Construction Of Intake Well, Wtp, Rising Main, Pump House, Sump Cum Tank , Distribution System, Cwrs, Feeder Main, Service Cwrs, Staff Quarter And Electrical And Mechanical Work Etc At Indra-Tipri Pumping Water Supply Scheme , uttarkashi-Uttarakhand

Drinking Water And Sanitation Department has published Construction Of Intake Well, Wtp, Rising Main, Pump House, Sump Cum Tank , Distribution System, Cwrs, Feeder Main, Service Cwrs, Staff Quarter And Electrical And Mechanical Work Etc At Indra-Tipri Pumping Water Supply Scheme . Submission Date for this Tender is 10-05-2022. Rising Mains Tenders in uttarkashi Uttarakhand. Bidders can get complete Tender details and download the document.




Tender Notice

31943917
Construction Of Intake Well, Wtp, Rising Main, Pump House, Sump Cum Tank , Distribution System, Cwrs, Feeder Main, Service Cwrs, Staff Quarter And Electrical And Mechanical Work Etc At Indra-Tipri Pumping Water Supply Scheme
Open Tender
Indian
Uttarakhand
uttarkashi
10-05-2022

Tender Details

Construction Of Intake Well, Wtp, Rising Main, Pump House, Sump Cum Tank , Distribution System, Cwrs, Feeder Main, Service Cwrs, Staff Quarter And Electrical And Mechanical Work Etc At Indra-Tipri Pumping Water Supply Scheme

Key Value

Document Fees
INR 9440 /-
EMD
INR 1127000.0 /-
Tender Value
INR 5.39 Crore /-

BOQ Items

Name of Work: Construction of Intake well, WTP, Rising Main, Pump House, Sump cum tank , Distribution System, CWRs, Feeder Main, Service CWRs, Staff Quarter and Electrical & Mechanical Work etc at Indra-Tipri Pumping Water Supply Scheme
Sl. No. Item Description
1Rates for Construction of Intake well, WTP, Rising Main, Pump House, Sump cum tank , Distribution System, CWRs, Feeder Main, Service CWRs, Staff Quarter and Electrical & Mechanical Work etc at Indra-Tipri Pumping Water Supply Scheme
2Construction of IntakeWell ,Check Dam, site development, protectionwork , drawing & design including supply of all materials, labour, carting, T&P etc. complete. As per direction of Engineer in charge.
3Construction of Rapid sand filter, flocculator tank, pre and post settling tank,Alum cum dosing mixing chamber, intake chamber, 3 KL back washtank and required protection work, drawing & design. including supply of all materials, labour, carting, T&P etc. complete. As per direction of Engineer in charge.
4Providing of all materials, Carting from site store to site of work, Lowering into trenches with true to alignment, Laying of MS ERW Pipes grade Yst 210, Jointing by electric welding process with proper grade of eletrodes suitable for jointing of water supply pipe lines (Ador, L&T or equivalent electrodes) by cutting of pipes and making required bends by welding, completion of work with testing of pipe line etc complete. 1) From SUMP to MPS MSERW Pipe 65 mm Dia 4.00mm Thickness
5From MPS to IPS MSERW Pipe 65 mm Dia 4.0 mm Thickness
6From IPS to TOP CWR. MSERW Pipe 65 mm Dia 5.2 mm Thickness
7Excavation of earth for pipeline in following strata lift upto 1.5 m lead upto 30 m including refilling, watering, ramming of excavated earth into the trenches and removal of surplus earth upto a distance of 60 m from trenches including supply of labour, T & P etc.all complete assumingthat 90% pipe line is laid in trenches, it is estimated that 75% excavation will be in soilmixed with shingle, bajari and boulders and rest 25% will be in medium rock Soil mixed with boulder (SMB)
8Medium Rock (MR)
9Supply & fixing of following sizes of valves including carting the same up to side of work and fixing the same in water supply lines including cost of valves, specials, labour and T&P complete in all respect Sluice Valve 65 mm dia
10C.I. Air valve (Double Acting) 80mm
11Supply of all materials, labour, T & P etc. and Construction of size Sluice Valve / Reflux Valve / Scour Valve Chamber as per type design complete(1.2x1.2x1.2)
12Supply of all materials, labour, T & P etc. and Construction of size Air Valve Chamber as per type design complete(1.2x1.2x1.2) 50 mm
13Supply of all materials, labour, T&P etc. and construction of 1.2 m x 1.2 m x 1.0 m size Bulk Water Meter Chamber with FPS bricks
14Supply of all materials, labour, T & P etc. and Construction ofR.C.C Anchor Block @ 40 m interval as per type design complete
15Makig2 M wide Briddle path forrising main including hill side cutting and coolie walling of all materials, labour, T & P etc.
16Painting of MS ERW/API Pipes with 2 coats of approved quality. (Anti-Corrosive paint over one coat of Primer) (Dia of pipe in mm) 65 mm dia
17Protection Work as per actual Excavation for foundation in Soil mixed with boulders
18RR Dry including supply of all materials, labour, T&P etc. complete
19Supply of all materials, labour and T & P etc. and construction of R.C.C. Sump / Clear Water Reservoir of following Capacity in K.L.(40.0 KL Capacity-2 No. and 160 KL Capacity-1No.) ,protection workincluding design, drawing .fixing of pipes and fittings including cartage of materials etc. complete
20Providing of all materials,Carting from site store to site of work,Laying & jointing of GI (M) screwed pipes(including supply of all jointing materials, white lead, hemp and oil etc) in trenches withits cutting, threading and testing of pipe line etc complete. G I PIPE(M) 25 mm dia
2132mm dia
2240mm dia
23Excavation of earth for pipeline in following strata lift upto 1.5 m lead upto 30 m including refilling, watering, ramming of excavated earth into the trenches and removal of surplus earth upto a distance of 60 m from trenches including supply of labour, T & P etc.all complete assumingthat 90% pipe line is laid in trenches, it is estimated that 75% excavation will be in soilmixed with shingle, bajari and boulders and rest 25% will be in medium rock Soil mixed with Bolder (SMB)
24Medium Rock (MR)
25Supply and fixing of the following fittings including cartage of materials, labour, T&P etc. complete Gate/Wheel Valve ( Brass )/G.M.Valve 25 mm dia
2632 mm dia
2740 mm dia
2865 mm dia
29Supply of all materials, labour, T&P etc. and construction of0.6 m x 0.6 m x 0.6 m size Gate Valve chamber with FPS bricks
30Supply of all materials, labour and T & P etc. and construction ofB P Tas per type design and drawing including fixing of pipes and fittings including cartage of materials etc. complete
31Protection Work as per actual Excavation for foundation in Soil mixed with boulders
32RR Stone Masonry 1:6 including supply of all materials, labour, T&P etc. complete
33RR Dry including supply of all materials, labour, T&P etc. complete
34Supply of all materials, labour and T & P etc. and construction of03 Pump Houseas per type design and drawing
35Supply of all materials, labour and T & P etc. and construction of02 Staff quarter for Chaukidar as per type design and drawing
36Provision of 1.5 m high Boundary Wall in brick masonry for SUMP, MPS, IPS and TOP CWR including supply of all materials, labour, carting T&P etc. complete
37Provision of Barbed Wire Fencing through angle iron posts around the water works sitefor SUMP, MPS, IPS and TOP CWR including supply of all materials, labour, carting T&P etc. complete
38Provision of Iron Gate with Pillars of following sizes complete 3.6 m wide
39Provision of Drainage System consisting of following works Manhole chambers
40Supply & laying of drainage 250 mm dia. RCC NP2 pipe
41Supply of all materials and construct 150 mm S.C. drain including supply of all labour T&P etc complete
42Cartage of Materials of pipe for Rising Main/Gravity main inclusive all as per the direction of E&I Raising main
43Supply Main
44Expenditure on Trial & Testing for 6 month. (Excluding Machinery work ,Maintenance staff)
45Provision for the payment to PWD for road cutting & reinstatement charges.(B.M/SDBC road)
46Pumping plant for I-Well to MPS 02 No. Pump motor set ( 220 lpm, 100 meter head, 10 HP ) suitable for handling Raw water.Including piping &Sluice valves (As per site requir.), Chain pulley Block (2 Ton capacity, gauges, main switch, Power Wiring & Earthing material etc complete
47Pumping plant for MPS to IPS 02 No. Pump motor set ( 200 lpm, 460 meter head, 40 HP ) suitable for handling clear water Complete in all respect ( incl. pump , motor, Base frame, coupling, coupling guard & other accessories )
48Pumping plant for IPS to Top CWR Pump motor02 No. set (200 lpm, 730 meter head, 75 HP ) suitable for handling clear water Complete in all respect ( incl. pump , motor, Base frame, coupling, coupling guard & other accessories )
49Supply and Fixing of Transformer including site development as per direction of engineer in charge. Transformer 25 KVA
50Transformer 63 KVA
51Transformer 100 KVA
52Supply, Fixing and Laying of Transmission line @ 2 Km 3 phase 11 KV line HT including adjustment of poles, safety measures as per the direction of E&I
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail