Tender For Urgent Maintenance Work Of Central Workshop Including Replacing Ac Roof Sheet With Gi Sheet And Replacing Ceiling Sheet , Etc, calicut-Kerala

National Institute Of Technology-NIT has published Tender For Urgent Maintenance Work Of Central Workshop Including Replacing Ac Roof Sheet With Gi Sheet And Replacing Ceiling Sheet , Etc. Submission Date for this Tender is 15-03-2023. Shed Construction Tenders in calicut Kerala. Bidders can get complete Tender details and download the document.




Tender Notice

36321357
Corrigendum : Tender For Urgent Maintenance Work Of Central Workshop Including Replacing Ac Roof Sheet With Gi Sheet And Replacing Ceiling Sheet , Etc
Open Tender
Indian
Kerala
calicut
15-03-2023

Tender Details

Urgent Maintenance Work Of Central Workshop Including Replacing Ac Roof Sheet With Gi Sheet And Replacing Ceiling Sheet , Etc

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 13-Mar-2023 Correction in Units Date 15-03-2023

Key Value

Document Fees
INR 590 /-
EMD
INR 196000.0 /-
Tender Value
INR 97.76 Lakhs /-

BOQ Items

Name of Work: Urgent maintenance work of central workshop including replacing AC roof sheet with GI sheet and replacing ceiling sheet , etc
Sl. No. Item Description
1Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
21:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
3Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
41:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size de rived from natural sources)
5Centering and shuttering including strutting, propping etc. and removal of form for
6Suspended floors, roofs, landings, balconies and access platform
7Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
8Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.
9Thermo-Mechanically Treated bars of grade Fe-500D or more.
10Laterate masonry with neatly dressed laterate stone of size 35x20x20cm or nearest size for superstructure above plinth level up to floor two level including all cost of materials, labour charges etc..
11Cement Mortar 1:6 (1 cement : 6 coarse sand).
12Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
13Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete.
14GI Tubular TATA or equvalent
15Providing & fixing fly proof wire gauze to windows, clerestory windows & doors with M.S. Flat 15x3 mm and nuts & bolts complete.
16Galvanised M.S. Wire gauze with 0.63 mm dia wire and 1.4 mm aperture on both sides
17Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer- in-charge. The sheet shall be fixed using self drilling /self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required.
18Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm (+0.05 %) total coated thickness, Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete :
19Ridges plain (500 - 600mm)
20Providing square type UPVC gutter with necessary clamps, bolts, nuts and specials such as nozzles sockets stoppers etc. including cost and conveyance of all materials and labour charges etc. complete as per the instructions of the dept. officers
21200mm or equivalent Square type UPVC
22Providing and fixing precoated galvanised iron (GI) sheet roofing accessories 0.50 mm (+0.05 %) total coated thickness, Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete :
23Ridges, hips or valley
24Providing and fixing false ceiling with 7.5 mm thick specified PVC panel board ceiling of approved quality in aluminium frame work with necessary screws etc complete ( aluminium frame work shall be paid separately)
25PVC plain panel 7.5 mm or nearest thick
2612 mm cement plaster of mix :
271:4 (1 cement: 4 fine sand)
28Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer"s specifications including appropriate priming coat, preparation of surface, etc. complete.
29On steel work
30Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 grams/ litre of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour.
31One coat
32Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead :
33Of sectional area below 40 square centimetres
34Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of:
35Asbestos Cement sheet
36Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead.
37Providing and fixing Polyvinyl Chloride (PVC) pipes, including all PVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step PVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall
38110 mm nominal dia Pipes (4kg/cm2)
39Providing and fixing powder coated aluminium work (minimum thickness of powder coating 50 micron) consisting of tee/ angle sections, of approved make conforming to IS : 733 in frames of false ceiling including aluminium angle cleats with necessary C.P. brass/ stainless steel sunk screws, aluminium perimeter angles fixed to wall with stainless steel rawl plugs @ 450 mm centre to centre and fixing the frame work to G.I. level adjusting hangers 6 mm dia. with necessary cadmium plated machine screws all complete as per approved architectural drawings and direction of the Engineer-in- charge (level adjusting hangers, ceiling cleats and expansion hold fasteners to be paid for separately).
40Providing and laying water proofing treatment over the concrete surface by applying cement based two component polymer modified water proofing slurry coating coating (SIKA 109 TOP seal or equivalent)after cleaning the surface free from scale, rust, grease, oil etc. preparing the surface to be true and flat and saturatedmixing the liquid (A) and powder (B) components in the ratio 1:4 by weight, applying in two coats with an interval of 2 to 6 hours for hardening in between and finally finished by rubbing down with a soft, dry sponge including protecting the applied surface from direct sunlight and storng wind and curing by gunny bags or polythene sheeting upto 5 days etc. complete.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail