Uttarakhand Power Corporation Limited-UPCL has published Repair Of Electricity Lines And Transformers Damaged In Natural Disaster In Between 07.10.2022 To 10.10.2022 At Lamgara Section Of Edsd 2Nd, Almora. Submission Date for this Tender is 15-03-2023. Transformer Supply Tenders in almora Uttarakhand. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Supply of Top Channel Clamp SP23 with N&B |
2 | Supply of LT Shackle Insulator with N&B |
3 | Supply of LT Clamp for SP-21 with N&B |
4 | Supply of LT Clamp for SP-10 with N&B |
5 | Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km ST pole SP 23 (Galvenised) |
6 | Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km ST pole SP 21 (Galvenised) |
7 | Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km ST pole SP 10 (Galvenised) |
8 | Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km 11/0.4 KV 25 KVA New |
9 | Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km11/0.4 KV 63 KVA New |
10 | Motarable cartage of Material from Almora to road side dump store Including Loading & Un-loading both End.Dist 65 Km Small materials |
11 | Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km ST pole SP 23 (Galvenised) |
12 | Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km ST pole SP 21 (Galvenised) |
13 | Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km ST pole SP 10 (Galvenised) |
14 | Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km 11/0.4 KV 25 KVA New (Upto 1 to 3 Km) |
15 | Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km 11/0.4 KV 63 KVA New (upto 1 Km) |
16 | Head load cartage of following materials from Dump store to pit site ava. Lead distance 2 Km Small materials (upto 1 to 3 Km) |
17 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductorSingle Pole SP 10 |
18 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductorSingle Pole SP 21 |
19 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductorSingle Pole SP 23 |
20 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductorDouble Pole Sp 23 |
21 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor11 KV ACSR weasel |
22 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductorLT 3 PH 4 wire Weasel / AB cable |
23 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductorLT 1 PH 2 Wire Weasel / AB Cable |
24 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor11/0.4 KV 25 KVA New |
25 | Dismentling of Existing T/F,LT/HT line including all accessories Including rolling of conductor11/0.4 KV 63 KVA New |
26 | Excavation of earth for pole pit for errection of pole in all type of soil in size 0.9X0.6X1/6 of pole lengh of Sp 23/21/10 |
27 | Erection of Double Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-23. |
28 | Erection of Single Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-23. |
29 | Erection of Single Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-21 |
30 | Erection of Single Poles alongwith Fixing all Accessories in the pole as per RESPO of SP-10 |
31 | Grouting of pole in CC ratio 1:4:8 including cost of Cement, sand, Stone ballast as per RESPO norms in size 0.45X0.45X1/9 of SP 23/21/10 Pole |
32 | Muffing of Pole With CC 1:3:6 Block 45cm Height from Ground level Including cost of Ballast,cement & sand Etc. |
33 | Fabrication of MS Channel/MS Angle making proper hole as per norms complete |
34 | Looping Chooping and cutting of tree which fallen on line |
35 | Laying & Resagging of 11 KV line in Weasel Conductor Complete including Fixing of all accessories as per RESPO (1ph or 3 Ph) |
36 | Laying & Resagging of LTLine with ACSR Weasel conductor including continuous earth wire complete work up to energizing LT 3 PH 4 wire Weasel / AB cable |
37 | Laying & Resagging of LTLine with ACSR Weasel conductor including continuous earth wire complete work up to energizing LT 1 PH 2 Wire Weasel / AB Cable |
38 | Installation/mounting of new T/F in DP structure and its complete comissioning as per RESPO 11/0.4 KV 25 KVA New |
39 | Installation/mounting of new T/F in DP structure and its complete comissioning as per RESPO 11/0.4 KV 63 KVA New |
40 | Back Head load cartage of materials from pit site to Dump store ava. Lead distance 3 Km 11/0.4 KV 25 KVA New (Upto 1 to 3 Km) |
41 | Back Head load cartage of materials from pit site to Dump store ava. Lead distance 3 Km 11/0.4 KV 63 KVA New (upto 1 Km) |
42 | Back Motarable cartage of Material from road side dump store to Almora Including Loading & Un-loading both End.Dist 65 Km 11/0.4 KV 25 KVA New |
43 | Back Motarable cartage of Material from road side dump store to Almora Including Loading & Un-loading both End.Dist 65 Km 11/0.4 KV 63 KVA New |
44 | Back Motarable cartage of Material from road side dump store to Almora Including Loading & Un-loading both End.Dist 65 KmSmall materials |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail