| 1 | Construction of Two Class RoomSchool Building in Panchayat Union Elementary School@ Rajiv Gandhi Nagar in Valayambattu Panchayat. |
| 2 | Earth work excavation for foundation in all classes of soils and sub soil to full depthexcept in hard rock requiring blasting but inclusive of shoring struttingif required forthe sides of foundation. |
| 3 | Supplying and filling in foundation and basement with good sand in layers not more 15 cm thick including ramming, watering and compacting etc.complete complying to standard specification |
| 4 | Cement Concrete 1:4:8 mix using 40 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., complete complying with standard specifications and as directed. |
| 5 | Cement Concrete 1:2:4 mix using 20 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., complete complying with standard specifications and as directed. |
| 6 | Brick work in CM 1:5 mix using country bricks ground moulded of size 23 x 11 x 7 Cm for the following including curing etc., complete complying with standard specifications. |
| 7 | Supplying and Fabricating and placing in position MS Steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and blinding wire all floors etc., complete complying with standard specification. |
| 8 | steel qty |
| 9 | Supplying and Erection centering for sides and soffiots including necessaary supports and strutting as directed by the departmental officers. Rate for 10m2 for the following items (RCC floor slab, roff slab, Rectangular / Square, Tee/ Ell beams, Lintels, |
| 10 | Beam |
| 11 | Rainforcement Cement Concrete 1:1.5:3 using 20 mm ISS HBG metal for all RCC item of works excluding cost of reinforcement and fabricating charges, centering and shuttering but icluding curing and providing fixtures like fan clamps in the RCC floor or roof s |
| 12 | Super Structure |
| 13 | Plastering with CM 1:4, 20mm thick over the cement concrete for floor finish including curing etc., complete complying with standard specifications and as directed by the departmental officers. |
| 14 | Plinth protection platform |
| 15 | Providing granolethic floor finish in cement concrete 1:2:4 mix using 10-12mm ISS metal to 40mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete. |
| 16 | Roof Top |
| 17 | Paving the floor with Vertified tiles of any colour and any size laid in cm 1:3, 20mm thick. And pointing with whites cement 0.4 kg per sqm mixed with colour of the tiles including finishing the joints neaty complying with the standard specifi |
| 18 | Providing and finishing with a one course of Cooled Tiles of 12mm thick of all sizes and shapes CM 1:3, 20mm thick |
| 19 | Ceiling Plastering with cement mortar 1:3 mixto 10 mm thick for R.C.C. Items including cost and conveyance of all materials to site and all labour charges etc complete |
| 20 | Plastering with CM 1:5, 12mm thick over the cement concrete for floor finish including curing etc., complete complying with standard specifications and as directed by the departmental officers. |
| 21 | Distembering 2 coats using Oil Buond Distember including cost and conveyanceand all labour charges ctc. Complete |
| 22 | Painting Two coat approved Plastic Emulsion paint over the plastered surface including cost and all other charges etc., |
| 23 | Painting TWO coats of new iron works such as steel doors, windows,ventilators, window bars, balustrades etc., with best approved first quality of synthetic enamel paint of approved colour over the existing priming coats, etc., complete |
| 24 | Black board paint two coat using with approved paint etc completed |
| 25 | Supply of steel doors and windows |
| 26 | door 1.20 x2.10 m |
| 27 | Window W1.20 x 1.30 |
| 28 | Provision for Cuddapha slab cubbourd etc., |
| 29 | Provision for rain water |
| 30 | Provision for labour charges for fixingdoor, windows, etc., |
| 31 | Door 1.20 x2.10 m |
| 32 | Window W1.20 x 1.30 |
| 33 | Providing Rain Water Harvesting Structure |
| 34 | Provision for electrification works |
| 35 | Providing C.F.L light with all accessories etc. complete |
| 36 | Light Point |
| 37 | Supply and fixing of C.F.L. 20Watts light and fittings etc., |
| 38 | Providing Fan Point with accessories etc. complete |
| 39 | Fan Point |
| 40 | Fan |
| 41 | Providing bulk head light Point with all accessories etc. complete |
| 42 | Light Point |
| 43 | Bulk head Fitting |
| 44 | Plug point |
| 45 | DPTC switch |
| 46 | Service wire |
| 47 | GST Amount for providing service to Government contract works for the above construction works. { GST amount is the Total GST amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |