel Earthing
15Digging of pit & erection of new Double STP 09 Mtr. Long for Chair Mounted Plinth Structure including grouting of pole and fixing of all clamps, cross arm, pin/disc insulator & other accessories with providing stone pad as per relevant drawings. Any fabrication if required for above support.
16Digging of pit & erection of new Double ST/PCC Pole (11/9/8.5 mtr. long) including grouting of pole and fixing of all clamps, cross arm, pin/disc insulator & other accessories with providing stone pad as per relevant drawings. Any fabrication if required for above support.
17Digging of pit & erection of new Single Pole 11 Mtr. Long for Tri Pole including grouting of pole and fixing of all clamps, channel, bracing,pin/disc insulator & other accessories with providing stone pad as per relevant drawings. Any fabrication if required for above support.
18Earthing of ST/PCC pole/Body earthing of T/F. by M.S earth rod.
19Painting of ST pole.
20Digging of pit & erection of Stay rod with grouting cement sand and brick ballast including Nuzzling, binding Complete.
21By Excavation land upto 6 mtr. and removing 33 KV XLPE Cable upto 50 mtr.
22Laying of 33/11KV/LT line on Dog/weasel conductor on erected poles.
23Laying of LT PVC/XLPE cable 1cx630/400/240 sq.mm.
24Digging of trench by excavation of earth 0.90/1.5 Mtr. deep put brick on both side, filling of sand & brick on cable & earth ramming and dressing properly with complete job for laying 33/11 KV XLPE cable in trench
25Laying of 33/11 KV XLPE cable in Trench/Double Pole structure & air and filling of cable jointing kit with proper dressing.
26Installation of LT Protection System for Distribution T/F with all fittings
27Providing & fixing of Aluminium Lug 70/150/240/400/630
28Straight Through for 33 KV Cable Underground
29Jointing of cable with another cable/overhead line at the D/P structure through 33/11 KV outdoor & indoor cable jointing kit
30Removal of old (250/160 KVA) transformer with all connected accessories from existing plinth.
31Removal of old transformer(100/63/25/ 16 KVA) with all connected accessories from existing double pole.
32Construction of Chair mounted plinth with fabrication & Angle clamp etc.
33The Construction of new Plinth of Size 5’X5’X4’ aboveground level and one ft. below the ground level for 400/250 KVA transformer
34Installation of following transformer on Plinth/Double pole with all connecting accessories jumering etc. including carriage of transformers from store centre, Mathura to work site.
35250 KVA Transformer on Plinth
36Erection of Tail less unit complete
37Construction of M.S angle fencing of size (3M x3M x2M) around the plinth of 400/250 KVA transformer and gap between the M.S angle should not be more than 65mm.
38Complete chemical earthingof 11/0.4 KV 250/400 Distribution Transformer by digging pits 6” dia upto 3 mtr. deep including chemical filled pipe in between (pipe-in-pipe) ISI mark B Grade & connecting with G.I strip of size 50mm X 6mm with neutral/body of 11/0.4 KV distribution transformer to above pipe-in-pipe (PIP) and filling of chemical crystalline conductive mixture containing highly conductive material around the (pipe-in-pipe) up to 3 Mtr. including making of chamber at the top of the earthing. Other details are as below:- 1.Earth pipe material – mild steel, Galvanised. 2-Main Electrode diameter – 42.4mm. 3-Auxiliary Electrode pipe, Diameter – 76mm. 4-Wall Thickness of main Electrode :- 2.6mm. 5-Wall thickness of auxiliary Ist whole:- 3.2mm. 6- Length of earthing electrode (PIP):- 3 Meter.
39Safe Carriage with Loading and unloading of Removed T/F and LT Cable from Work side to 132 KV S/S Store Center Mathura
40Dismantling of 33/11KV line and cartage of material from work site to Store Centre, Mathura.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail