| 1 | Description |
| 2 | Removing, Servicing and reinstalling, testing. perfect aligning and proper leveling and commission ing Booster Pump, 900 LPM (Litres/min) at 40 m head, 12.5 specification No.FF-MFP HP(10kW),3Phase, 415 volt,50 Hz /BP |
| 3 | Removing Servicing and reinstalling testing, perfect aligning and proper leveling and commission| ing of fire service main pump,2400 LPM (Litres/min) at 76 m head Dump,75HP.(55kW) Suction centrifugal type single stage /Delivery Size of 100/80mm as per specification No.FF-MFP /SSC2 |
| 4 | Removing. Servicing and reinstalling testing, perfect aligning and proper ing Jockey Pump,240 LPM leveling and commission (Litres/min) at 56 m head 15HP.(11kW),3 Phase,415 volt,50 Hz,as p |
| 5 | Removing,Servicing and reinstalling testing. perfect aligning and proper leveling and commission ing Sprinkler Pump,2280 LPM (Litres/min) at 56 m head as 15HP.(11kW).3 Phase,415 volt,50 Hz. per specification No.FF-MFP /JP |
| 6 | Removing, Servicing and reinstalling testing, perfect aligning and proper leveling and commission ing of Diesel fire pump.69 HP, having capacity of 50 mtrs. Head. 1440 LPM |
| 7 | Supplying.Rewiring, Installing,Servicing,Testing. Commissioning of fire coupled panel hydrant system auto for jockey and main pump complete with 3 star/delta starters phase indicators withrelays volt / Ammeter, main switches cut of fuses manual/ auto switch etc. (supply 3 phase 415 volt) |
| 8 | Supplying, installting ,Testng and Commissioning of 2.Smm.3core, wire for Booster Pump tofire pump room |
| 9 | Suppy Testing.Instaling and Commissioning of 69 HP Diesel Fire Pump Battery.12Volt Replacingd Bettery |
| 10 | Refilling, servicing. testing. painting. abeling. transportation, Installing and commisioning ofABCDy Chemical Powder).4 Kg Fire Extinguisher |
| 11 | Refing servicing. testing. painting. abeling. transportation, Installing and commisioningofco2,4,5 Kg Fire Extinguisher |
| 12 | Supplying and erecting MS, CRCA cabinet for housing Single hydrant valvesize 400x40dx40Omm.) made from 16 SWG sheet & angle iron 25mmx25mmx4mmhaving front doors with viewing glass (8\"x5) and locking arrangement with necessary withNecessary fixing material such as rubber bidding etc. duly painted in post box red colou |
| 13 | Supply.Installing. Testing and Commissioning of Branch Pipe Nozzle,Size -63mm,Gun Metal |
| 14 | Supply.Installing. Testing and Commissioning cf Shut Off Nozzlet |
| 15 | Supply,Instaling. Testing & Commissioning of R.RL Hosepipe.63mm dia15mm length fitted withnecessary accessories components |
| 16 | Supply, installation, testing& commissioning of optical type smoke detector and heat detectorcomp.On box as per specification No FF-FAS/SD |
| 17 | Servicing of Main fire Alarm panel microprocessor based fire alarm panel 36 zones type having2 sounder outputs fire & fault relay suitable for connecting 180 detectors manual call points frontglass proection |
| 18 | Sevicing of Main fire Alam panel microprocessor based fire alarm panel 28 zones type having2 sounder outouts fire & fault relay suitable for connecting 180 detectors manual call points frontglass protection |
| 19 | Senvicing of Main fire Alam panel microprocessor based fire alarm panel 04 zones type having2 sounder outputs fire & fault relay suitable for connecting 180 detectors manual call points frontglass protection |
| 20 | Supply.Testing.installation of Single Outlet Hydrant Valve Female Coupling |
| 21 | Servicing and loop connecting of smoke detector |
| 22 | Servicing.connecting and testing of manual control points |
| 23 | Senvicing.connecting and testing of alarnm Hooter |
| 24 | Supply and erecting testing and commissioning manual control points pill box with break glass4 Obtaining Fire No Objection Certficate from Fire Department |
| 25 | Obtaining Fire NO Objection Certificate from Fire Department |
| 26 | GST 18% |