| 1 | Labour for the Dismantling of 230 KV Double Conductor Strung Bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer. ( 50% cost of Erection+ 30% extra for LC works) |
| 2 | Labour for the Dismantling of 75 mm (1 length) Busbar including suitable Modifications of End Clamps, providing holes wherever necessary as directed by the field engineer. ( 50% cost of Erection+ 30% extra for LC works) |
| 3 | Labour for the Dismantling of Jumper/Droppers using Moose/Zebra/panther Double Conductors including Modification of End clamps, providing holes etc,. ( 50% cost of Erection+ 30% extra for LC works) |
| 4 | Labour for providing split arrangement(to connect disc insulators with fittings) in the strung bus/phase. |
| 5 | Labour for the Erection of 230 KV Double Conductor Strung Bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer.(30% extra for LC works) |
| 6 | Labour for the Erection of 75 mm (1 length) Busbar including suitable Modifications of End Clamps, providing holes wherever necessary as directed by the field engineer. |
| 7 | Labour for the Erection of Jumper/Droppers using Moose/Zebra/panther Double Conductors including Modification of End clamps, providing holes etc,. |
| 8 | Labour for the Dismantling of 110 KV Single Conductor Strung Bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer. |
| 9 | Labour for the Dismantling of 110 KV Double Conductor Strung Bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer. |
| 10 | Labour for the Erection of 110 KV Single Conductor Strung Bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer. |
| 11 | Labour for the Erection of 110 KV Double Conductor Strung Bus/phase and all related hardwares, fittings, clamps including Meggering, hoisting of insulators, and consumables and as directed by the field engineer. |
| 12 | SUPPLY OF MATERIALS:-11KV, 120 KN Ordinary Strain Disc Insulator |
| 13 | ACSR Zebra Conductor |
| 14 | T\"Clamp forZebra toZebra |
| 15 | Spacer Clamp for zebra (each )225mm spacing |
| 16 | T\"Clamp for 3\" Bus to Zebra |
| 17 | 6 bolted Tension fitting clamp |
| 18 | 24 \" Eyebolt with 2 nuts per unit |
| 19 | SGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only for Tamil Nadu Contractor. If the contractor is outside Tamil Nadu may be quoted as \"0\" only |
| 20 | CGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only for Tamil Nadu Contractor. If the contractor is outside Tamil Nadu may be quoted as \"0\" only |
| 21 | Inter-state GST to be quoted in percentage (value alone) Ex. 18%, it should be entered as 18 only for other than Tamil Nadu contractor. If the contractor is within Tamil Nadu may be quoted as \"0\" only |