Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited-UPRVUNL has published Work Of Operation Maintenance And Management Work Of Operation Maintenance And Management Of Complete Merry Go Round ( Mgr ) System Of Anpara Thermal Power Station ( 3X210 Mw Atps 2X500 Mw Btps And 2X500 Mw Dtps As Per Indian Railway Rdso Standard And . Submission Date for this Tender is 20-09-2022. Playground Merry Go Rounds Tenders in anpara Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 20-Aug-2022 | Extension of dates | Date | 30-08-2022 |
2 | 30-Aug-2022 | DATE EXTENSION1 | Date | 12-09-2022 |
3 | 13-Sep-2022 | Date Extension 2 | Date | 20-09-2022 |
Sl. No. | Item Description |
1 | Management and safe operation of coal rakes including assistance in receiving of coal, shunting of rakes, preparation, attachment/ detachment of wagons, changing of points for transportation of coal round the clock. |
2 | Kakari Wharfwall/ Kakari CHP to track hopper A/B/D by Nigam’s BOBR wagons and return back. |
3 | (in Lac MT/month) |
4 | Khadia CHP to track hopper A/B/D by Nigam’s BOBR wagons and return back. |
5 | (in Lac MT/month) |
6 | Safe operation, transportation, shunting of rakes, attachment, detachment of wagons, changing of points etc. with the help of Rly. Loco/ Nigam loco from Krishnashilla exchange yard to track hopper A/B/D and return back. |
7 | (in Lac MT/month) |
8 | Note- The amount for two years against Item No. 1.1, 1.2 and 2 will be calculated by considering the approximate monthly quantity of 4.50 Lac, 5.30 Lac, & 2.70Lac MT of coal respectively. |
9 | Unloading of crushed coal from BOBR wagons round the clock at ‘A’/ ‘B’ track hopper including cleaning of track and grating of A / B track hopper, wagon capacity 60 MT each wagon. |
10 | (in Lac MT/month) |
11 | Note- The amount for two years against Item No. 3 will be calculated by considering the approximate monthly quantity of 7.50 Lac MT of coal. |
12 | Maintenance of signaling & telecommunication system |
13 | Maintenance of signaling system including daily, weekly, monthly, quarterly, half yearly, yearly schedule maintenance and attending break down maintenance round the clock at Anpara ‘A’ & ‘B’ area as per scope of works. |
14 | Maintenance of signaling system including daily, weekly, monthly, quarterly, half yearly, yearly schedule maintenance and attending break down maintenance round the clock at Anpara ‘D’ area as per scope of works . |
15 | Maintenance of signaling system including daily, weekly, monthly, quarterly, half yearly, yearly schedule maintenance and attending break down maintenance round the clock at Kakari area as per scope of works. |
16 | Maintenance of signaling system including daily, weekly, monthly, quarterly, half yearly, yearly schedule maintenance and attending break down maintenance round the clock at Khadia area as per scope of works. |
17 | Signalling cable laying, underground, all sizes and cores as and when required as per scope of works. |
18 | Round the clock operation and minor maintenance at each manned Level Crossing gates in all three shifts (04 Nos./Month). |
19 | Round the clock operation and day to day maintenance offollowing weigh bridges: |
20 | In-motion Rail-weigh bridge (04 Nos./Month). |
21 | Static road weigh bridge (03 Nos./Month). |
22 | Routine/ breakdown maintenance of locomotives as per manufacturer’s/ RDSO recommendations(10 Nos./Month) . This will include following works:- |
23 | Daily checking / breakdown maintenance. |
24 | Fortnightly maintenance. |
25 | Weekly maintenance. |
26 | Monthly maintenance. |
27 | Schedule maintenance of locomotives. |
28 | Quarterly maintenance. |
29 | Yearly maintenance. |
30 | Schedule maintenance of wagons. |
31 | Quarterly maintenance. |
32 | Yearly maintenance. |
33 | Three yearly maintenance. |
34 | Routine/ breakdown maintenance of CIMMCO/ BURN make bottom discharge type wagons as manufacturers/ RDSO recommendations (177 Nos./Month). This will include following works:- |
35 | Daily checking / breakdown maintenance. |
36 | Weekly maintenance. |
37 | Monthly maintenance. |
38 | Routine/ breakdown maintenance of telecommunication equipments (VHF) sets 16 Nos. Hand Held wireless set (30 Nos./Month). |
39 | Fixed set. |
40 | Loco mounted. |
41 | Sax hand set. |
42 | Routine Maintenance of Track - To carryout daily, weekly, monthly routine/ breakdown maintenance of rail track of MGR system including track on bridge etc. as per Rly./ RDSO recommendation (86.529 Kms/Month). This will include following works:-- |
43 | Daily examination of complete track, points & crossings and tightening their fittings and their replacement, if any. |
44 | Replacement of the demaged/ missing fittings. |
45 | Picking up slakes and packing of sleepers with existing ballast. |
46 | Squaring of sleepers and removal of uneven spacing. |
47 | Gauging of track / rail crossing. |
48 | Shallow screening and making up of ballast section after opening of track where-ever required. |
49 | Alignment of track by lifting / lowering and correcting longitudinal cross level and final alignment. |
50 | Realignment of curves. |
51 | Maintenance of points and crossings with their accessories. |
52 | Maintenance of proper crossing gauge on the check rails and it"s adjustment to the correct profile. |
53 | Adjustment of creeps and expansion gaps of joints by pulling back of rail and providing anti creep bearing plates/ creep archer to prevent further creeping. |
54 | Maintenance of level crossings. |
55 | Maintenance of posts curves. |
56 | Removal of all track defects like high joint blowing and pumping joint, longitudinal sag in the track, centre bound sleeper. |
57 | Maintenance of the meter/ KM/ curve/ signal post lying along MGR track (Post shall be supplied by the department i.e. Nigam free of cost). |
58 | Emergency maintenance of track hopper/ Kakari silo/ Khadia silo / wharf-wall loading point/ track during dislocation or derail- ment on the track. |
59 | Daily checking and tightening of the all bolts and nuts, two way keys and other fittings on the track. |
60 | Schedule maintenance of track and other civil works. |
61 | Grouting of inserts with eppoxy compound and quartz sand at track hopper , Kakari and Khadia silo, MGR workshop or wherever required including all epoxy material quartz sand, T&Pand labour etc. Epoxy compound shall be CIBA or Dr Beck or equivalent make. |
62 | Replacement of broken/ damaged rail, glued joints and points including to and fro transportation from yards. |
63 | Replacement of crossings including to and fro transportation from yards. - 1 in 8.5 |
64 | Replacement of crossings including to and fro transportation from yards. - 1 in 16 |
65 | Replacement of damaged / rotten sleepers . - All type of track sleepers. |
66 | Replacement of damaged / rotten sleepers .- Wooden sleepers at bridge& culverts. |
67 | Lubrication of fish plate, its nuts & bolts after unscrewing the same and including tightening after lubrication (one job shall be considered as one unit. |
68 | Cleaning of track from grass & vegetation including uprooting of rank vegetation, bush wood, trees & sapling and disposal of garbage out side the track area as directed by the Engineer-in- charge including all leads & lifts (DSR code 2.32). Quantity taken for 2 times in a year : 02 Years X(63700 m + 22829 m =86529 m track length) X 4.0 m (width) X 2 times = 1384464 sqm. |
69 | Cleaning of MGR track from muds, land slides, fallen tree and disposal of earth/rubbish outside the track area as directed by the Engineer-in-charge up to a lead of 2 km including all leads & lifts of 10 M by mechanical transport including dressing the disposed earth neatly. |
70 | Earth work in excavation over areas (excluding 30 cm in depth, 1.5 m in width as well as 10 sq.m on plan including transportation of excavated earth and filling in rain cuts fissures cess repair on formation level in layers not exceeding 20 cm. In depth, consoli - dation each layer by remaining and watering including all leads & lifts (payment shall be made by measurement of borrow pits). |
71 | Through packing of track ballast including opening of track, squaring of sleepers, aligning of track and dressing includes all labour, T&P etc. complete. Quantity calculated as per norms of IndianRailways Permanent way manual for maintenance of track: 02 Years X (63700 m - 6000 m = 57700 m + 22829 m - 4500 m = 18329 m ) = 152058 m. |
72 | Deep screening of the stone ballast by opening the track, deep screening, lying and through packing, levelling, aligning and commissioning the track with all materials, labour and T&P required for proper completion of the work as per specifications. |
73 | Painting of the caution marks and the boards with synthetic enamel paint of first quality including a coat of primer on new work (DSR code 13.62.1). |
74 | Lettering with black Japan paint of approved brand & manufacturer (DSR code 13.71). |
75 | Providing and laying cement concrete in footing and bases of columns excluding the cost of centering & shuttering. (DSR code 4.1) - (a) 1:2:4 (1 cement:2 coarse sand:4 graded stone aggregate 20 mm nominal size (DSR code 4.1.3). |
76 | Providing and laying cement concrete in footing and bases of columns excluding the cost of centering & shuttering. (DSR code 4.1) -(b) 1:5:10 (1 cement:5 coarse sand:10 graded stone aggregate 40 mm nominalsize. (DSR code 4.1.10) |
77 | Centering and shuttering including strutting propping etc. and removal of form work for lintels and beams, plinth beams, girders, bressumers and cantilevers (DSR code 5.9.5). |
78 | Reinforced cement concrete work in footings and bases of the columnsexcluding centering, shuttering and reinforcement. - (a) 1:1.5:3 (1 cement:1.5 coarse sand:3 graded stone aggregate 20 mm nominalsize (DSR code 5.1.2). |
79 | Reinforced cement concrete work in footings and bases of the columnsexcluding centering, shuttering and reinforcement. -(b) 1:2:4 (1 cement:2 coarse sand:4graded stone aggregate 20 mm nominal size (DSR code 5.1.3). |
80 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level with cold twisted bars (DSR code 5.22.3). |
81 | Brick work with common burnt clay F.P.S (non modular) bricks of class designation 7.5 in foundation and plinth in Cement mortar 1:4 (1 cement : 4 coarse sand) (DSR code 6.1.1). |
82 | Random rubble masonry with hard stone in foundation and plinth including leveling upwith cement concrete 1:6:12 (1 cement: 6 coarse sand:12 graded stone aggregate 20 mm nominal size with 1:6 cement mortar) (DSR code 7.1.1). |
83 | Structural steel work in single section, fixed with or without connecting plate including cutting, hoisting, fixing in position and applying priming coat of approved steel primer all complete (DSR code 10.1). |
84 | Dry stone pitching 22.5 Cm thick including supply of of stone and preparing surface completely (DSR code 16.11). |
85 | Cutting, welding and grinding of damaged tongue rail with IVR 456 L&T/ CFS-80 Advani or equivalent make electrodes on existing running track of MGR including finishinglike original surface without interruption in coal rake movement of MGR. |
86 | Cutting, welding and grinding of worn out crossing with IVR 456 L&T/CGS-80Advani make electrode or equivalent on existing running track of MGR including finishing like original surface without interruption in coal rake movement of MGR. |
87 | Spreading of 65 mm stone ballast on the track from different location or as desired by the Engineer-in-charge including all leads and lifts. (Stone ballast supplied by nigam free of cost). |
88 | Supply and spreading of 65 mm stone ballast on the track from different location or as desired by the Engineer-in-charge including all leads and lifts. |
89 | White washing with lime on wall surface to give an even shed on old work (one or more coats) including cost of material, labour, T&P etc. (DSR code 14.42.2). |
90 | Distempering with oil bound washable distemper of approvedbrand & manufacturer and of required shed to give an even shed on old work (one or more coats) including cost of material, labour,T&P etc. (DSR code 14.45.1). |
91 | Finishing of walls with water proofing cement paintof required shed on old work (one or more coats applied @2.20Kg/10 sqm) over priming coat of primer applied @0.80 litrs/10sqm completeincluding cost ofmaterial,labourT&P etc. (DSR code 14.64.1). |
92 | Painting with synthetic enamel paint of approved brand & manufacturer and to give an even shed. One or more coats on old work in all sheds except black or chocolate shade for first quality paint. This includes cost of material, labour, T&P etc. (DSR code 14.54). |
93 | Providing wood works in frames or doors / windows / clearstory windows and other frames wrought framed and fixed in position (salwood) (DSR code 9.1.2). |
94 | Providing and fixing glass panes weighing 10 Kg/ sq meter (4 mm thick) (DSR code 14.6.1). |
95 | Varnishing with flating Varnish of approved brand and manufac- turer, one or more coats on old work (DSR code 14.71). |
96 | Operation & maintenance of Buldozers & payloader. |
97 | Preventing checking/ routine maintenance of equipment as and when required. |
98 | Providing assistance to operators/ technicians during running/ maintenance of buldozers. |
99 | Operation of bulldozers by experienced skilled/ operator in coal yard of A/B TPS. |
100 | Operation of 01 no. pay loader by experienced /skilled operation in coal yard of A/B TPS. |
101 | Operation of equipment by experienced/ skilled operator as and when required by the division other than CHP coal yard - Inside plant area. |
102 | Operation of equipment by experienced/ skilled operator as and when required by the division other than CHP coal yard - Outside plant area. |
103 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of clutch system of buldozer no. D-80-A-12. |
104 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of gear box and transmission system of BD-155-A-3. |
105 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of steering system of:BD-155-A-3/D-155-A-1/D6H. |
106 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of steering system of:D-80-A-12. |
107 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of brake shoe lining of buldozer no. BD-155-A-3/D-155-A-1/D6H/D-80-A-12. |
108 | Tightening of brake drum By adopter system after putting grease for : BD-155-A-3/D-155-A-1/D6H. |
109 | Tightening of brake drum By adopter system after putting grease for : D-80-A-12. |
110 | Tightening of brake drum By dismantling of broken chain and its cuttingfor :BD-155-A-3/D-155-A-1/D6H. |
111 | Tightening of brake drum By dismantling of broken chain and its cuttingfor : D-80-A-12. |
112 | Dismantling, checking, repairing, replacement/adjustment and reassembling of recoil spsring system of BD-155-A-3/D-155-A-1/D6H/D-80-A-12. |
113 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of oil seals for hydraulic system for blade lift cylinder of: BD-155-A-3/D-155-A-1/D6H. |
114 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of oil seals for hydraulic system for blade lift cylinder of: D-80-A-12. |
115 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of:BD-155-A-3/D-155-A-1/D6H. |
116 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of:D-80-A-12. |
117 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of: BD-155-A-3/D-155-A-1/D6H. |
118 | Dismantling, checking, repairing, replacement/ adjustment and reassembling of: D-80-A-12. |
119 | Repairing of support plates of cutting edge of : BD-155-A-3/D-155-A-1/D6H. |
120 | Repairing of support plates of cutting edge of : D-80-A-12. |
121 | Repairing of bulldozer blade of BD-155-A-3/D-155-A-1/D6H/D-8-A-12 by cutting straightering and welding. |
122 | Dismantling, checking, repairing, replacement/ adjustment andreassembling of Alternator of : BD-155-A-3/D-155-A-1/D6H. |
123 | Dismantling, checking, repairing, replacement/ adjustment andreassembling of Alternator of : D-80-A-12. |
124 | Dismantling, checking, repairing, replacement/ adjustment andreassembling of Winding of coils for alternator using standard make gauge wire for : BD-155-A-3/D-155-A-1/D6H. |
125 | Dismantling, checking, repairing, replacement/ adjustment andreassembling of Winding of coils for alternator using standard make gauge wire for : D-80-A-12/pay loader. |
126 | Dismantling, checking, repairing, replacement/adjustment andreassembling of Self Starter of : BD-155-A-3/D-155-A-1/D6H. |
127 | Dismantling, checking, repairing, replacement/adjustment andreassembling of Self Starter of : D-80-A-12/pay loader. |
128 | Dismantling, checking, repairing, replacement/adjustment andreassembling of Winding of coils for self starter using standard make gauge wire for BD-155-A-3/D-155-A-1/D6H. |
129 | Dismantling, checking, repairing, replacement/adjustment andreassembling of Winding of coils for self starter using standard make gauge wire for D-80-A-12/pay loader. |
130 | Dismantling, checking, repairing, replacement/adjustment andreassembling of radiator of : BD-155-A-3/D-155-A-1/D6H. |
131 | Dismantling, checking, repairing, replacement/adjustment andreassembling of radiator of : D-80-A-12/pay loader. |
132 | Dismantling, checking, repairing, replacement/ adjustment andreassembling of universal joint for : BD-155-A-3/D-155-A-1/D6H. |
133 | Dismantling, checking, repairing, replacement/ adjustment andreassembling of universal joint for : D-80-A-12/pay loader. |
134 | Dismantling, checking, repairing, replacement/adjustment andreassembling of water pump of :BD-155-A-3/D-155-A-1/D6H/ D-80-A-12. |
135 | Dismantling, checking, repairing, replacement/adjustment andreassembling of water pump of : Pay loader. |
136 | Dismantling, checking, repairing, replacement/adjustment and ressembling of main oil cooler of BD-155-A-3/D-155-A-1/D6H/D-A-12. |
137 | Dismantling, checking, repairing, replacement/adjustment of oil cooler of BD-155-A-3/D-155-A-1/D6H/ D-80-A-12. |
138 | Dismantling, checking, repairing, replacement/ adjustment of Turbo charger of BD-155-A-3/D-155-A-1/D6H/ D-80-A-12. |
139 | Dismantling, checking and mounting the driver seat using good quality of Rexene, jute, spring of : BD-155-A-3/D-155-A-1/D6H. |
140 | Dismantling, checking and mounting the driver seat using good quality of Rexene, jute, spring of : D-80-A-12/ pay loader. |
141 | To set right the dislocated track chain due to slipping or any other reason of BD-155A-3/D-155A-1/D6H/D-8-A-12. |
142 | Dismantling, cleaning, oiling/greasing, repairing,replacement/ adjustment and reassembling of : BD-155-A-3/D-155-A-1/D6H. |
143 | Dismantling, cleaning, oiling/greasing, repairing,replacement/ adjustment and reassembling of : D-80-A-12/ pay loader. |
144 | Dismantling, cleaning, oiling/greasing, repairing,replacement/ adjustment and reassembling of blade control linkage of : BD-155-A-3/D-155-A-1/D6H. |
145 | Dismantling, cleaning, oiling/greasing, repairing,replacement/ adjustment and reassembling of blade control linkage of : D-80-A-12. |
146 | Dismantling, cleaning, checking, repairing/ replacement, adjustment and reassembling of bucket control linkage of pay loader. |
147 | Dismantling, cleaning, checking, repairing/ replacement, adjustment and reassembling of blade lift servo valve of BD-155-A-3/D-155-A-1/D6H/D-80-A-12. |
148 | Dismantling, cleaning, checking, repairing/ replacement, adjustment and reassembling of fuel control linkage/steering control linkage of. BD-155-A-3/D-155-A-1/D6H/D-80-A-12. |
149 | Dismantling, cleaning, checking, repairing/ replacement, adjustment and reassembling of gear shift lever/clutch lever of : BD-155-A-3/D-155-A-1/D6H. |
150 | Dismantling, cleaning, checking, repairing/ replacement, adjustment and reassembling of gear shift lever/clutch lever of : D-80-A-12/ pay loader. |
151 | Dismantling/ replacement and reassembling of Carrier roller ofBD-155-A-3/D-155-A-1/D6H. |
152 | Dismantling/ replacement and reassembling of Carrier roller of D-80-A-12. |
153 | Dismantling/ replacement and reassembling ofTrack roller BD-155-A-3/D-155-A-1/D6H/D-80-A-12. |
154 | Dismantling/ replacement and reassembling ofIdlers:BD-155-A-3/D-155-A-1/D6H/D-80-A-12D-80-A-12. |
155 | Dismantling/ replacement and reassembling ofTeeth sprocket segment: Idlers: BD-155-A-3/D-155-A-1/D6H/D-80-A-12D-80-A-12. |
156 | Dismantling, checking, repairing, replacement, adjustment of control valve, release valve of torque corivertor of BD-155-A-3/D-155-A-1. |
157 | Dismantling, cleaning, calibaration and assembling of injector nozzels of : BD-155-A-3/D-155-A-1/D6H. |
158 | Dismantling, cleaning, calibaration and assembling of injector nozzels of : D-80-A-12. |
159 | Dismantling, replacement, tightening and reassembling of hoses of Idlers:BD-155-A-3/D-155-A-1/D6H/D-80-A-12D-80-A-12/payloader. |
160 | Dismantling, checking andfitting of plate for changing, tightening of internal hoses of BD-155-A-3/D-155-A-1/D6H. |
161 | Dismantling, checking andfitting of plate for changing, tightening of internal hoses of D-80-A-12. |
162 | Detachment of engine of bulldozer/pay loader for overhauling purpose/ any other purpose for : BD-155-A-3/D-155-A-1/D6H. |
163 | Detachment of engine of bulldozer/pay loader for overhauling purpose/ any other purpose for : D-80-A-12. |
164 | Detachment of engine of bulldozer/pay loader Mounting and commissioning of bulldozer/pay loader engine for :BD-155-A-3/D-155-A-1/D6H. |
165 | Detachment of engine of bulldozer/pay loader Mounting and commissioning of bulldozer/pay loader engine forD-80-A-12/ pay loader. |
166 | Service/maintenance of bulldozers/pay loader Every 250 running hours for :BD-155-A-3/D-155-A-1/D6H |
167 | Service/maintenance of bulldozers/pay loader Every 250 running hours for :D-80-A-12/ pay loader. |
168 | Service/maintenance of bulldozers/pay loader Every 500 running hours for : BD-155-A-3/D-155-A-1/D6H. |
169 | Service/maintenance of bulldozers/pay loader Every 500 running hours for : D-80-A-12/ pay loader. |
170 | Service/maintenance of bulldozers/pay loader Every 1000 running hours for :BD-155-A-3/D-155-A-1/D6H. |
171 | Service/maintenance of bulldozers/pay loader Every 1000 running hours for :D-80-A-12/ pay loader. |
172 | Dismantling, cleaning, repairing, replacement, adjustment and reassembling of: Service system of pay loader. |
173 | Dismantling, cleaning, repairing, replacement, adjustment and reassembling of: Transmission system of pay loader. |
174 | Dismantling, cleaning, repairing, replacement, adjustment and reassembling of: Brake systgem of pay loader. |
175 | Dismantling, cleaning, repairing, replacement, adjustment and reassembling of: Hydraulic system of pay loader. |
176 | Dismantling, replacement/ adjustment of different types of oil seals of pay loader |
177 | Dismantling, replacement/adjustment of punctured tube and reassembly of tyre and pay loader. |
178 | Dismantling, replacement/adjustment of different type of oil seals of buldozers BD-155-A-3/D-155-A-1/D6H/D-80-A-12D-80-A-12. |
179 | Dismantling of canopy and repairing it by using good quality or Rexene & canvas and mounting the same. |
180 | Dismantling of canopy by cutting and welding of broken pprotion and reassembling of the same on bulldozers/pay loader. |
181 | Dismantling, repairing/replacement and adjustment of electrical and alarm system and gauges and fitting the same (i.e. fitting of light). |
182 | Preventive check up of batteries (including topping up of acid, voltage check up and putting them into charging). |
183 | Reconditioning of batteries - For 25 plate 12 V 180 AH. |
184 | Reconditioning of batteries - For 19 plate 12 V 135 AH. |
185 | Reconditioning of batteries - For 19 plate 12 V 110 AH. |
186 | Replacement of damaged cells of batteries - For 25 plate 12 V 180 AH. |
187 | Replacement of damaged cells of batteries - For 19 plate 12 V 135 AH. |
188 | Replacement of damaged cells of batteries - For 25 plate 12 V 110 AH. |
189 | Painting of bulldozers - BD-155-A-3/D-155-A-1. |
190 | Painting of bulldozers - D-80-A-12. |
191 | Painting of bulldozers - D6H/pay loader. |
192 | Dismantling, complete cleaning/flushing minor repairing &reassembling of hydraulic tank of bulldozer model D-155/D6H/D-80. |
193 | Mounting, complete cleaning flushing of fuel tank of bulldozer and its remounting of bulldozer model D-155/D6H/D-80. |
194 | Cleaning of drains along MGR Track & private railway siding |
195 | NSR, Cleaning of pucca/kuchcha drains of various sizes including removal of deposited earth, grass, vegetation, boulders, ballast & other debris from the bed and sides of the drain and its disposal up to 100 M as directed by the Engineer-in-charge including all leads and lifts and neatly dressing the disposed material. Top width up to 0.5 mtr. & depth from 0.5 to 1.0 mtr. |
196 | NSR, Cleaning of pucca/kuchcha drains of various sizes including removal of deposited earth, grass, vegetation, boulders, ballast & other debris from the bed and sides of the drain and its disposal up to 100 M as directed by the Engineer-in-charge including all leads and lifts and neatly dressing the disposed material. Top width from 0.5 mtr. to 1 mtr. & depth up to 1.5 mtr |
197 | NSR, Cleaning of pucca/kuchcha drains of various sizes including removal of deposited earth, grass, vegetation, boulders, ballast & other debris from the bed and sides of the drain and its disposal up to 100 M as directed by the Engineer-in-charge including all leads and lifts and neatly dressing the disposed material. Top width more than 1 mtr & depth more than 1.5 mtr. |
198 | DSR-2014, 2.8, Earth work in excavation in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m including getting out excavated soil and disposal of surplus up to 100 M. DSR-2014, 2.8.1, all kinds of soil. |
199 | NSR, Collection of garbage from different locations to a specified place and its disposal by Truck/Tractor/Trolley within 1 km distance including cost of labour T&P etc. required for proper completion of work. |
200 | NSR, Cleaning ofNala / Big drain flowing along M.G.R. Track with the help of mechanical device such as JCB with operator and one helper or sweeper, filled with slush brick, bats, mud, sewer, Cow dugs & other waste materials deposited in the bed to achieve free flow of water andremoving of stagnation of water including stacking the obtained material at proper location within 100 meter or directed by Engineer-in-charge including cost of all labour, T&P etc. required for proper completion of work. |
201 | Fabrication/ Erection and Repairing of gratings of the track hopper, stone pickers chutes, stands and other Misc. steel fabrication work |
202 | Fabrication of broken/damaged M.S. gratings at the track hopper of “A”TPS CHP (Wt. approx. 200 Kg.). |
203 | Repairing of broken/damaged M.S. gratings at the track hopper of “A”TPS CHP (Wt. approx. 200 Kg.). |
204 | Fabrication of stone picking chutes of stone picking of “A”TPS CHP (Wt. approx. 850 Kg.). |
205 | Repairing of broken damaged stone picking chute of picking area “A”TPS CHP (Wt. approx. 850 Kg.) |
206 | Fabrications of stone picking stand of stone picking area of “A” TPS CHP (Wt. approx. 100 Kg.). |
207 | Repairing of broken/damaged stone picking stand of stone picking area of “A”TPS CHP (Wt. approx. 100 Kg.). |
208 | Miscellaneous emergency fabrication and erection works at track hopper |
209 | Note – Rates should be exclusive of GST. |